INDOT contract R-43623-A bid tabulation
INTERSECTION IMPROVEMENT, ROUNDABOUT. Let by Indiana DOT on July 8, 2026, Allen, Fort Wayne. 5 bids received; low bid $2,592,099 by Fleming Excavating Inc.
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 102
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Fleming Excavating Inc | $2,592,099 | Low |
| 2 | Milestone Contractors LP | $2,648,821 | +2.0% |
| 3 | Brooks Construction Company Inc | $2,752,688 | +6.0% |
| 4 | E & B Paving LLC | $2,941,894 | +13% |
| 5 | Api Construction Corp | $3,424,249 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fleming Excavating Inc | 2. Milestone Contractors LP | 3. Brooks Construction Company Inc | 4. E & B Paving LLC | 5. Api Construction Corp |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $39,160 | $56,250 | $32,900 | $36,600 | $40,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 12 | $1,200.00 | $1,350.00 | $1,350.00 | $471.52 | $720.00 |
| 0003 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 12 | $1,000.00 | $1,150.00 | $675.00 | $471.52 | $540.00 |
| 0004 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Mobilization and demobilization (110-01001) | LS | 1 | $168,447 | $132,441 | $100,000 | $147,094 | $70,000 |
| 0013 | Tree, 30 in., remove (201-02260) | EACH | 2 | $3,400.00 | $5,600.00 | $4,750.00 | $3,500.00 | $6,200.00 |
| 0014 | Clearing right-of-way (201-52370) | LS | 1 | $43,491 | $79,465 | $20,000 | $10,157 | $32,000 |
| 0015 | Pavement removal (202-02240) | SYS | 6,945 | $5.83 | $6.75 | $7.00 | $5.00 | $9.00 |
| 0016 | Headwall, remove (202-02271) | EACH | 1 | $1,150.00 | $1,150.00 | $760.00 | $648.75 | $4,500.00 |
| 0017 | Pipe, remove (202-96133) | LFT | 20 | $60.00 | $60.00 | $38.00 | $32.44 | $44.00 |
| 0018 | Fence, farm field, remove (202-99187) | LFT | 55 | $20.00 | $21.00 | $28.00 | $28.00 | $28.00 |
| 0019 | Excavation, common (203-02000) | CYS | 3,404 | $40.62 | $39.89 | $59.00 | $100.76 | $48.00 |
| 0020 | Excavation, unclassified (203-02020) | CYS | 1,449 | $25.00 | $25.00 | $59.00 | $42.00 | $60.00 |
| 0021 | Borrow (203-02070) | CYS | 4,086 | $16.00 | $16.00 | $31.00 | $42.00 | $35.00 |
| 0022 | Stormwater management budget (205-12108) | DOL | 23,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0023 | Stormwater management implementation (205-12616) | LS | 1 | $20,930 | $3,050.00 | $1,000.00 | $11,500 | $15,000 |
| 0024 | SWQCP preparation (205-12618) | LS | 1 | $2,420.00 | $2,125.00 | $2,200.00 | $2,200.00 | $2,200.00 |
| 0025 | Subgrade treatment, type II (207-08264) | SYS | 230 | $6.59 | $6.59 | $20.00 | $10.00 | $33.00 |
| 0026 | Subgrade treatment, type IC (207-09935) | SYS | 124 | $13.97 | $13.97 | $38.00 | $94.00 | $50.00 |
| 0027 | Subgrade treatment, type ibc (207-12635) | SYS | 17,388 | $12.28 | $11.55 | $12.00 | $8.00 | $15.00 |
| 0028 | Structure backfill, type 2 (211-09265) | CYS | 219 | $37.60 | $37.60 | $79.00 | $123.39 | $60.00 |
| 0029 | Geotextile for pavement, type 2A (214-12238) | SYS | 2,793 | $5.41 | $5.50 | $4.35 | $2.25 | $7.00 |
| 0030 | Dense graded subbase (302-07455) | CYS | 39 | $50.00 | $68.25 | $87.00 | $190.00 | $70.00 |
| 0031 | Compacted aggregate, no. 53 (303-01180) | TON | 5,049 | $25.74 | $33.25 | $34.00 | $42.00 | $33.00 |
| 0032 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 1,078 | $111.24 | $89.00 | $87.50 | $103.00 | $130.00 |
| 0033 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 1,640 | $96.12 | $74.00 | $73.00 | $89.00 | $113.00 |
| 0034 | QC/QA-HMA, 2, 58S, base, 19.0 MM (401-000052) | TON | 3,349 | $91.80 | $73.00 | $72.50 | $85.00 | $113.00 |
| 0035 | Joint adhesive (401-11526) | LFT | 3,520 | $0.22 | $0.25 | $0.25 | $0.19 | $2.50 |
| 0036 | Asphalt for tack coat (406-05520) | TON | 11 | $1.15 | $700.00 | $700.00 | $1.00 | $700.00 |
| 0037 | QC/QA-PCCP, 11 in. (501-06322) | SYS | 2,793 | $95.04 | $99.50 | $126.50 | $88.00 | $165.00 |
| 0038 | PCCP, 8 in. (502-06999) | SYS | 377 | $75.60 | $83.00 | $101.00 | $70.00 | $137.00 |
| 0039 | PCCP, 4 in. (502-11543) | SYS | 416 | $48.60 | $68.25 | $77.00 | $45.00 | $116.00 |
| 0040 | D-1 contraction joint (503-05240) | LFT | 1,271 | $13.10 | $26.75 | $10.00 | $10.73 | $28.00 |
| 0041 | Curb, concrete (605-06120) | LFT | 220 | $31.90 | $24.00 | $109.00 | $29.00 | $50.00 |
| 0042 | Curb and gutter, concrete (605-06140) | LFT | 1,171 | $21.60 | $40.25 | $30.00 | $20.00 | $66.00 |
| 0043 | Curb and gutter, concrete , turnout (605-06140) | LFT | 72 | $219.66 | $149.25 | $156.00 | $199.69 | $200.00 |
| 0044 | Curb and gutter, concrete, type B , modified (605-06145) | LFT | 2,081 | $30.80 | $31.50 | $32.00 | $28.00 | $56.00 |
| 0045 | Center curb, concrete, type D (605-06255) | SYS | 663 | $44.00 | $85.25 | $98.00 | $40.00 | $130.00 |
| 0046 | Aggregate for shoulder drains (608-04395) | TON | 15 | $38.05 | $126.00 | $81.00 | $605.83 | $45.00 |
| 0047 | HMA for approaches, type B (610-07487) | TON | 55 | $154.00 | $158.00 | $147.00 | $140.00 | $180.00 |
| 0048 | PCCP for approaches, 6 in. (610-08446) | SYS | 230 | $126.50 | $94.00 | $122.00 | $35.00 | $160.00 |
| 0049 | Mailbox assembly, reset, single (611-08232) | EACH | 2 | $345.00 | $613.75 | $400.00 | $400.00 | $400.00 |
| 0050 | Monument, type B (615-06505) | EACH | 37 | $1,045.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 0051 | Monument, type C (615-06510) | EACH | 1 | $517.50 | $450.00 | $450.00 | $450.00 | $450.00 |
| 0052 | Monument, section corner (615-06527) | EACH | 1 | $747.50 | $1,675.00 | $650.00 | $650.00 | $650.00 |
| 0053 | Riprap, revetment (616-06405) | TON | 57 | $46.50 | $46.50 | $88.00 | $118.62 | $72.00 |
| 0054 | Geotextile for riprap, type 1A (616-12246) | SYS | 68 | $4.95 | $4.95 | $6.00 | $23.58 | $3.00 |
| 0055 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $880.00 | $500.00 | $800.00 | $800.00 | $500.00 |
| 0056 | Erosion control blanket (621-02770) | SYS | 5,723 | $1.93 | $2.35 | $1.75 | $1.75 | $3.00 |
| 0057 | Mulched seeding, type R (621-06559) | SYS | 12,007 | $0.77 | $2.25 | $0.70 | $0.70 | $2.00 |
| 0058 | Water (621-06567) | KGAL | 4 | $1.15 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0059 | Topsoil (621-06570) | CYS | 670 | $48.60 | $52.00 | $46.00 | $1.00 | $52.00 |
| 0060 | Sodding, nursery (621-06575) | SYS | 242 | $10.80 | $12.00 | $10.00 | $10.00 | $21.00 |
| 0061 | Field office, type D (628-12683) | MOS | 12 | $1,422.23 | $3,925.00 | $3,650.00 | $3,650.00 | $8,000.00 |
| 0062 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 700 | $16.11 | $15.64 | $16.00 | $10.67 | $30.00 |
| 0063 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 5 | $217.60 | $222.80 | $115.00 | $227.76 | $65.00 |
| 0064 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 700 | $59.13 | $60.56 | $76.00 | $85.09 | $68.00 |
| 0065 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 60 | $87.13 | $90.06 | $83.00 | $78.89 | $82.00 |
| 0066 | Pipe end section, diameter 15 in. (715-46005) | EACH | 4 | $800.00 | $800.00 | $600.00 | $943.90 | $700.00 |
| 0067 | Pipe end section, diameter 18 in. (715-46010) | EACH | 2 | $1,040.00 | $1,040.00 | $900.00 | $994.77 | $950.00 |
| 0068 | Geotextile for underdrains, type 1A (718-12305) | SYS | 9 | $20.75 | $67.50 | $36.00 | $22.00 | $5.00 |
| 0069 | Casting, manhole, adjust to grade (720-12798) | EACH | 1 | $2,100.00 | $2,100.00 | $875.00 | $602.75 | $1,000.00 |
| 0070 | Inlet, type F7 (720-45035) | EACH | 5 | $2,683.00 | $2,683.00 | $3,550.00 | $5,206.00 | $2,700.00 |
| 0071 | Manhole, type B4 (720-45405) | EACH | 1 | $2,315.00 | $2,315.00 | $3,850.00 | $8,896.00 | $3,200.00 |
| 0072 | Road closure sign assembly (801-04308) | EACH | 10 | $362.25 | $315.00 | $315.00 | $315.00 | $315.00 |
| 0073 | Detour route marker assembly (801-06625) | EACH | 42 | $201.25 | $175.00 | $175.00 | $175.00 | $175.00 |
| 0074 | Construction sign, type A (801-06640) | EACH | 8 | $281.75 | $245.00 | $245.00 | $245.00 | $245.00 |
| 0075 | Construction sign, type B (801-06645) | EACH | 2 | $172.50 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0076 | Maintaining traffic (801-06775) | LS | 1 | $16,400 | $45,285 | $8,102.65 | $179,555 | $15,000 |
| 0077 | Barricade, type III-B (801-07119) | LFT | 220 | $20.70 | $18.00 | $18.00 | $18.00 | $18.00 |
| 0078 | Sign, sheet, remove (802-04089) | EACH | 10 | $115.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0079 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 336 | $27.50 | $30.00 | $25.00 | $25.00 | $30.00 |
| 0080 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 160 | $28.75 | $20.00 | $25.00 | $25.00 | $20.00 |
| 0081 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 53 | $35.65 | $23.00 | $31.00 | $31.00 | $23.00 |
| 0082 | Conduit, HDPE, 2 in. schedule 40 (805-11814) | LFT | 460 | $10.80 | $15.00 | $10.00 | $10.00 | $15.00 |
| 0083 | Handhole, lighting (807-02191) | EACH | 1 | $2,160.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0084 | Lighting foundation, concrete, with grounding, 24 in. X 24 in. X 96 in. (807-03758) | EACH | 16 | $2,700.00 | $2,000.00 | $2,500.00 | $2,500.00 | $2,000.00 |
| 0085 | Luminaire , roadway, LED, 67 watt (807-04866) | EACH | 16 | $648.00 | $700.00 | $600.00 | $600.00 | $700.00 |
| 0086 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 1,750 | $31.32 | $21.00 | $29.00 | $29.00 | $21.00 |
| 0087 | Cable, pole circuit, XHHW, no. 10 copper, stranded, 1/C (807-12343) | LFT | 2,240 | $1.65 | $7.00 | $1.50 | $1.50 | $7.00 |
| 0088 | Light pole, 40 FT E.M.H., 10 FT mast arm, breakaway base (807-85752) | EACH | 16 | $5,400.00 | $6,000.00 | $5,000.00 | $5,000.00 | $6,000.00 |
| 0089 | Service point, type I (807-86805) | EACH | 1 | $16,500 | $6,500.00 | $15,000 | $15,000 | $6,500.00 |
| 0090 | Connector kit, unfused (807-86910) | EACH | 16 | $115.00 | $75.00 | $100.00 | $100.00 | $75.00 |
| 0091 | Connector kit, fused (807-86915) | EACH | 16 | $138.00 | $70.00 | $120.00 | $120.00 | $70.00 |
| 0092 | Multiple compression fitting, waterproofed (807-86925) | EACH | 22 | $40.25 | $75.00 | $35.00 | $35.00 | $75.00 |
| 0093 | Insulation link, waterproofed (807-86935) | EACH | 38 | $34.50 | $35.00 | $30.00 | $30.00 | $35.00 |
| 0094 | Line, multi-component, solid, white, 4 in. (808-10033) | LFT | 6,117 | $0.92 | $0.80 | $0.80 | $0.80 | $1.00 |
| 0095 | Line, multi-component, solid, yellow, 4 in. (808-10034) | LFT | 2,784 | $0.92 | $0.80 | $0.80 | $0.80 | $1.00 |
| 0096 | Transverse marking, multi-component, crosshatch line, yellow, 12 in. (808-10042) | LFT | 105 | $9.20 | $8.00 | $8.00 | $8.00 | $8.00 |
| 0097 | Transverse marking, multi-component, stop line, white, 24 in. (808-10051) | LFT | 24 | $23.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 0098 | Pavement message marking, multi- component, lane indication arrow (808-10077) | EACH | 8 | $287.50 | $250.00 | $250.00 | $250.00 | $250.00 |
| 0099 | Transverse marking, multi-component, yield line, white, 27 in. (808-10097) | LFT | 72 | $51.75 | $45.00 | $45.00 | $45.00 | $45.00 |
| 0100 | Line, multi-component, dotted, white, 4 in. (808-11481) | LFT | 44 | $5.75 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0101 | Grooving for pavement markings (808-12032) | LFT | 10,829 | $0.75 | $0.65 | $0.65 | $0.65 | $1.00 |
| 0102 | Line, multi-component, solid, yellow, 10 in. (808-12859) | LFT | 1,884 | $2.30 | $2.00 | $2.00 | $2.00 | $2.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.