INDOT contract B-43636-A bid tabulation
BRIDGE AND ROAD REPLACEMENT. Let by Indiana DOT on May 7, 2025, Lake, LaPorte. 5 bids received; low bid $12,187,142 by Superior Construction Co Inc.
- Owner
- Indiana DOT
- Letting
- 07 MAY 2025
- Pay items
- 167
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Construction Co Inc | $12,187,142 | Low |
| 2 | Dunnet Bay Construction Company | $13,889,041 | +14% |
| 3 | F H Paschen S N Nielsen & Associates LLC | $13,894,516 | +14% |
| 4 | Rieth-Riley Construction Co., Inc. | $14,518,856 | +19% |
| 5 | Walsh Construction Company II LLC | $17,285,379 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Construction Co Inc | 2. Dunnet Bay Construction Company | 3. F H Paschen S N Nielsen & Associates LLC | 4. Rieth-Riley Construction Co., Inc. | 5. Walsh Construction Company II LLC |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $125,000 | $1,292,536 | $600,000 | $98,000 | $875,903 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $605,000 | $685,000 | $694,725 | $700,000 | $850,000 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $100,000 | $150,000 | $138,000 | $110,000 | $165,000 |
| 0013 | Pavement removal (202-02240) | SYS | 8,520 | $6.30 | $20.50 | $17.59 | $30.00 | $15.00 |
| 0014 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $1,600,000 | $1,250,000 | $700,000 | $700,000 | $725,000 |
| 0015 | Sign, remove (202-74035) | EACH | 12 | $120.00 | $120.00 | $168.16 | $100.00 | $60.00 |
| 0016 | Excavation, common (203-02000) | CYS | 19,180 | $24.50 | $33.50 | $32.12 | $31.00 | $31.43 |
| 0017 | Borrow (203-02070) | CYS | 1,994 | $0.01 | $12.50 | $8.91 | $16.00 | $6.00 |
| 0018 | Stormwater management budget (205-12108) | DOL | 65,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $20,000 | $50,000 | $15,000 | $20,000 | $125,000 |
| 0020 | SWQCP preparation (205-12618) | LS | 1 | $1,900.00 | $2,450.00 | $2,450.00 | $13,750 | $50,000 |
| 0021 | Subgrade treatment, type II (207-08264) | SYS | 275 | $21.00 | $30.50 | $45.66 | $45.00 | $30.00 |
| 0022 | Subgrade treatment, type III (207-08266) | SYS | 1,845 | $7.50 | $7.50 | $5.35 | $7.50 | $10.00 |
| 0023 | Subgrade treatment, type IC (207-09935) | SYS | 12,933 | $30.00 | $33.00 | $31.29 | $39.00 | $35.00 |
| 0024 | B borrow (211-02050) | CYS | 5,196 | $5.00 | $71.50 | $51.45 | $63.00 | $55.00 |
| 0025 | Structure backfill, type 2 (211-09265) | CYS | 603 | $60.00 | $88.00 | $68.41 | $88.00 | $65.00 |
| 0026 | Structure backfill, type 3 (211-09266) | CYS | 10,520 | $65.00 | $71.50 | $73.64 | $66.00 | $56.00 |
| 0027 | Geogrid, type IB (214-11796) | SYS | 275 | $3.25 | $2.10 | $4.70 | $4.50 | $4.14 |
| 0028 | Geotextile for pavement, type 2B (214-12239) | SYS | 12,933 | $4.20 | $2.50 | $3.35 | $3.50 | $4.21 |
| 0029 | Compacted aggregate, no. 8 (301-12233) | CYS | 215 | $100.00 | $136.25 | $96.22 | $100.00 | $95.00 |
| 0030 | Compacted aggregate, no. 53 (301-12234) | CYS | 1,495 | $87.00 | $66.25 | $69.26 | $66.50 | $85.00 |
| 0031 | Subbase for PCCP (302-06464) | CYS | 132 | $90.00 | $145.00 | $146.83 | $105.00 | $130.00 |
| 0032 | Dense graded subbase (302-07455) | CYS | 46 | $142.00 | $100.00 | $148.71 | $105.00 | $250.00 |
| 0033 | Compacted aggregate, no. 53 (303-01180) | TON | 632 | $52.00 | $55.00 | $37.04 | $41.00 | $43.79 |
| 0034 | Widening with HMA, type C (304-07494) | TON | 4 | $650.00 | $1,298.00 | $1,211.80 | $1,211.80 | $880.39 |
| 0035 | Widening with HMA, type D (304-07789) | TON | 94 | $200.00 | $187.00 | $154.10 | $154.10 | $258.11 |
| 0036 | HMA patching, full depth, type C (304-12625) | TON | 22 | $350.00 | $178.00 | $142.40 | $142.40 | $450.00 |
| 0037 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 746 | $3.05 | $5.50 | $5.32 | $10.00 | $12.04 |
| 0038 | Milling, transition (306-08043) | SYS | 744 | $3.25 | $7.00 | $5.33 | $10.00 | $12.04 |
| 0039 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 410 | $150.00 | $125.35 | $125.35 | $125.35 | $150.45 |
| 0040 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 95 | $180.00 | $123.25 | $123.25 | $123.25 | $180.54 |
| 0041 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 593 | $120.00 | $101.75 | $101.75 | $101.75 | $120.36 |
| 0042 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 136 | $145.00 | $113.85 | $113.85 | $113.85 | $145.44 |
| 0043 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 1,943 | $105.00 | $91.40 | $91.40 | $91.40 | $105.32 |
| 0044 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 20 | $160.00 | $154.85 | $154.85 | $154.85 | $160.48 |
| 0045 | QC/QA-HMA, 4, 58E, intermediate, OG, 19.0 MM (401-000067) | TON | 1,111 | $135.00 | $102.20 | $102.20 | $102.20 | $135.41 |
| 0048 | Asphalt for tack coat (406-05520) | TON | 6 | $1,750.00 | $1,345.20 | $1,345.20 | $1,345.20 | $1,755.27 |
| 0049 | Cracks in asphalt pavement, fill (408-12028) | TON | 1 | $2,000.00 | $500.00 | $500.00 | $500.00 | $2,006.02 |
| 0051 | PCCP, 4 in. (502-11543) | SYS | 1,845 | $45.00 | $56.00 | $60.23 | $65.00 | $55.60 |
| 0052 | D-1 contraction joint (503-05240) | LFT | 4,081 | $20.70 | $16.00 | $19.59 | $30.00 | $25.00 |
| 0053 | Jointed reinforced concrete pavement, 12 in. (503-12476) | SYS | 198 | $220.00 | $234.00 | $254.13 | $240.00 | $265.00 |
| 0054 | Terminal joint, type PCCP (503-12478) | LFT | 124 | $300.00 | $222.00 | $252.84 | $325.00 | $326.85 |
| 0055 | Expansion joint with load transfer (503-12479) | LFT | 61 | $37.75 | $24.00 | $70.97 | $50.00 | $45.86 |
| 0056 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,525.25 |
| 0057 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,525.25 |
| 0058 | Guardrail, remove (601-02241) | LFT | 1,906 | $4.50 | $4.50 | $4.50 | $4.50 | $4.55 |
| 0059 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 975 | $21.00 | $21.00 | $21.00 | $21.00 | $21.21 |
| 0060 | Guardrail transition, MGS with curb (601-12291) | EACH | 2 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,030.31 |
| 0061 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,030.30 |
| 0062 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 62.50 | $24.00 | $24.00 | $24.00 | $24.00 | $24.24 |
| 0063 | Barrier delineator (602-06729) | EACH | 42 | $21.88 | $21.88 | $21.88 | $22.00 | $49.76 |
| 0064 | Fence, chain link, 96 in. (603-01932) | LFT | 322 | $65.00 | $65.00 | $65.00 | $65.00 | $65.66 |
| 0065 | Fence, chain link, PVC coated, 48 in. (603-98225) | LFT | 944 | $30.00 | $30.00 | $30.00 | $30.00 | $30.30 |
| 0066 | Curb ramp, concrete (604-08086) | SYS | 40 | $240.00 | $148.00 | $249.34 | $230.00 | $240.72 |
| 0067 | Curb, integral concrete, type B (605-06095) | LFT | 503 | $58.89 | $81.00 | $44.65 | $53.00 | $52.16 |
| 0068 | Curb and gutter, concrete (605-06140) | LFT | 155 | $65.00 | $65.00 | $42.23 | $58.00 | $65.20 |
| 0069 | Curb and gutter, concrete , modified (605-06140) | LFT | 441 | $65.00 | $82.50 | $36.37 | $45.00 | $65.20 |
| 0070 | Curb and gutter, concrete, type B (605-06145) | LFT | 441 | $60.00 | $76.50 | $42.82 | $43.00 | $60.18 |
| 0071 | Center curb, concrete, type B , modified (605-06205) | LFT | 781 | $58.22 | $65.00 | $66.96 | $57.00 | $75.23 |
| 0072 | Gutter, concrete, type A (607-06175) | LFT | 8 | $250.00 | $115.00 | $136.90 | $192.00 | $200.60 |
| 0073 | Paved side ditch, type A (607-06335) | LFT | 71 | $97.91 | $141.50 | $134.60 | $180.00 | $160.48 |
| 0074 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 252 | $141.50 | $163.00 | $155.03 | $195.00 | $165.49 |
| 0075 | PCCP for approaches, 9 in. (610-09108) | SYS | 275 | $80.00 | $98.50 | $151.36 | $95.00 | $135.41 |
| 0076 | Right-of-way marker (615-06490) | EACH | 24 | $200.00 | $250.00 | $200.00 | $200.00 | $202.02 |
| 0077 | Monument, type B (615-06505) | EACH | 11 | $1,150.00 | $1,050.00 | $1,150.00 | $1,150.00 | $1,161.62 |
| 0078 | Benchmark post (615-06530) | EACH | 1 | $805.00 | $950.00 | $900.00 | $1,200.00 | $950.00 |
| 0079 | Riprap, revetment (616-06405) | TON | 315 | $190.00 | $300.00 | $114.03 | $150.00 | $120.00 |
| 0080 | Geotextile for riprap, type 1A (616-12246) | SYS | 525 | $7.00 | $1.50 | $4.64 | $4.00 | $7.00 |
| 0081 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $500.00 | $500.00 | $500.00 | $750.00 | $500.00 |
| 0082 | Seed mixture, native (621-03909) | LBS | 157 | $50.00 | $8.11 | $50.00 | $8.11 | $8.11 |
| 0083 | Topsoil (621-06570) | CYS | 53 | $110.00 | $96.00 | $86.00 | $106.00 | $96.00 |
| 0084 | Sodding (621-06574) | SYS | 491 | $11.00 | $11.00 | $11.00 | $11.00 | $11.00 |
| 0085 | Geocell confinement system for erosion control (621-12947) | SYS | 2,029 | $39.00 | $39.00 | $47.99 | $39.00 | $39.00 |
| 0086 | Computer system equipment (628-11976) | EACH | 5 | $500.00 | $350.00 | $789.74 | $850.00 | $3,000.00 |
| 0087 | Field office, type D (628-12683) | MOS | 16 | $2,900.00 | $3,135.00 | $3,500.00 | $3,450.00 | $5,000.00 |
| 0088 | Plant growth layer (629-12029) | SYS | 12,662 | $9.00 | $4.75 | $4.75 | $13.00 | $4.75 |
| 0089 | Dynamic pile load test (701-06011) | EACH | 3 | $3,110.00 | $7,500.00 | $1,452.44 | $2,500.00 | $4,500.00 |
| 0090 | Pile, sleeves (701-08253) | EACH | 55 | $985.00 | $2,980.00 | $1,628.65 | $2,075.00 | $2,500.00 |
| 0091 | Test pile, dynamic, production (701-09557) | LFT | 197 | $95.90 | $100.00 | $209.57 | $80.00 | $145.00 |
| 0092 | Test pile, dynamic, restrike (701-09559) | EACH | 3 | $3,110.00 | $5,000.00 | $1,874.68 | $4,500.00 | $6,000.00 |
| 0093 | Pile, steel pipe, 0.312 in., diameter 14 in. (701-09663) | LFT | 2,272 | $85.00 | $40.00 | $107.33 | $82.00 | $125.00 |
| 0094 | Prebored hole, diameter 12 in. (701-11714) | LFT | 1,738 | $0.01 | $35.00 | $1.00 | $38.00 | $175.00 |
| 0095 | Automated pile driving data acquisition device (701-12836) | EACH | 1 | $1,500.00 | $83,760 | $7,500.00 | $31,750 | $12,000 |
| 0096 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 2,783 | $86.00 | $39.00 | $78.69 | $83.00 | $110.00 |
| 0097 | Temporary shoring (702-04325) | LS | 1 | $60,000 | $50,000 | $325,000 | $425,000 | $450,000 |
| 0098 | Concrete, A, substructure (702-51005) | CYS | 161.70 | $1,000.00 | $805.00 | $1,064.81 | $990.00 | $1,850.00 |
| 0099 | Concrete, B, footings (702-51015) | CYS | 68.50 | $600.00 | $495.00 | $638.39 | $850.00 | $1,300.00 |
| 0100 | Field drilled hole in concrete (702-51863) | EACH | 810 | $29.40 | $14.00 | $25.72 | $25.00 | $31.90 |
| 0101 | Threaded tie bar assembly (703-01540) | EACH | 62 | $47.40 | $50.00 | $57.71 | $70.00 | $81.05 |
| 0102 | Reinforcing bars (703-06028) | LBS | 29,016 | $1.40 | $1.30 | $1.26 | $1.70 | $1.35 |
| 0103 | Reinforcing bars, epoxy coated (703-06029) | LBS | 165,580 | $1.45 | $1.53 | $1.37 | $1.80 | $1.55 |
| 0104 | Concrete, C, superstructure (704-51002) | CYS | 557.40 | $800.00 | $1.35 | $965.51 | $1,425.00 | $1,750.00 |
| 0105 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 4 | $3,000.00 | $4,700.00 | $4,240.25 | $7,000.00 | $4,500.00 |
| 0106 | Reinforced concrete moment slab, 12 in. (706-08496) | SYS | 1,063 | $185.00 | $188.00 | $224.73 | $265.00 | $250.00 |
| 0107 | Railing, steel type PF-1 (706-11404) | LFT | 1,033 | $89.63 | $74.00 | $74.00 | $110.00 | $74.75 |
| 0108 | Railing, steel type PF-1 , modified (706-11404) | LFT | 616 | $147.94 | $144.00 | $144.00 | $180.00 | $145.45 |
| 0109 | Bridge railing pedestrian fence (706-11455) | LFT | 458 | $158.00 | $158.00 | $158.00 | $205.00 | $159.60 |
| 0110 | Railing, concrete type PF-1 (706-11602) | CYS | 100.70 | $1,300.00 | $1,355.00 | $2,395.57 | $2,000.00 | $2,190.28 |
| 0111 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $7,000.00 | $2,000.00 | $1.00 | $1.00 | $5,803.80 |
| 0112 | Inclinometer (711-07857) | EACH | 4 | $11,625 | $8,700.00 | $21,045 | $15,000 | $25,000 |
| 0113 | Structural steel (711-51038) | LS | 1 | $1,517,785 | $2,000,000 | $2,165,818 | $2,076,250 | $2,193,413 |
| 0114 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 2,930 | $12.00 | $14.00 | $26.40 | $21.00 | $16.78 |
| 0115 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 115 | $31.50 | $29.50 | $127.81 | $18.00 | $46.70 |
| 0116 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 1,471 | $80.00 | $127.00 | $56.96 | $127.00 | $133.49 |
| 0117 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 44 | $178.00 | $180.00 | $110.64 | $180.00 | $1,298.25 |
| 0118 | HMA for structure installation, type C (715-08306) | TON | 36 | $346.00 | $241.55 | $241.55 | $241.55 | $250.00 |
| 0119 | Video inspection for pipe (715-09064) | LFT | 1,515 | $2.15 | $4.75 | $2.15 | $5.00 | $2.15 |
| 0120 | Pipe end section, diameter 15 in. (715-46005) | EACH | 4 | $718.00 | $2,810.00 | $1,228.48 | $2,810.00 | $1,243.73 |
| 0121 | Video inspection for underdrain (718-06532) | LFT | 1,646 | $5.00 | $4.75 | $2.00 | $5.00 | $2.00 |
| 0122 | Geotextile for underdrains, type 2B (718-12308) | SYS | 2,250 | $5.85 | $3.00 | $5.54 | $5.00 | $7.71 |
| 0123 | Aggregate for underdrains (718-52610) | CYS | 255 | $63.50 | $94.50 | $80.66 | $120.00 | $76.18 |
| 0124 | Manhole, type J5, modified (720-08660) | EACH | 3 | $5,500.00 | $8,540.00 | $8,018.84 | $8,540.00 | $7,902.17 |
| 0125 | Inlet, type HA5 (720-45042) | EACH | 14 | $3,700.00 | $6,250.00 | $6,643.04 | $6,250.00 | $6,538.18 |
| 0126 | Inlet, type P12 (720-45069) | EACH | 3 | $3,900.00 | $7,530.00 | $5,592.80 | $7,530.00 | $7,847.43 |
| 0127 | Catch basin, type E7 (720-45235) | EACH | 1 | $4,800.00 | $7,440.00 | $5,103.11 | $7,440.00 | $7,469.93 |
| 0128 | Manhole, type C4 (720-45410) | EACH | 8 | $3,000.00 | $7,230.00 | $5,915.52 | $7,230.00 | $5,781.12 |
| 0129 | Expansion joint sliding plate (724-03855) | LFT | 20 | $545.00 | $358.36 | $382.70 | $1,250.00 | $693.38 |
| 0130 | Bearing assembly, elastomeric (726-92406) | EACH | 24 | $2,759.00 | $3,000.00 | $3,130.96 | $4,650.00 | $3,108.95 |
| 0131 | Face panels, concrete (731-93945) | SFT | 16,734 | $50.00 | $44.50 | $42.63 | $54.00 | $52.00 |
| 0132 | Wall erection (731-93946) | SFT | 16,734 | $18.00 | $9.50 | $20.74 | $18.50 | $46.00 |
| 0133 | Leveling pad, concrete (731-93947) | LFT | 901 | $35.00 | $41.20 | $35.14 | $38.00 | $100.00 |
| 0134 | Construction sign, type C (801-03290) | EACH | 9 | $271.00 | $271.00 | $271.00 | $271.00 | $271.00 |
| 0135 | Road closure sign assembly (801-04308) | EACH | 10 | $291.00 | $291.00 | $291.00 | $291.00 | $291.00 |
| 0136 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 5,710 | $1.44 | $1.44 | $1.44 | $1.44 | $1.44 |
| 0137 | Temporary pavement marking, removable, 5 in. (801-06208) | LFT | 3,100 | $2.11 | $2.11 | $2.11 | $2.11 | $2.11 |
| 0138 | Detour route marker assembly (801-06625) | EACH | 44 | $171.00 | $171.00 | $171.00 | $171.00 | $171.00 |
| 0139 | Construction sign, type A (801-06640) | EACH | 25 | $234.00 | $234.00 | $234.00 | $234.00 | $476.00 |
| 0140 | Construction sign, type B (801-06645) | EACH | 6 | $117.00 | $117.00 | $117.00 | $117.00 | $117.00 |
| 0141 | Maintaining traffic (801-06775) | LS | 1 | $100,000 | $100,000 | $250,000 | $170,000 | $530,000 |
| 0142 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $9,550.00 | $9,550.00 | $9,550.00 | $7,500.00 | $9,646.47 |
| 0143 | Barricade, type III-A (801-07118) | LFT | 244 | $15.52 | $15.52 | $15.52 | $15.52 | $15.52 |
| 0144 | Barricade, type III-B (801-07119) | LFT | 120 | $15.52 | $15.52 | $15.52 | $15.52 | $15.52 |
| 0145 | Temporary traffic barrier, type 2 (801-08401) | LFT | 470 | $32.90 | $53.00 | $36.78 | $80.00 | $37.21 |
| 0146 | Law enforcement officer (801-12324) | HRS | 40 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0147 | Temporary pedestrian channelizer (801-12862) | LFT | 36 | $49.11 | $49.11 | $49.11 | $49.11 | $49.11 |
| 0148 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 100 | $23.00 | $23.00 | $23.00 | $23.00 | $23.23 |
| 0149 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 74 | $25.00 | $25.00 | $25.00 | $25.00 | $25.25 |
| 0150 | Transverse marking, remove (808-06368) | LFT | 157 | $8.44 | $8.44 | $8.44 | $8.44 | $8.44 |
| 0151 | Line, thermoplastic, broken, white, 4 in. (808-06701) | LFT | 78 | $4.11 | $4.11 | $4.11 | $4.11 | $4.11 |
| 0152 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 234 | $3.61 | $3.61 | $3.61 | $3.61 | $3.61 |
| 0153 | Retro-reflectivity testing (808-09381) | LS | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0154 | Transverse marking, multi-component, crosshatch line, white, 12 in. (808-10047) | LFT | 389 | $6.88 | $6.88 | $6.88 | $6.88 | $6.88 |
| 0155 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 3,974 | $1.19 | $1.19 | $1.19 | $1.19 | $1.19 |
| 0156 | Transverse marking, multi-component, stop line, white, 24 in. (808-10051) | LFT | 52 | $14.28 | $14.28 | $14.28 | $14.28 | $14.28 |
| 0157 | Transverse marking, multi-component, crosswalk line, white, 6 in. (808-10056) | LFT | 160 | $5.91 | $0.68 | $5.91 | $5.91 | $5.91 |
| 0158 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 3,810 | $1.19 | $1.09 | $1.19 | $1.19 | $1.19 |
| 0159 | Transverse marking, multi-component, crosshatch line, yellow, 24 in. (808-10119) | LFT | 45 | $14.28 | $3.61 | $14.28 | $14.28 | $14.28 |
| 0160 | Grooving for pavement markings (808-12032) | LFT | 12,935 | $0.68 | $0.68 | $0.68 | $0.68 | $0.68 |
| 0161 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 3,345 | $1.09 | $1.09 | $1.09 | $1.09 | $1.09 |
| 0162 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 156 | $3.61 | $3.61 | $3.61 | $3.61 | $3.61 |
| 0163 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 2,089 | $1.09 | $1.09 | $1.09 | $1.09 | $1.09 |
| 0164 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 328 | $6.91 | $6.91 | $6.91 | $6.91 | $6.91 |
| 0165 | Snowplowable raised pavement marker (808-75998) | EACH | 228 | $34.25 | $34.25 | $34.25 | $34.25 | $34.25 |
| 0166 | Joint adhesive (401-11526) | LFT | 3,347 | $1.40 | $2.00 | $2.00 | $2.00 | $1.40 |
| 0167 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 3,806 | $3.50 | $5.15 | $5.15 | $5.15 | $3.51 |
| 0168 | PCCP, 12 in. (502-06329) | SYS | 6,755 | $105.00 | $118.00 | $122.94 | $130.00 | $165.00 |
| 0169 | Mulching material (621-06565) | TON | 5.30 | $550.00 | $550.00 | $550.00 | $550.00 | $550.00 |
| 0170 | Longitudinal grooving (722-12732) | SYS | 1,337 | $5.07 | $4.50 | $4.50 | $8.00 | $7.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of May 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.