INDOT contract B-43355-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on May 7, 2026, Porter, LaPorte. 4 bids received; low bid $1,855,375 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 07 MAY 2026
- Pay items
- 92
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $1,855,375 | Low |
| 2 | Icc Group Inc | $2,019,000 | +9.0% |
| 3 | Dunnet Bay Construction Company | $2,024,865 | +9.0% |
| 4 | Milestone Contractors LP | $2,469,789 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Icc Group Inc | 3. Dunnet Bay Construction Company | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,450 | $20,000 | $50,000 | $25,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $90,000 | $100,922 | $101,200 | $135,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $18,000 | $20,000 | $20,291 | $65,000 |
| 0011 | Pavement removal (202-02240) | SYS | 110 | $63.50 | $125.00 | $40.00 | $120.00 |
| 0012 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $258,800 | $97,270 | $350,000 | $165,000 |
| 0013 | Excavation, common (203-02000) | CYS | 144 | $196.00 | $75.00 | $55.00 | $70.00 |
| 0014 | Borrow (203-02070) | CYS | 803 | $0.01 | $75.00 | $80.00 | $90.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 9,360 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $7,300.00 | $20,500 | $3,208.00 | $30,000 |
| 0017 | SWQCP preparation (205-12618) | LS | 1 | $4,500.00 | $4,500.00 | $2,000.00 | $2,000.00 |
| 0018 | Subgrade treatment, type II (207-08264) | SYS | 233 | $43.00 | $25.00 | $25.00 | $50.00 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 580 | $45.00 | $55.00 | $45.00 | $95.00 |
| 0020 | Drilled hole for flowable backfill (213-08068) | EACH | 4 | $100.00 | $300.00 | $500.00 | $625.00 |
| 0021 | Flowable backfill, non- removable (213-09269) | CYS | 5 | $472.00 | $750.00 | $500.00 | $1,500.00 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 788 | $5.00 | $7.00 | $3.50 | $7.00 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 52 | $121.00 | $100.00 | $140.00 | $235.00 |
| 0024 | Compacted aggregate, no. 73 (303-07449) | TON | 104 | $56.00 | $45.00 | $100.00 | $90.00 |
| 0025 | Widening with HMA, type B (304-07493) | TON | 51 | $194.00 | $194.00 | $240.00 | $175.00 |
| 0026 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 686 | $17.60 | $19.00 | $16.00 | $6.00 |
| 0027 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 105 | $237.00 | $237.00 | $237.00 | $260.00 |
| 0028 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 80 | $180.00 | $180.00 | $180.00 | $240.00 |
| 0029 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 192 | $138.00 | $138.00 | $138.00 | $198.00 |
| 0030 | Joint adhesive (401-11526) | LFT | 1,318 | $3.00 | $3.00 | $3.00 | $2.75 |
| 0031 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 1,919 | $8.60 | $0.40 | $8.30 | $9.55 |
| 0032 | Asphalt for tack coat (406-05520) | TON | 1 | $770.00 | $770.00 | $770.00 | $3,000.00 |
| 0033 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 757 | $25.00 | $21.00 | $25.00 | $25.00 |
| 0034 | Guardrail transition, MGS with curb (601-12291) | EACH | 2 | $4,050.00 | $3,100.00 | $4,050.00 | $4,050.00 |
| 0035 | Guardrail transition, MGS without curb (601-12292) | EACH | 2 | $3,950.00 | $3,000.00 | $3,950.00 | $3,950.00 |
| 0036 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $3,400.00 | $2,900.00 | $3,400.00 | $3,400.00 |
| 0037 | Barrier delineator (602-06729) | EACH | 16 | $22.08 | $22.08 | $22.08 | $22.08 |
| 0038 | Fence, farm field, reset (603-06060) | LFT | 182 | $30.00 | $16.00 | $30.00 | $30.00 |
| 0039 | Curb and gutter, concrete, type B (605-06145) | LFT | 90 | $84.00 | $70.00 | $120.00 | $98.00 |
| 0040 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 208 | $190.00 | $225.00 | $200.00 | $345.00 |
| 0041 | Monument, type B (615-06505) | EACH | 2 | $1,220.00 | $1,012.00 | $1,220.00 | $1,220.00 |
| 0042 | Riprap, revetment (616-06405) | TON | 72 | $121.00 | $90.00 | $150.00 | $275.00 |
| 0043 | Geotextile for riprap, type 2B (616-12249) | SYS | 96 | $15.00 | $15.00 | $15.00 | $20.00 |
| 0044 | Clean drains , weep holes bent no.1 (619-98427) | EACH | 4 | $300.00 | $1,000.00 | $200.00 | $500.00 |
| 0045 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $750.00 | $500.00 | $475.00 | $750.00 |
| 0046 | Erosion control blanket (621-02770) | SYS | 5,794 | $1.60 | $1.60 | $1.60 | $1.60 |
| 0047 | Mulched seeding, type U (621-06560) | SYS | 4,419 | $1.25 | $1.25 | $0.92 | $1.25 |
| 0048 | Seed mixture, floodplain (621-12612) | LBS | 8 | $275.00 | $275.00 | $240.00 | $275.00 |
| 0049 | Field office, type C (628-09403) | MOS | 18 | $3,000.00 | $2,183.33 | $1,740.00 | $1,500.00 |
| 0050 | Computer system equipment (628-11976) | EACH | 1 | $850.00 | $810.00 | $270.00 | $650.00 |
| 0051 | Topsoil processing and distribution (629-000149) | SYS | 5,794 | $18.80 | $5.00 | $10.00 | $15.00 |
| 0052 | Topsoil amendment budget (629-000150) | DOL | 11,588 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0053 | Field drilled hole in concrete (702-51863) | EACH | 636 | $22.00 | $30.00 | $20.00 | $30.00 |
| 0054 | Concrete, C, substructure (702-92857) | CYS | 5.20 | $2,250.00 | $1,500.00 | $3,400.00 | $8,000.00 |
| 0055 | Reinforcing bars, epoxy coated (703-06029) | LBS | 20,812 | $2.20 | $1.90 | $2.00 | $2.75 |
| 0056 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 48 | $59.66 | $42.00 | $70.00 | $80.00 |
| 0057 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 4 | $4,955.00 | $4,500.00 | $5,000.00 | $6,500.00 |
| 0058 | Railing, steel type PF-1 , modified (706-11404) | LFT | 445 | $111.00 | $138.00 | $85.00 | $85.00 |
| 0059 | Bridge railing pedestrian fence , modified (706-11455) | LFT | 211 | $100.00 | $105.00 | $125.00 | $100.00 |
| 0060 | Railing, concrete type PF-1 , modified (706-11602) | CYS | 31.40 | $1,640.00 | $2,000.00 | $1,275.00 | $4,800.00 |
| 0061 | Surface seal (709-51821) | LS | 1 | $5,255.00 | $5,254.70 | $1.00 | $5,254.70 |
| 0062 | Patching concrete structures (710-09158) | SFT | 39 | $241.50 | $231.00 | $231.00 | $231.00 |
| 0063 | Structural steel (711-51038) | LS | 1 | $83,400 | $125,000 | $100,000 | $109,000 |
| 0064 | Jacking and supporting superstructure (711-90114) | LS | 1 | $22,000 | $75,000 | $80,000 | $69,000 |
| 0065 | Bridge deck, remove concrete overlay and surface (722-000183) | SYS | 1,034 | $9.65 | $10.00 | $8.50 | $9.00 |
| 0066 | Hydrodemolition (722-01066) | SYS | 1,034 | $73.00 | $145.00 | $98.00 | $115.00 |
| 0067 | Bridge deck overlay budget (722-12380) | DOL | 48,600 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0068 | Longitudinal grooving (722-12732) | SYS | 1,236 | $6.25 | $7.00 | $5.50 | $4.25 |
| 0069 | Bridge deck patching, full depth (722-51401) | SFT | 483 | $34.00 | $200.00 | $1.00 | $19.00 |
| 0070 | Bridge deck overlay, latex modified (722-51842) | SYS | 1,034 | $63.25 | $160.00 | $65.00 | $125.00 |
| 0071 | Overlay dam (722-51874) | SFT | 88 | $70.00 | $60.00 | $70.00 | $70.00 |
| 0072 | Bridge expansion joint, type PCF, replace (724-12776) | LFT | 94 | $82.00 | $100.00 | $100.00 | $120.00 |
| 0073 | Bearing assembly, elastomeric (726-92406) | EACH | 14 | $6,680.00 | $10,000 | $7,147.00 | $12,000 |
| 0074 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 12 | $64.00 | $64.00 | $64.00 | $64.00 |
| 0075 | Epoxy injection, crack preparation (727-90308) | LFT | 145 | $114.00 | $114.00 | $114.00 | $114.00 |
| 0076 | Epoxy injection, furnishing equipment (727-93560) | LS | 1 | $965.00 | $965.00 | $965.00 | $965.00 |
| 0077 | Road closure sign assembly (801-04308) | EACH | 6 | $253.00 | $253.00 | $253.00 | $253.00 |
| 0078 | Detour route marker assembly (801-06625) | EACH | 42 | $149.00 | $149.00 | $149.00 | $149.00 |
| 0079 | Construction sign, type A (801-06640) | EACH | 77 | $203.00 | $203.00 | $203.00 | $203.00 |
| 0080 | Construction sign, type B (801-06645) | EACH | 4 | $102.00 | $102.00 | $102.00 | $102.00 |
| 0081 | Flashing arrow sign (801-06710) | DAY | 70 | $14.00 | $14.00 | $14.00 | $14.00 |
| 0082 | Maintaining traffic (801-06775) | LS | 1 | $80,000 | $18,217 | $100,000 | $70,000 |
| 0083 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $8,800.00 | $2.00 | $7,750.00 | $7,750.00 |
| 0084 | Barricade, type III-A (801-07118) | LFT | 112 | $15.33 | $15.33 | $15.33 | $15.33 |
| 0085 | Barricade, type III-B (801-07119) | LFT | 144 | $15.33 | $15.33 | $15.33 | $15.33 |
| 0086 | Temporary traffic barrier, type 2 (801-08401) | LFT | 755 | $62.00 | $41.00 | $35.00 | $85.86 |
| 0087 | Portable changeable message sign (801-11642) | EACH | 2 | $4,439.00 | $4,439.00 | $4,439.00 | $4,439.00 |
| 0088 | Lane separator (804-11353) | LFT | 1,041 | $63.00 | $100.00 | $55.00 | $130.00 |
| 0089 | Line, multi-component, solid, white, 4 in. (808-10033) | LFT | 1,659 | $0.88 | $0.88 | $0.88 | $0.88 |
| 0090 | Line, multi-component, solid, yellow, 4 in. (808-10034) | LFT | 1,778 | $0.88 | $0.88 | $0.88 | $0.88 |
| 0091 | Grooving for pavement markings (808-12032) | LFT | 3,437 | $0.79 | $0.79 | $0.79 | $0.79 |
| 0092 | Guardrail, remove (601-02241) | LFT | 1,135 | $7.00 | $4.00 | $7.00 | $7.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of May 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.