INDOT contract B-42442-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on July 8, 2026, Lake, LaPorte. 4 bids received; low bid $8,117,156 by Dunnet Bay Construction Company.
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 107
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dunnet Bay Construction Company | $8,117,156 | Low |
| 2 | F H Paschen S N Nielsen & Associates LLC | $8,262,151 | +2.0% |
| 3 | Rieth-Riley Construction Co., Inc. | $8,322,364 | +3.0% |
| 4 | Superior Construction Co Inc | $8,996,387 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dunnet Bay Construction Company | 2. F H Paschen S N Nielsen & Associates LLC | 3. Rieth-Riley Construction Co., Inc. | 4. Superior Construction Co Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $425,000 | $350,000 | $65,900 | $750,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $390,416 | $500,000 | $496,000 | $453,000 |
| 0010 | Clearing and grubbing (201-06587) | ACRE | 2 | $13,000 | $7,602.99 | $13,600 | $22,500 |
| 0011 | Pavement removal (202-02240) | SYS | 257 | $26.00 | $52.40 | $40.00 | $45.82 |
| 0012 | Curb and gutter, remove (202-02279) | LFT | 267 | $11.00 | $12.09 | $9.00 | $17.00 |
| 0013 | Regulated materials, dispose, type Z (202-09243) | CYS | 5 | $1,960.00 | $347.11 | $750.00 | $62.00 |
| 0014 | Regulated materials, remove, type Z (202-09244) | CYS | 5 | $335.00 | $1,657.35 | $590.00 | $1,380.00 |
| 0015 | Regulated materials, transport, type Z (202-09245) | CYS | 5 | $1,223.00 | $689.34 | $428.00 | $230.00 |
| 0016 | Present structure, remove, structure no. , (6)51-45-01943 B (202-51330) | LS | 1 | $775,000 | $697,761 | $616,000 | $900,000 |
| 0017 | Sidewalk concrete, remove (202-52710) | SYS | 51 | $22.00 | $37.66 | $32.00 | $65.00 |
| 0018 | Guardrail end treatment, remove (202-93741) | EACH | 4 | $250.00 | $250.00 | $250.00 | $250.00 |
| 0019 | Apron, remove (202-94425) | SYS | 466 | $13.00 | $20.81 | $60.00 | $0.01 |
| 0020 | Excavation, common (203-02000) | CYS | 995 | $40.00 | $49.22 | $41.00 | $85.00 |
| 0021 | Excavation, waterway (203-51223) | CYS | 5,095 | $33.00 | $35.53 | $26.00 | $0.01 |
| 0022 | Stormwater management budget (205-12108) | DOL | 43,200 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0023 | Stormwater management implementation (205-12616) | LS | 1 | $80,000 | $1.00 | $15,000 | $30,000 |
| 0024 | SWQCP preparation (205-12618) | LS | 1 | $1,800.00 | $2,350.00 | $1,800.00 | $1,800.00 |
| 0025 | Subgrade treatment, type II (207-08264) | SYS | 932 | $25.00 | $27.63 | $25.00 | $30.00 |
| 0026 | Subgrade treatment, type IC (207-09935) | SYS | 2,201 | $38.00 | $40.78 | $35.00 | $40.00 |
| 0027 | Flowable backfill, non- removable (213-09269) | CYS | 22 | $815.00 | $368.20 | $390.00 | $230.00 |
| 0028 | Geogrid, type IB (214-11796) | SYS | 805 | $3.00 | $3.62 | $3.00 | $8.00 |
| 0029 | Geotextile for pavement, type 2B (214-12239) | SYS | 276 | $6.00 | $7.68 | $8.00 | $9.00 |
| 0030 | Compacted aggregate, no. 53 (301-12234) | CYS | 301 | $70.00 | $89.68 | $80.00 | $120.00 |
| 0031 | Subbase for PCCP (302-06464) | CYS | 69 | $130.00 | $165.55 | $110.00 | $120.00 |
| 0032 | Compacted aggregate, no. 53 (303-01180) | TON | 35 | $110.00 | $89.86 | $65.00 | $98.00 |
| 0033 | Compacted aggregate, no. 53, temporary for driveways (303-08210) | TON | 6.70 | $220.00 | $303.10 | $185.00 | $100.00 |
| 0034 | Milling, asphalt, 2 in. (306-08036) | SYS | 776 | $21.00 | $5.78 | $22.00 | $8.00 |
| 0035 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 273 | $139.50 | $139.50 | $139.50 | $139.50 |
| 0036 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 240 | $136.00 | $136.00 | $136.00 | $136.00 |
| 0037 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 1,042 | $105.00 | $105.00 | $105.00 | $105.00 |
| 0038 | Joint adhesive (401-11526) | LFT | 2,623 | $1.85 | $1.85 | $1.85 | $1.85 |
| 0039 | Asphalt for tack coat (406-05521) | SYS | 8,586 | $0.75 | $0.75 | $0.75 | $0.75 |
| 0040 | Terminal joint, type HMA (503-12477) | LFT | 88 | $400.00 | $387.91 | $450.00 | $450.00 |
| 0041 | Guardrail transition, type TGB (601-01522) | EACH | 4 | $2,900.00 | $2,900.00 | $2,900.00 | $2,900.00 |
| 0042 | Guardrail terminal system, W-beam, curved, type 2 (601-01701) | EACH | 1 | $2,960.00 | $2,960.00 | $2,960.00 | $2,960.00 |
| 0043 | Guardrail, remove (601-02241) | LFT | 432 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0044 | Hand dig guardrail post holes (601-09238) | EACH | 2 | $106.00 | $106.00 | $106.00 | $106.00 |
| 0045 | Guardrail end treatment, type OS , SKT 350 (601-94689) | EACH | 3 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0046 | Sidewalk, concrete (604-06070) | SYS | 50 | $115.00 | $137.79 | $120.00 | $155.00 |
| 0047 | Curb ramp, concrete (604-08086) | SYS | 7 | $330.00 | $193.87 | $377.00 | $330.00 |
| 0048 | Detectable warning surfaces (604-12083) | SYS | 3 | $100.00 | $878.81 | $196.00 | $175.00 |
| 0049 | Curb and gutter, concrete (605-06140) | LFT | 303 | $70.00 | $74.54 | $65.00 | $55.00 |
| 0050 | Milled HMA corrugations, conventional (606-12399) | LFT | 508 | $1.22 | $1.22 | $3.00 | $1.22 |
| 0051 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 211 | $130.00 | $168.40 | $200.00 | $250.00 |
| 0052 | HMA for approaches, type B (610-07487) | TON | 443 | $123.25 | $152.22 | $123.50 | $123.25 |
| 0053 | PCCP for approaches, 6 in. (610-08446) | SYS | 127 | $120.00 | $140.45 | $113.50 | $124.00 |
| 0054 | Mailbox assembly, single (611-06497) | EACH | 2 | $296.00 | $296.00 | $296.00 | $296.00 |
| 0055 | Right-of-way marker (615-06490) | EACH | 11 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0056 | Monument, type B (615-06505) | EACH | 3 | $892.00 | $892.00 | $892.00 | $892.00 |
| 0057 | Monument, type D (615-06515) | EACH | 1 | $339.00 | $339.00 | $339.00 | $339.00 |
| 0058 | Riprap, class 1 (616-05688) | TON | 1,332 | $140.00 | $112.53 | $125.00 | $150.00 |
| 0059 | Riprap, revetment (616-06405) | TON | 37 | $150.00 | $170.43 | $180.00 | $163.00 |
| 0060 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,380 | $3.00 | $3.66 | $5.00 | $5.00 |
| 0061 | Inspection hole (616-93772) | EACH | 2 | $500.00 | $1,675.38 | $250.00 | $850.00 |
| 0062 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $650.00 | $1,000.00 | $500.00 | $650.00 |
| 0063 | Mulched seeding, type R (621-06559) | SYS | 1,269 | $2.02 | $1.35 | $1.35 | $2.02 |
| 0064 | Mulching material (621-06565) | TON | 4 | $645.00 | $550.00 | $550.00 | $645.00 |
| 0065 | Water (621-06567) | KGAL | 5 | $10.00 | $100.00 | $100.00 | $10.00 |
| 0066 | Seed mixture, emergent wetland (621-06737) | LBS | 23 | $258.00 | $75.00 | $75.00 | $258.00 |
| 0067 | Seed mixture, floodplain (621-12612) | LBS | 6 | $385.00 | $440.00 | $440.00 | $385.00 |
| 0068 | Sign, 'DO not spray' (621-52448) | EACH | 3 | $125.00 | $140.00 | $140.00 | $125.00 |
| 0069 | Plant, deciduous tree, single stem, 1.25 in. to 2 in. (622-05649) | EACH | 5 | $995.00 | $620.00 | $620.00 | $995.00 |
| 0070 | Field office, type C (628-09403) | MOS | 18 | $2,100.00 | $2,412.36 | $2,800.00 | $2,200.00 |
| 0071 | Computer system equipment (628-11976) | EACH | 2 | $270.00 | $875.37 | $750.00 | $500.00 |
| 0072 | Topsoil processing and distribution (629-000149) | SYS | 9,478 | $7.50 | $8.25 | $8.00 | $6.00 |
| 0073 | Topsoil amendment budget (629-000150) | DOL | 18,956 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0074 | Pile, steel pipe, epoxy coated, 0.5IN., diameter 16 in. (701-000088) | LFT | 1,163 | $155.00 | $250.00 | $198.00 | $155.00 |
| 0075 | Dynamic pile load test (701-06011) | EACH | 8 | $6,708.76 | $1,465.68 | $7,500.00 | $4,500.00 |
| 0076 | Test pile, dynamic, production (701-09557) | LFT | 851 | $150.00 | $166.19 | $145.00 | $135.00 |
| 0077 | Test pile, dynamic, restrike (701-09559) | EACH | 8 | $10,219 | $1,489.82 | $5,000.00 | $3,500.00 |
| 0078 | Pile, steel pipe, 0.5 in., diameter 16 in. (701-11344) | LFT | 13,051 | $136.00 | $121.21 | $142.00 | $130.00 |
| 0079 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 21 | $1,500.00 | $1,307.10 | $2,100.00 | $2,500.00 |
| 0080 | Concrete, A, substructure (702-51005) | CYS | 39.30 | $1,300.00 | $2,152.20 | $1,900.00 | $2,000.00 |
| 0081 | Reinforcing bars, epoxy coated (703-06029) | LBS | 471,664 | $1.50 | $1.37 | $1.75 | $1.50 |
| 0082 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 47 | $103.00 | $64.32 | $54.00 | $45.00 |
| 0083 | Concrete, C, superstructure (704-51002) | CYS | 1,623.40 | $1,210.00 | $1,350.00 | $1,507.00 | $1,350.00 |
| 0084 | Railing, concrete type FT (706-11601) | CYS | 122.40 | $670.00 | $684.75 | $657.00 | $657.00 |
| 0085 | Concrete bridge railing transition, type TFT (706-11621) | EACH | 4 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0086 | Surface seal , (6)51-45- 10466 (709-51821) | LS | 1 | $1.00 | $11,200 | $1.00 | $0.01 |
| 0087 | Pipe extension, circular, diameter 6 in. , PVC (715-06566) | LFT | 32 | $35.00 | $124.10 | $175.00 | $450.00 |
| 0088 | Casting, inlet, adjust to grade (720-12797) | EACH | 2 | $750.00 | $1,846.13 | $2,000.00 | $1,000.00 |
| 0089 | Longitudinal grooving (722-12732) | SYS | 2,229 | $4.00 | $4.50 | $3.50 | $4.43 |
| 0090 | Bridge expansion joint, type SS (724-12771) | LFT | 142 | $330.00 | $395.86 | $415.00 | $500.00 |
| 0091 | Road closure sign assembly (801-04308) | EACH | 6 | $252.00 | $252.00 | $252.00 | $252.00 |
| 0092 | Temporary transverse pavement marking, removable, 6 in. (801-06217) | LFT | 29 | $2.88 | $2.88 | $2.88 | $2.88 |
| 0093 | Detour route marker assembly (801-06625) | EACH | 49 | $158.00 | $158.00 | $158.00 | $158.00 |
| 0094 | Construction sign, type A (801-06640) | EACH | 11 | $219.00 | $219.00 | $219.00 | $219.00 |
| 0095 | Construction sign, type B (801-06645) | EACH | 29 | $109.00 | $109.00 | $109.00 | $109.00 |
| 0096 | Maintaining traffic (801-06775) | LS | 1 | $40,000 | $250,000 | $10,000 | $389,039 |
| 0097 | Barricade, type III-A (801-07118) | LFT | 90 | $16.01 | $16.01 | $16.01 | $16.01 |
| 0098 | Barricade, type III-B (801-07119) | LFT | 122 | $16.01 | $16.01 | $16.01 | $16.01 |
| 0099 | Temporary curb ramp (801-11990) | EACH | 1 | $9,392.07 | $6,648.58 | $1,200.00 | $5,290.00 |
| 0100 | Temporary pedestrian channelizer (801-12862) | LFT | 238 | $49.55 | $49.55 | $49.55 | $21.39 |
| 0101 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 72 | $13.82 | $13.82 | $13.82 | $13.82 |
| 0102 | Pavement message marking , DO not enter (808-06609) | EACH | 10 | $388.00 | $388.00 | $388.00 | $388.00 |
| 0103 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 2,021 | $0.94 | $0.94 | $0.94 | $0.94 |
| 0104 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 1,974 | $0.94 | $0.94 | $0.94 | $0.94 |
| 0105 | Grooving for pavement markings (808-12032) | LFT | 1,708 | $0.68 | $0.68 | $0.68 | $0.68 |
| 0106 | Snowplowable raised pavement marker (808-75998) | EACH | 14 | $122.00 | $122.00 | $122.00 | $122.00 |
| 0107 | Dense graded subbase (302-07455) | CYS | 22 | $120.00 | $206.64 | $110.00 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.