Dunnet Bay Construction Company: INDOT bid record
Dunnet Bay Construction Company submitted 76 bids on Indiana DOT contracts in the data, from 09 FEB 2022 to 05 NOV 2026, and was the low bidder on 19 of them (25%). When it was not low, its total sat a median +12% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $53,505,227
- Latest bid
- 05 NOV 2026
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 10 | 4 | 40% |
| 2023 | 14 | 6 | 43% |
| 2024 | 23 | 4 | 17% |
| 2025 | 12 | 4 | 33% |
| 2026 | 17 | 1 | 6% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 75 | 75 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 75 | 75 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 75 | 75 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 69 | 69 (100%) | $1.00 | $1.00 |
| Stormwater management budget | 205-12108 | DOL | 63 | 63 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 63 | 63 (100%) | $1.00 | $1.00 |
| Quality adjustments, HMA | 109-08440 | DOL | 58 | 58 (100%) | $1.00 | $1.00 |
| Road closure sign assembly | 801-04308 | EACH | 62 | 55 (89%) | $252.50 | $280.00 |
| Construction sign, type A | 801-06640 | EACH | 61 | 54 (89%) | $201.00 | $200.00 |
| Detour route marker assembly | 801-06625 | EACH | 62 | 52 (84%) | $151.50 | $140.00 |
| Barricade, type III-A | 801-07118 | LFT | 55 | 48 (87%) | $15.43 | $16.00 |
| Payment adjustment, PG asphalt binder | 109-09489 | DOL | 48 | 48 (100%) | $1.00 | $1.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Rieth-Riley Construction Co., Inc. | 72 | 29 of 72 |
| Milestone Contractors LP | 41 | 10 of 41 |
| F H Paschen S N Nielsen & Associates LLC | 39 | 12 of 39 |
| Superior Construction Co Inc | 28 | 16 of 28 |
| Ellas Construction Company Inc | 25 | 15 of 25 |
| Laporte Construction Company Inc | 16 | 5 of 16 |
| Gariup Construction Co Inc | 15 | 1 of 15 |
| Milestone Contractors North Inc | 7 | 2 of 7 |
| Ram Construction SRVCS of Michigan Inc | 7 | 5 of 7 |
| Icc Group Inc | 6 | 3 of 6 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 NOV 2026 | B-43912-A | LaPorte | BRIDGE THIN DECK OVERLAY | 3 of 4 | $123,960 | +43% |
| 05 NOV 2026 | B-45648-A | LaPorte | BRIDGE THIN DECK OVERLAY | 3 of 4 | $477,779 | +12% |
| 07 OCT 2026 | B-43353-A | LaPorte | BRIDGE DECK OVERLAY | 5 of 6 | $1,266,860 | +38% |
| 02 SEP 2026 | B-44107-A | LaPorte | BRIDGE REPLACEMENT | 2 of 6 | $1,483,109 | +5.0% |
| 02 SEP 2026 | B-44108-A | LaPorte | BRIDGE REPLACEMENT | 4 of 7 | $1,799,467 | +9.0% |
| 08 JUL 2026 | B-42442-A | LaPorte | BRIDGE REPLACEMENT | 1 of 4 | $8,117,156 | Low, 2.0% under the second |
| 07 MAY 2026 | R-43927-A | LaPorte | SMALL STRUCTURE REPLACEMENT | 2 of 4 | $408,932 | +3.0% |
| 07 MAY 2026 | B-43355-A | LaPorte | BRIDGE DECK OVERLAY | 3 of 4 | $2,024,865 | +9.0% |
| 08 APR 2026 | B-44005-A | LaPorte | BRIDGE REPLACEMENT | 4 of 4 | $1,912,573 | +18% |
| 08 APR 2026 | B-45593-A | LaPorte | BRIDGE THIN DECK OVERLAY | 3 of 4 | $1,057,497 | +26% |
| 11 MAR 2026 | B-43873-A | LaPorte | BRIDGE DECK OVERLAY AND SMALL STRUCTURE REPLACEMENT | 3 of 4 | $2,593,991 | +8.0% |
| 11 MAR 2026 | B-44198-A | LaPorte | BRIDGE DECK OVERLAY | 3 of 3 | $4,479,418 | +6.0% |
| 11 MAR 2026 | B-44666-A | LaPorte | BRIDGE DECK OVERLAY | 2 of 6 | $536,698 | +23% |
| 11 FEB 2026 | B-43916-A | LaPorte | REPLACE SUPERSTRUCTURE | 3 of 7 | $2,131,086 | +23% |
| 11 FEB 2026 | B-45595-A | LaPorte | BRIDGE THIN DECK OVERLAY | 3 of 4 | $300,646 | +28% |
| 11 FEB 2026 | B-46167-A | LaPorte | BRIDGE DECK OVERLAY | 3 of 3 | $6,759,996 | +23% |
| 14 JAN 2026 | B-44098-A | LaPorte | REPLACE SUPERSTRUCTURE | 3 of 6 | $1,320,694 | +18% |
| 10 DEC 2025 | B-42436-A | LaPorte | BRIDGE REPLACEMENT | 5 of 7 | $4,783,156 | +14% |
| 10 DEC 2025 | B-43906-A | LaPorte | BRIDGE DECK OVERLAY AND BRIDGE THIN DECK OVERLAY | 1 of 4 | $945,694 | Low, 11% under the second |
| 10 DEC 2025 | B-43917-A | LaPorte | REPLACE SUPERSTRUCTURE, BRIDGE DECK OVERLAY AND PIPE LINING | 4 of 5 | $11,173,635 | +15% |
| 08 OCT 2025 | B-43876-A | LaPorte | BRIDGE DECK OVERLAY, SMALL STRUCTURES AND DRAINS CONSTR | 4 of 5 | $1,319,327 | +16% |
| 08 OCT 2025 | B-43921-A | LaPorte | BRIDGE DECK REPLACEMENT | 4 of 5 | $2,780,697 | +20% |
| 07 MAY 2025 | B-41850-A | LaPorte | NEW BRIDGE CONSTRUCTION AND GRADE SEPARATION | 2 of 4 | $17,522,354 | 0.0% |
| 07 MAY 2025 | B-43636-A | LaPorte | BRIDGE AND ROAD REPLACEMENT | 2 of 5 | $13,889,041 | +14% |
| 07 MAY 2025 | B-44263-A | LaPorte | BRIDGE REHABILITATION OR REPAIR AND NEW BRIDGE | 2 of 3 | $6,065,570 | +5.0% |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.