INDOT contract B-43906-A bid tabulation
BRIDGE DECK OVERLAY AND BRIDGE THIN DECK OVERLAY. Let by Indiana DOT on December 10, 2025, Laporte, Starke, LaPorte. 4 bids received; low bid $945,694 by Dunnet Bay Construction Company.
- Owner
- Indiana DOT
- Letting
- 10 DEC 2025
- Pay items
- 82
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dunnet Bay Construction Company | $945,694 | Low |
| 2 | Milestone Contractors LP | $1,047,856 | +11% |
| 3 | Rieth-Riley Construction Co., Inc. | $1,072,139 | +13% |
| 4 | Laporte Construction Company Inc | $1,599,253 | +69% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dunnet Bay Construction Company | 2. Milestone Contractors LP | 3. Rieth-Riley Construction Co., Inc. | 4. Laporte Construction Company Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $50,000 | $10,000 | $6,700.00 | $10,163 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $48,000 | $57,000 | $65,000 | $70,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $18,769 | $20,000 | $35,000 | $30,000 |
| 0012 | Pavement removal (202-02240) | SYS | 480 | $0.01 | $38.00 | $25.00 | $10.00 |
| 0013 | Contaminated soil, remove (202-06580) | CYS | 59 | $204.00 | $125.00 | $1.00 | $672.18 |
| 0014 | Regulated materials, dispose, type Y (202-07555) | CYS | 59 | $77.00 | $131.00 | $1.00 | $1,070.00 |
| 0015 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $10,000 | $15,000 | $10,000 | $277,873 |
| 0016 | Bridge railing, remove (202-62420) | LFT | 81 | $22.00 | $39.00 | $80.00 | $190.77 |
| 0017 | Testing for contaminated material , sediment testing, 10 working days (202-92222) | EACH | 3 | $1,200.00 | $4,100.00 | $1,500.00 | $5,000.00 |
| 0018 | Guardrail end treatment, remove (202-93741) | EACH | 1 | $503.00 | $503.00 | $503.00 | $503.00 |
| 0019 | Excavation, common (203-02000) | CYS | 60 | $150.00 | $60.00 | $200.00 | $75.14 |
| 0020 | Linear grading (203-08607) | LFT | 491 | $12.00 | $4.00 | $4.00 | $26.38 |
| 0021 | Stormwater management budget (205-12108) | DOL | 3,900 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0022 | Stormwater management implementation (205-12616) | LS | 1 | $15,000 | $4,000.00 | $46,704 | $39,370 |
| 0023 | Excavation, wet (206-51220) | CYS | 59 | $230.00 | $500.00 | $1.00 | $174.51 |
| 0024 | Cofferdam (206-51235) | LS | 1 | $165,000 | $102,500 | $176,000 | $203,053 |
| 0025 | Subgrade treatment, type IC (207-09935) | SYS | 515 | $45.00 | $60.00 | $70.00 | $72.20 |
| 0026 | B borrow (211-02050) | CYS | 74 | $100.00 | $18.00 | $1.00 | $214.92 |
| 0027 | Geotextile for pavement, type 2B (214-12239) | SYS | 475 | $3.00 | $7.00 | $5.00 | $4.15 |
| 0028 | Subbase for PCCP (302-06464) | CYS | 38.20 | $145.00 | $200.00 | $250.00 | $125.60 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 65 | $50.00 | $90.00 | $120.00 | $123.92 |
| 0030 | Milling, transition (306-08043) | SYS | 800 | $3.00 | $4.00 | $8.00 | $5.34 |
| 0031 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 100 | $205.00 | $215.00 | $201.00 | $201.00 |
| 0032 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 45 | $203.00 | $710.00 | $204.65 | $204.65 |
| 0033 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 190 | $125.00 | $190.00 | $123.25 | $123.25 |
| 0034 | Joint adhesive (401-11526) | LFT | 180 | $2.50 | $4.00 | $6.00 | $6.00 |
| 0035 | Asphalt for tack coat (406-05521) | SYS | 1,845 | $0.25 | $1.00 | $0.85 | $0.85 |
| 0036 | Terminal joint, type HMA (503-12477) | LFT | 80 | $425.00 | $500.00 | $320.00 | $437.31 |
| 0037 | Rcba crack filling, PCC sealer/healer (507-12941) | LFT | 120 | $50.00 | $7.50 | $22.00 | $22.00 |
| 0038 | Guardrail, remove (601-02241) | LFT | 491 | $3.00 | $3.00 | $3.00 | $3.00 |
| 0039 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 188 | $22.00 | $22.00 | $22.00 | $22.00 |
| 0040 | Guardrail height transition, MGS (601-12289) | EACH | 3 | $950.00 | $950.00 | $950.00 | $950.00 |
| 0041 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,201.00 | $3,201.00 | $3,201.00 | $3,201.00 |
| 0042 | Guardrail end treatment, type OS (601-94689) | EACH | 1 | $2,900.00 | $2,900.00 | $2,900.00 | $2,900.00 |
| 0044 | Riprap, revetment (616-06405) | TON | 87 | $200.00 | $125.00 | $150.00 | $186.41 |
| 0045 | Geotextile for riprap, type 1A (616-12246) | SYS | 127 | $8.00 | $4.00 | $6.00 | $14.79 |
| 0046 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $400.00 | $400.00 | $400.00 | $400.00 |
| 0047 | Mulched seeding, type R (621-06559) | SYS | 680 | $2.50 | $2.50 | $2.50 | $2.50 |
| 0048 | Sodding (621-06574) | SYS | 58 | $36.50 | $36.50 | $36.50 | $36.50 |
| 0049 | Sign, 'DO not disturb' (622-98200) | EACH | 8 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0050 | Field office, type C (628-09403) | MOS | 6 | $3,000.00 | $3,000.00 | $2,500.00 | $5,119.33 |
| 0051 | Computer system equipment (628-11976) | EACH | 3 | $100.00 | $750.00 | $25.00 | $750.00 |
| 0052 | Clean and epoxy coat existing piles (701-93790) | LS | 1 | $31,000 | $85,000 | $57,000 | $54,000 |
| 0053 | Reinforcing bars, epoxy coated (703-06029) | LBS | 14,778 | $2.00 | $1.80 | $4.00 | $1.62 |
| 0054 | Inertial profiler, bridge encounter (704-000080) | LS | 1 | $4,960.00 | $4,960.00 | $4,960.00 | $4,960.00 |
| 0055 | Corrective grinding, bridge encounter (704-000082) | LS | 1 | $29,300 | $33,000 | $36,504 | $29,300 |
| 0056 | Concrete, C, superstructure (704-51002) | CYS | 2.20 | $2,700.00 | $6,300.00 | $4,500.00 | $3,697.81 |
| 0057 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $8,000.00 | $4,500.00 | $6,500.00 | $3,982.21 |
| 0058 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $4,900.00 | $4,265.53 | $4,062.00 | $4,062.00 |
| 0059 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $3,700.00 | $2,338.43 | $2,658.00 | $2,658.00 |
| 0060 | Hydrodemolition (722-01066) | SYS | 920 | $60.00 | $90.00 | $65.00 | $89.82 |
| 0061 | Bridge deck overlay budget (722-12380) | DOL | 6,900 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0063 | Bridge deck, remove concrete surface (722-12464) | SYS | 920 | $5.00 | $6.00 | $7.00 | $8.73 |
| 0064 | Longitudinal grooving (722-12732) | SYS | 1,110 | $7.00 | $6.37 | $8.00 | $9.92 |
| 0065 | Bridge deck patching, full depth (722-51401) | SFT | 415 | $1.00 | $10.00 | $1.00 | $55.00 |
| 0066 | Bridge deck overlay, latex modified (722-51842) | SYS | 920 | $65.00 | $120.00 | $110.00 | $187.40 |
| 0067 | Bridge deck patching, partial depth (722-51852) | SFT | 100 | $0.01 | $2.50 | $5.00 | $5.00 |
| 0068 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 190 | $80.00 | $94.10 | $110.00 | $85.00 |
| 0069 | Construction sign, type C (801-03290) | EACH | 2 | $220.00 | $220.00 | $220.00 | $190.00 |
| 0070 | Road closure sign assembly (801-04308) | EACH | 14 | $242.00 | $242.00 | $218.00 | $325.00 |
| 0071 | Detour route marker assembly (801-06625) | EACH | 58 | $141.00 | $141.00 | $135.00 | $135.00 |
| 0072 | Construction sign, type A (801-06640) | EACH | 27 | $175.00 | $175.00 | $175.00 | $190.00 |
| 0073 | Construction sign, type B (801-06645) | EACH | 2 | $105.00 | $105.00 | $105.00 | $100.00 |
| 0074 | Maintaining traffic (801-06775) | LS | 1 | $20,000 | $7,400.00 | $20,434 | $18,226 |
| 0075 | Barricade, type III-A (801-07118) | LFT | 114 | $13.85 | $13.85 | $13.85 | $16.00 |
| 0076 | Barricade, type III-B (801-07119) | LFT | 318 | $13.85 | $13.85 | $13.85 | $16.00 |
| 0077 | Sign, sheet, remove (802-04089) | EACH | 4 | $101.00 | $101.00 | $101.00 | $101.00 |
| 0078 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 36 | $40.00 | $40.00 | $40.00 | $40.00 |
| 0079 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 18 | $55.00 | $55.00 | $55.00 | $55.00 |
| 0080 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 171 | $0.53 | $0.53 | $0.53 | $1.20 |
| 0081 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 1,317 | $0.45 | $0.45 | $0.45 | $1.00 |
| 0082 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 580 | $0.45 | $0.45 | $0.45 | $1.00 |
| 0083 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 5 | $20.00 | $101.27 | $102.54 | $50.00 |
| 0084 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 189.60 | $225.00 | $250.00 | $185.00 | $217.84 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.