INDOT contract B-44005-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on April 8, 2026, Lake, LaPorte. 4 bids received; low bid $1,625,610 by Ellas Construction Company Inc.
- Owner
- Indiana DOT
- Letting
- 08 APR 2026
- Pay items
- 100
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ellas Construction Company Inc | $1,625,610 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $1,778,599 | +9.0% |
| 3 | Icc Group Inc | $1,852,200 | +14% |
| 4 | Dunnet Bay Construction Company | $1,912,573 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ellas Construction Company Inc | 2. Rieth-Riley Construction Co., Inc. | 3. Icc Group Inc | 4. Dunnet Bay Construction Company |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $57,500 | $43,200 | $20,250 | $105,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $81,000 | $88,900 | $109,000 | $95,590 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $32,400 | $2,500.00 | $20,000 | $38,000 |
| 0011 | Pavement removal (202-02240) | SYS | 98 | $62.00 | $25.00 | $24.00 | $35.00 |
| 0012 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $232,900 | $121,000 | $157,806 | $65,000 |
| 0013 | Inlet, remove (202-91385) | EACH | 1 | $1,200.00 | $650.00 | $700.00 | $500.00 |
| 0014 | Pipe, remove (202-96133) | LFT | 173 | $31.00 | $22.00 | $30.00 | $10.00 |
| 0015 | Excavation, common (203-02000) | CYS | 385 | $42.00 | $48.00 | $40.00 | $60.00 |
| 0016 | Borrow (203-02070) | CYS | 90 | $50.00 | $1.00 | $100.00 | $50.00 |
| 0017 | Excavation, waterway (203-51223) | CYS | 520 | $50.00 | $32.00 | $35.00 | $40.00 |
| 0018 | Stormwater management budget (205-12108) | DOL | 21,974 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $14,500 | $24,500 | $5,000.00 |
| 0020 | Excavation, foundation, unclassified (206-51230) | CYS | 22 | $60.00 | $105.00 | $85.00 | $110.00 |
| 0021 | Cofferdam (206-51235) | LS | 1 | $1,000.00 | $119,000 | $100,000 | $300,000 |
| 0022 | Subgrade treatment, type II (207-08264) | SYS | 165 | $26.00 | $45.50 | $24.00 | $25.00 |
| 0023 | Subgrade treatment, type IC (207-09935) | SYS | 1,326 | $48.00 | $38.60 | $48.00 | $35.00 |
| 0024 | Aggregate for end bent backfill (211-06467) | CYS | 22 | $102.00 | $96.50 | $160.00 | $425.00 |
| 0025 | Structure backfill, type 1 (211-09264) | CYS | 21 | $89.00 | $95.00 | $105.00 | $450.00 |
| 0026 | Geotextile for pavement, type 2A (214-12238) | SYS | 400 | $4.00 | $4.20 | $4.00 | $3.50 |
| 0027 | Geotextile for pavement, type 2B (214-12239) | SYS | 154 | $8.75 | $10.00 | $10.00 | $8.50 |
| 0028 | Compacted aggregate, no. 2 (301-12231) | CYS | 8 | $150.00 | $116.00 | $110.00 | $85.00 |
| 0029 | Compacted aggregate, no. 5 (301-12232) | CYS | 67 | $74.00 | $94.50 | $60.00 | $75.00 |
| 0030 | Compacted aggregate, no. 53 (301-12234) | CYS | 43 | $97.00 | $92.50 | $115.00 | $118.00 |
| 0031 | Dense graded subbase (302-07455) | CYS | 18 | $106.00 | $125.50 | $110.00 | $130.00 |
| 0032 | Compacted aggregate, no. 53 (303-01180) | TON | 252 | $48.00 | $59.00 | $60.00 | $40.00 |
| 0033 | Compacted aggregate, no. 73 (303-07449) | TON | 30 | $56.00 | $99.00 | $42.00 | $90.00 |
| 0034 | Milling, transition (306-08043) | SYS | 479 | $11.00 | $10.50 | $6.00 | $7.70 |
| 0035 | Lean concrete base, 9 in. (309-12695) | SYS | 154 | $119.50 | $125.00 | $125.00 | $130.00 |
| 0036 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 146 | $142.55 | $142.55 | $142.55 | $142.55 |
| 0037 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 172 | $128.45 | $128.45 | $128.45 | $128.45 |
| 0038 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 554 | $100.65 | $100.65 | $100.65 | $100.65 |
| 0039 | Joint adhesive (401-11526) | LFT | 2,373 | $1.55 | $1.55 | $1.55 | $1.55 |
| 0040 | Asphalt for tack coat (406-05521) | SYS | 4,184 | $1.15 | $1.15 | $1.15 | $1.15 |
| 0041 | Guardrail transition, type TGB , modified (601-01522) | EACH | 2 | $4,450.00 | $4,450.00 | $4,450.00 | $4,450.00 |
| 0042 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 25 | $26.00 | $26.00 | $26.00 | $26.00 |
| 0043 | Guardrail transition, MGS without curb (601-12292) | EACH | 2 | $3,900.00 | $3,900.00 | $3,900.00 | $3,900.00 |
| 0044 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $2,850.00 | $2,850.00 | $2,850.00 | $2,850.00 |
| 0045 | Barrier delineator (602-06729) | EACH | 10 | $35.00 | $25.00 | $24.00 | $35.55 |
| 0046 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 160 | $187.00 | $185.00 | $210.00 | $155.00 |
| 0047 | HMA for approaches, type B (610-07487) | TON | 13 | $273.45 | $273.45 | $273.45 | $273.45 |
| 0048 | PCCP for approaches, 6 in. (610-08446) | SYS | 108 | $110.00 | $110.00 | $70.00 | $130.00 |
| 0049 | Mailbox assembly, single (611-06497) | EACH | 3 | $325.00 | $325.00 | $325.00 | $325.00 |
| 0050 | Right-of-way marker (615-06490) | EACH | 9 | $230.00 | $230.00 | $230.00 | $230.00 |
| 0051 | Monument, type B (615-06505) | EACH | 2 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 |
| 0052 | Riprap, revetment (616-06405) | TON | 365 | $85.00 | $80.00 | $135.00 | $100.00 |
| 0053 | Geotextile for riprap, type 1A (616-12246) | SYS | 626 | $4.00 | $5.00 | $3.50 | $2.50 |
| 0054 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $500.00 | $1,000.00 | $500.00 | $500.00 |
| 0055 | Erosion control blanket (621-02770) | SYS | 942 | $1.50 | $3.00 | $1.50 | $1.50 |
| 0056 | Mulched seeding, type U (621-06560) | SYS | 525 | $1.30 | $1.30 | $1.30 | $1.30 |
| 0057 | Water (621-06567) | KGAL | 1 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0058 | Sodding (621-06574) | SYS | 13 | $25.00 | $25.00 | $25.00 | $25.00 |
| 0059 | Seed mixture, floodplain (621-12612) | LBS | 28 | $225.00 | $225.00 | $225.00 | $225.00 |
| 0060 | Plant, coniferous evergreen, cone, broad upright, 36 in. or under (622-05623) | EACH | 3 | $300.00 | $300.00 | $300.00 | $300.00 |
| 0061 | Field office, type C (628-09403) | MOS | 6 | $3,000.00 | $3,250.00 | $3,150.00 | $2,250.00 |
| 0062 | Computer system equipment (628-11976) | EACH | 2 | $350.00 | $550.00 | $270.00 | $300.00 |
| 0063 | Dynamic pile load test (701-06011) | EACH | 3 | $3,500.00 | $6,500.00 | $6,000.00 | $19,944 |
| 0064 | Test pile, dynamic, production (701-09557) | LFT | 282 | $60.00 | $86.00 | $110.00 | $110.00 |
| 0065 | Test pile, dynamic, restrike (701-09559) | EACH | 3 | $6,000.00 | $5,400.00 | $4,500.00 | $5,027.03 |
| 0066 | Pile, steel pipe, 0.312 in., diameter 14 in. (701-09663) | LFT | 1,370 | $60.00 | $86.00 | $85.00 | $94.00 |
| 0067 | Pile, steel pipe, epoxy coated, 0.312 in., diameter 14 in. (701-09675) | LFT | 210 | $175.00 | $205.00 | $100.00 | $90.00 |
| 0068 | Conical pile tip, 14 in. (701-09679) | EACH | 22 | $380.00 | $580.00 | $400.00 | $380.00 |
| 0069 | Concrete, A, substructure (702-51005) | CYS | 14 | $3,200.00 | $1,800.00 | $2,600.00 | $3,500.00 |
| 0070 | Reinforcing bars, epoxy coated (703-06029) | LBS | 71,612 | $1.55 | $2.25 | $1.60 | $1.50 |
| 0071 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 32 | $38.00 | $70.00 | $50.00 | $84.00 |
| 0072 | Concrete, C, superstructure (704-51002) | CYS | 229.50 | $1,100.00 | $1,450.00 | $2,000.00 | $1,300.00 |
| 0073 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 4 | $3,200.00 | $3,500.00 | $5,000.00 | $3,500.00 |
| 0074 | Railing, concrete type PF-1 (706-09962) | LFT | 120 | $180.00 | $140.00 | $120.00 | $123.00 |
| 0075 | Railing, steel type PF-1 (706-11404) | LFT | 137 | $117.00 | $150.00 | $117.00 | $117.00 |
| 0076 | Surface seal (709-51821) | LS | 1 | $1.00 | $3,550.00 | $1.00 | $1.00 |
| 0077 | Safety metal end section, 6:1, diameter 15 in. (715-02628) | EACH | 1 | $1,600.00 | $2,200.00 | $1,700.00 | $1,500.00 |
| 0078 | Safety metal end section, 6:1, diameter 18 in. (715-02629) | EACH | 2 | $1,800.00 | $2,500.00 | $2,100.00 | $2,250.00 |
| 0079 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 60 | $98.00 | $120.00 | $85.00 | $100.00 |
| 0080 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 146 | $72.00 | $140.00 | $70.00 | $125.00 |
| 0081 | Pipe, type 3, circular, diameter 18 in. (715-05171) | LFT | 60 | $123.00 | $165.00 | $90.00 | $195.00 |
| 0082 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 104 | $18.00 | $20.00 | $15.00 | $20.00 |
| 0083 | HMA for structure installation, type B (715-08305) | TON | 15 | $377.40 | $377.40 | $377.40 | $382.78 |
| 0084 | Pipe end section, diameter 15 in. (715-46005) | EACH | 1 | $800.00 | $1,220.00 | $1,500.00 | $1,300.00 |
| 0085 | Pipe end section, diameter 18 in. (715-46010) | EACH | 1 | $850.00 | $1,300.00 | $1,800.00 | $1,400.00 |
| 0086 | Geotextile for underdrains, type 1A (718-12305) | SYS | 66 | $6.20 | $10.50 | $10.00 | $9.50 |
| 0087 | Pipe, plug existing (720-02442) | EACH | 4 | $680.00 | $1,500.00 | $1,200.00 | $1,800.00 |
| 0088 | Catch basin, type E7 (720-45235) | EACH | 1 | $4,300.00 | $3,750.00 | $7,000.00 | $5,000.00 |
| 0089 | Manhole, type E4 (720-45416) | EACH | 1 | $6,450.00 | $9,600.00 | $12,000 | $9,000.00 |
| 0090 | Longitudinal grooving (722-12732) | SYS | 471 | $12.00 | $11.00 | $11.00 | $10.00 |
| 0091 | Road closure sign assembly (801-04308) | EACH | 5 | $325.00 | $325.00 | $325.00 | $325.00 |
| 0092 | Detour route marker assembly (801-06625) | EACH | 28 | $135.00 | $135.00 | $135.00 | $135.00 |
| 0093 | Construction sign, type A (801-06640) | EACH | 17 | $199.00 | $199.00 | $199.00 | $199.00 |
| 0094 | Construction sign, type B (801-06645) | EACH | 2 | $122.00 | $122.00 | $122.00 | $122.00 |
| 0095 | Maintaining traffic (801-06775) | LS | 1 | $57,500 | $48,000 | $2,955.00 | $2,955.00 |
| 0096 | Barricade, type III-A (801-07118) | LFT | 48 | $17.55 | $17.55 | $17.55 | $17.55 |
| 0097 | Barricade, type III-B (801-07119) | LFT | 72 | $17.55 | $17.55 | $17.55 | $17.55 |
| 0098 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 1,390 | $1.10 | $1.10 | $1.10 | $1.10 |
| 0099 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 1,390 | $1.10 | $1.10 | $1.10 | $1.10 |
| 0100 | Snowplowable raised pavement marker (808-75998) | EACH | 17 | $65.00 | $65.00 | $65.00 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of April 8, 2026. Compiled by Mirage Metrics.