INDOT contract R-43476-A bid tabulation
INTERSECTION IMPROVEMENT, ROUNDABOUT. Let by Indiana DOT on February 11, 2026, Madison, Greenfield. 7 bids received; low bid $1,976,926 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 11 FEB 2026
- Pay items
- 113
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $1,976,926 | Low |
| 2 | 3D Company Inc | $1,997,000 | +1.0% |
| 3 | Midwest Paving LLC | $2,074,470 | +5.0% |
| 4 | Rieth-Riley Construction Co., Inc. | $2,125,594 | +8.0% |
| 5 | His Constructors Inc | $2,242,728 | +13% |
| 6 | Calumet Civil Contractors Inc | $2,289,000 | +16% |
| 7 | Morphey Construction Inc. | $2,573,000 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. 3D Company Inc | 3. Midwest Paving LLC | 4. Rieth-Riley Construction Co., Inc. | 5. His Constructors Inc | 6. Calumet Civil Contractors Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $31,500 | $32,915 | $28,000 | $22,475 | $31,000 | $27,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $85,000 | $87,387 | $103,703 | $173,021 | $120,000 | $95,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $6,435.00 | $6,175.00 | $38,000 | $31,887 | $34,000 | $30,000 |
| 0012 | Inlet, remove (202-91385) | EACH | 2 | $1,054.00 | $1,015.00 | $349.00 | $830.57 | $1,305.00 | $400.00 |
| 0013 | Manhole, remove (202-93047) | EACH | 1 | $1,683.00 | $1,630.00 | $698.00 | $738.40 | $1,470.00 | $600.00 |
| 0014 | Light standard and foundation, remove (202-93763) | EACH | 2 | $1,290.00 | $689.15 | $575.39 | $561.00 | $300.00 | $1,500.00 |
| 0015 | Pipe, remove (202-96133) | LFT | 407 | $18.83 | $18.37 | $25.00 | $20.94 | $26.00 | $19.00 |
| 0016 | Borrow (203-02070) | CYS | 3,607 | $16.83 | $14.06 | $1.00 | $0.01 | $16.00 | $21.00 |
| 0017 | Stormwater management budget (205-12108) | DOL | 15,738 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $14,921 | $14,922 | $40,000 | $4,498.59 | $38,000 | $28,000 |
| 0019 | SWQCP preparation (205-12618) | LS | 1 | $2,500.00 | $2,425.00 | $3,520.00 | $2,000.00 | $2,000.00 | $2,500.00 |
| 0020 | Subgrade treatment, type II (207-08264) | SYS | 395 | $18.58 | $18.51 | $26.00 | $20.77 | $34.00 | $20.00 |
| 0021 | Subgrade treatment, type ibc (207-12635) | SYS | 9,058 | $14.00 | $11.06 | $11.50 | $11.11 | $13.00 | $11.75 |
| 0022 | Structure backfill, type 2 (211-09265) | CYS | 545 | $90.47 | $90.46 | $78.00 | $62.54 | $95.00 | $100.00 |
| 0023 | Geogrid, type IB (214-11796) | SYS | 395 | $4.88 | $4.88 | $1.50 | $1.42 | $4.00 | $1.35 |
| 0024 | Geotextile for pavement, type 2A (214-12238) | SYS | 9,328 | $2.64 | $2.65 | $1.81 | $2.34 | $3.00 | $1.50 |
| 0025 | Compacted aggregate, no. 53 (301-12234) | CYS | 1,094 | $70.00 | $75.48 | $60.00 | $80.51 | $88.00 | $85.00 |
| 0026 | Dense graded subbase (302-07455) | CYS | 66 | $94.87 | $94.87 | $143.00 | $105.16 | $100.00 | $115.00 |
| 0027 | Compacted aggregate, no. 53 (303-01180) | TON | 1,144 | $38.00 | $40.68 | $30.00 | $48.16 | $48.00 | $50.00 |
| 0028 | Milling, asphalt, 2 in. (306-08036) | SYS | 547 | $5.00 | $7.32 | $9.50 | $2.59 | $8.70 | $5.79 |
| 0029 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 775 | $99.25 | $105.21 | $115.00 | $102.66 | $106.00 | $100.00 |
| 0030 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 949 | $83.00 | $87.98 | $105.00 | $80.65 | $89.00 | $95.00 |
| 0031 | QC/QA-HMA, 2, 58S, base, 19.0 MM (401-000052) | TON | 1,329 | $80.00 | $84.80 | $100.00 | $90.65 | $86.00 | $95.00 |
| 0032 | QC/QA-HMA, 4, 58E, intermediate, OG, 19.0 MM (401-000067) | TON | 1,048 | $66.00 | $69.96 | $110.00 | $97.94 | $71.00 | $91.00 |
| 0033 | Joint adhesive (401-11526) | LFT | 3,975 | $0.20 | $0.22 | $0.50 | $0.56 | $0.25 | $0.50 |
| 0034 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 4,431 | $2.55 | $2.70 | $4.95 | $5.05 | $8.00 | $7.50 |
| 0035 | Asphalt for tack coat (406-05520) | TON | 8 | $0.01 | $111.00 | $1.00 | $0.01 | $0.05 | $0.01 |
| 0036 | PCCP, 7 in. (502-11564) | SYS | 664 | $72.00 | $76.32 | $74.00 | $97.59 | $77.00 | $107.00 |
| 0037 | D-1 contraction joint (503-05240) | LFT | 458 | $15.00 | $15.90 | $7.48 | $15.10 | $16.00 | $18.00 |
| 0038 | Curb, integral concrete (605-06090) | LFT | 470 | $34.00 | $36.04 | $30.00 | $28.63 | $36.00 | $24.00 |
| 0039 | Curb and gutter, concrete (605-06140) | LFT | 1,182 | $34.50 | $36.57 | $30.00 | $32.16 | $37.00 | $33.00 |
| 0040 | Curb and gutter, concrete, type B , modified (605-06145) | LFT | 311 | $35.50 | $37.63 | $42.00 | $32.78 | $38.00 | $51.00 |
| 0042 | Curb and gutter, rolled curb , modified (605-97937) | LFT | 315 | $24.00 | $25.44 | $32.00 | $34.05 | $26.00 | $51.00 |
| 0043 | PCCP for approaches, 9 in. (610-09108) | SYS | 358 | $82.50 | $87.45 | $90.00 | $98.07 | $88.00 | $104.00 |
| 0044 | Mailbox assembly, single (611-06497) | EACH | 1 | $325.00 | $307.40 | $325.00 | $325.00 | $345.00 | $325.00 |
| 0045 | Right-of-way marker (615-06490) | EACH | 32 | $190.00 | $192.92 | $190.00 | $190.00 | $205.00 | $190.00 |
| 0046 | Monument, type B (615-06505) | EACH | 23 | $920.00 | $1,222.00 | $920.00 | $920.00 | $985.00 | $920.00 |
| 0047 | Monument, type D (615-06515) | EACH | 11 | $110.00 | $149.00 | $110.00 | $110.00 | $120.00 | $110.00 |
| 0048 | Riprap, revetment (616-06405) | TON | 121 | $83.57 | $83.57 | $80.89 | $91.34 | $96.00 | $83.00 |
| 0049 | Geotextile for riprap, type 1A (616-12246) | SYS | 179 | $3.78 | $3.78 | $1.52 | $2.64 | $6.25 | $4.00 |
| 0050 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $625.00 | $663.00 | $800.00 | $250.00 | $855.00 | $800.00 |
| 0051 | Seed mixture, native (621-03909) | LBS | 7 | $331.00 | $350.86 | $297.00 | $600.00 | $320.00 | $297.00 |
| 0052 | Mulching material (621-06565) | TON | 1 | $815.00 | $863.90 | $435.00 | $510.00 | $465.00 | $435.00 |
| 0053 | Water (621-06567) | KGAL | 37 | $15.00 | $15.90 | $5.00 | $1.00 | $5.30 | $5.00 |
| 0054 | Sodding (621-06574) | SYS | 8,739 | $4.46 | $5.02 | $5.77 | $8.00 | $6.20 | $10.00 |
| 0055 | Field office, type C (628-09403) | MOS | 6 | $3,750.00 | $4,195.00 | $3,500.00 | $3,824.27 | $3,685.00 | $3,200.00 |
| 0056 | Topsoil processing and distribution (629-000149) | SYS | 9,119 | $5.20 | $5.04 | $4.00 | $6.92 | $4.00 | $3.83 |
| 0057 | Topsoil amendment budget (629-000150) | DOL | 18,238 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0058 | Pipe, type 2, circular, diameter 36 in. (715-05024) | LFT | 215 | $134.60 | $134.61 | $142.00 | $164.32 | $184.00 | $150.00 |
| 0059 | Pipe, type 2, circular, diameter 15 in. (715-05032) | LFT | 368 | $53.93 | $53.92 | $61.00 | $78.59 | $74.00 | $52.00 |
| 0060 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 3,354 | $13.75 | $12.87 | $10.00 | $8.75 | $9.35 | $12.00 |
| 0061 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 224 | $29.70 | $29.41 | $25.00 | $35.00 | $38.00 | $12.00 |
| 0062 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 101 | $47.10 | $47.11 | $58.00 | $59.53 | $87.00 | $60.00 |
| 0063 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 288 | $77.76 | $77.76 | $93.00 | $95.66 | $126.00 | $95.00 |
| 0064 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 27 | $77.28 | $77.28 | $69.00 | $86.94 | $74.00 | $61.00 |
| 0065 | Pipe end section, diameter 12 in. (715-46000) | EACH | 2 | $957.00 | $957.00 | $1,165.00 | $855.74 | $1,850.00 | $1,500.00 |
| 0066 | Pipe end section, diameter 15 in. (715-46005) | EACH | 8 | $968.00 | $968.00 | $1,314.00 | $1,153.25 | $1,935.00 | $1,500.00 |
| 0067 | Pipe end section, diameter 24 in. (715-46020) | EACH | 1 | $1,299.00 | $1,300.00 | $1,695.00 | $1,604.85 | $2,345.00 | $1,700.00 |
| 0068 | Pipe end section, diameter 36 in. (715-46040) | EACH | 1 | $1,814.00 | $1,815.00 | $2,522.00 | $2,252.11 | $3,060.00 | $2,000.00 |
| 0069 | Outlet protector, type 1 (718-06528) | EACH | 6 | $928.00 | $930.00 | $317.00 | $3,325.00 | $3,270.00 | $450.00 |
| 0070 | Geotextile for underdrains, type 1A (718-12305) | SYS | 2,299 | $1.92 | $1.92 | $0.90 | $3.75 | $4.00 | $1.00 |
| 0071 | Aggregate for underdrains (718-52610) | CYS | 302 | $89.71 | $89.71 | $72.00 | $77.95 | $83.00 | $100.00 |
| 0072 | Inlet, type G7 (720-45040) | EACH | 2 | $4,502.00 | $4,502.00 | $4,380.00 | $4,072.89 | $2,395.00 | $4,200.00 |
| 0073 | Manhole, type C4 (720-45410) | EACH | 2 | $3,417.00 | $3,420.00 | $3,571.00 | $4,156.14 | $4,700.00 | $5,500.00 |
| 0074 | Manhole, type C4, modified (720-45510) | EACH | 1 | $3,319.00 | $3,320.00 | $3,571.00 | $4,124.87 | $4,585.00 | $5,500.00 |
| 0075 | Manhole, type L4 (720-93501) | EACH | 1 | $7,987.00 | $7,990.00 | $9,786.00 | $11,247 | $13,460 | $18,000 |
| 0076 | Manhole, type K4 (720-94612) | EACH | 3 | $6,197.00 | $6,197.00 | $6,643.00 | $8,425.00 | $8,915.00 | $9,800.00 |
| 0077 | Inlet, type B15 (720-98174) | EACH | 1 | $3,696.00 | $3,695.00 | $4,254.00 | $3,867.42 | $3,415.00 | $4,000.00 |
| 0078 | Inlet, type C15 (720-98555) | EACH | 1 | $3,696.00 | $3,695.00 | $4,254.00 | $3,867.42 | $3,415.00 | $4,000.00 |
| 0079 | Catch basin, type B15 (720-99416) | EACH | 6 | $4,410.00 | $4,410.00 | $4,677.00 | $4,574.03 | $3,560.00 | $3,900.00 |
| 0080 | Catch basin, type C15 (720-99417) | EACH | 1 | $4,222.00 | $4,221.00 | $4,782.00 | $4,405.06 | $4,040.00 | $3,900.00 |
| 0081 | Road closure sign assembly (801-04308) | EACH | 11 | $219.00 | $233.00 | $219.00 | $219.00 | $235.00 | $219.00 |
| 0082 | Detour route marker assembly (801-06625) | EACH | 35 | $128.00 | $136.00 | $128.00 | $128.00 | $137.00 | $128.00 |
| 0083 | Construction sign, type A (801-06640) | EACH | 28 | $192.00 | $205.00 | $192.00 | $192.00 | $205.00 | $192.00 |
| 0084 | Maintaining traffic (801-06775) | LS | 1 | $20,765 | $10,112 | $17,068 | $5,837.38 | $23,455 | $70,778 |
| 0085 | Barricade, type III-A (801-07118) | LFT | 96 | $11.00 | $11.66 | $11.00 | $11.00 | $12.00 | $11.00 |
| 0086 | Barricade, type III-B (801-07119) | LFT | 144 | $12.00 | $12.72 | $12.00 | $12.00 | $13.00 | $12.00 |
| 0087 | Portable changeable message sign (801-11642) | EACH | 2 | $1,910.00 | $2,025.00 | $1,910.00 | $1,910.00 | $2,050.00 | $1,910.00 |
| 0088 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 340 | $30.00 | $21.20 | $30.77 | $30.00 | $32.00 | $30.00 |
| 0089 | Sign post, square, type 2, reinforced anchor base (802-05702) | LFT | 56 | $26.79 | $19.08 | $27.48 | $26.79 | $29.00 | $29.00 |
| 0090 | Sign, sheet, and supports, remove (802-07059) | EACH | 14 | $78.57 | $63.60 | $80.58 | $78.57 | $84.00 | $50.00 |
| 0091 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 141 | $25.54 | $26.50 | $26.19 | $25.54 | $27.00 | $30.00 |
| 0092 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 110 | $27.28 | $23.32 | $27.98 | $27.28 | $29.00 | $32.00 |
| 0093 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 232 | $31.90 | $33.82 | $32.72 | $31.90 | $34.00 | $25.00 |
| 0094 | Handhole, lighting (807-02191) | EACH | 7 | $1,200.00 | $1,272.00 | $1,230.77 | $1,200.00 | $1,285.00 | $1,250.00 |
| 0095 | Lighting foundation, concrete, with grounding, 24 in. X 24 in. X 96 in. (807-03758) | EACH | 15 | $2,173.30 | $2,305.00 | $2,229.03 | $2,173.30 | $2,340.00 | $2,800.00 |
| 0096 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 4,301 | $18.02 | $19.10 | $18.48 | $18.02 | $19.25 | $22.00 |
| 0097 | Luminaire, high lumen roadway (807-12199) | EACH | 15 | $460.00 | $488.00 | $471.79 | $460.00 | $495.00 | $600.00 |
| 0098 | Light pole, 40 FT E.M.H., 8 FT mast arm, anchor base (807-83748) | EACH | 15 | $3,400.00 | $3,604.00 | $3,487.18 | $3,400.00 | $3,645.00 | $3,400.00 |
| 0099 | Service point, type II (807-86810) | EACH | 1 | $9,000.00 | $9,540.00 | $9,230.77 | $9,000.00 | $9,650.00 | $10,000 |
| 0100 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 1,200 | $1.42 | $1.51 | $1.46 | $1.42 | $1.50 | $1.75 |
| 0101 | Connector kit, unfused (807-86910) | EACH | 15 | $35.30 | $37.47 | $36.21 | $35.30 | $38.00 | $55.00 |
| 0102 | Connector kit, fused (807-86915) | EACH | 15 | $35.30 | $37.47 | $36.21 | $35.30 | $38.00 | $55.00 |
| 0103 | Multiple compression fitting, non- waterproofed (807-86920) | EACH | 44 | $29.55 | $31.34 | $30.31 | $29.55 | $32.00 | $30.00 |
| 0104 | Insulation link, waterproofed (807-86935) | EACH | 88 | $29.55 | $31.33 | $30.31 | $29.55 | $32.00 | $50.00 |
| 0105 | Wire, no. 4 copper, in plastic duct, 4 1/C (807-97237) | LFT | 464 | $18.11 | $19.20 | $18.57 | $18.11 | $19.50 | $22.00 |
| 0106 | Transverse marking, thermoplastic, yield line, white, 24 in. (808-10118) | LFT | 72 | $23.00 | $24.38 | $23.00 | $23.00 | $24.00 | $23.00 |
| 0107 | Line, thermoplastic, dotted, white, 8 in. (808-11478) | LFT | 189 | $7.23 | $7.67 | $7.23 | $7.23 | $7.75 | $7.23 |
| 0108 | Grooving for pavement markings (808-12032) | LFT | 6,514 | $0.95 | $1.00 | $0.95 | $0.95 | $1.00 | $0.95 |
| 0109 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 1,823 | $1.87 | $1.98 | $1.87 | $1.87 | $2.00 | $1.87 |
| 0110 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 4,502 | $1.22 | $1.29 | $1.22 | $1.22 | $1.30 | $1.22 |
| 0111 | Transverse marking, thermoplastic, crosshatch line, yellow, 24 in. (808-75290) | LFT | 72 | $9.46 | $10.03 | $9.46 | $9.46 | $10.00 | $9.46 |
| 0112 | Center curb, concrete, type B , colored (605-06245) | SYS | 557 | $120.00 | $127.20 | $200.00 | $101.15 | $128.00 | $107.03 |
| 0113 | Sidewalk, concrete (604-06070) | SYS | 21 | $96.50 | $102.29 | $77.00 | $73.17 | $103.00 | $99.69 |
| 0114 | Excavation, common (203-02000) | CYS | 2,780 | $40.84 | $40.16 | $33.00 | $41.25 | $39.00 | $39.42 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 11, 2026. Compiled by Mirage Metrics.