INDOT contract B-45003-A bid tabulation
BRIDGE PAINTING. Let by Indiana DOT on February 12, 2025, Marion, Greenfield. 4 bids received; low bid $481,758 by Eagle Painting & Maintenance Company Inc.
- Owner
- Indiana DOT
- Letting
- 12 FEB 2025
- Pay items
- 37
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eagle Painting & Maintenance Company Inc | $481,758 | Low |
| 2 | Civil Coatings and Construction Inc | $539,385 | +12% |
| 3 | American Industrial Coatings Inc | $774,841 | +61% |
| 4 | Three Star Painting Inc | $875,977 | +82% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Painting & Maintenance Company Inc | 2. Civil Coatings and Construction Inc | 3. American Industrial Coatings Inc | 4. Three Star Painting Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $500.00 | $1.00 | $20,000 | $1.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $24,000 | $25,000 | $40,000 | $52,100 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $1,000.00 | $1.00 | $30,000 | $1.00 |
| 0010 | Excavation, common (203-02000) | CYS | 500 | $20.00 | $1.00 | $95.00 | $1.00 |
| 0011 | Stormwater management budget (205-12108) | DOL | 5,823 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Stormwater management implementation (205-12616) | LS | 1 | $15,000 | $3,000.00 | $10,000 | $1.00 |
| 0013 | Guardrail, reset (601-06035) | LFT | 25 | $36.00 | $30.00 | $31.00 | $1.00 |
| 0014 | Clean steel bridge, QP-2, bridge no. 1 (619-11052) | LS | 1 | $114,800 | $172,580 | $132,632 | $334,958 |
| 0015 | Clean steel bridge, QP-2, bridge no. 2 (619-11052) | LS | 1 | $114,800 | $172,580 | $132,632 | $334,958 |
| 0016 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $9,000.00 | $1.00 | $5,000.00 | $2,500.00 |
| 0017 | Disposal of cleaning waste, hazardous, bridge no. 2 (619-12459) | LS | 1 | $9,000.00 | $1.00 | $5,000.00 | $2,500.00 |
| 0018 | Coat steel bridge, bridge no. 1 (619-51859) | LS | 1 | $40,200 | $35,000 | $81,754 | $31,662 |
| 0019 | Coat steel bridge, bridge no. 2 (619-51859) | LS | 1 | $40,200 | $35,000 | $81,754 | $31,622 |
| 0020 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $100.00 | $525.00 | $7,000.00 | $1.00 |
| 0021 | Seed mixture, floodplain (621-12612) | LBS | 1 | $1,000.00 | $1,450.00 | $4,000.00 | $1.00 |
| 0022 | Temporary shoring (702-04325) | LS | 1 | $20,000 | $0.01 | $50,000 | $1.00 |
| 0023 | Road closure sign assembly (801-04308) | EACH | 1 | $200.00 | $200.00 | $200.00 | $200.00 |
| 0024 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 1,435 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0025 | Detour route marker assembly (801-06625) | EACH | 13 | $75.00 | $75.00 | $75.00 | $75.00 |
| 0026 | Construction sign, type A (801-06640) | EACH | 43 | $200.00 | $200.00 | $200.00 | $200.00 |
| 0027 | Construction sign, type B (801-06645) | EACH | 2 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0028 | Flashing arrow sign (801-06710) | DAY | 2 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0029 | Maintaining traffic (801-06775) | LS | 1 | $11,500 | $22,467 | $40,000 | $20,800 |
| 0030 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $6,225.00 | $8,500.00 | $6,900.00 | $8,500.00 |
| 0031 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,145 | $18.30 | $15.00 | $32.00 | $9.60 |
| 0032 | Portable changeable message sign (801-11642) | EACH | 2 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 0033 | Truck mounted attenuator (801-12042) | DAY | 2 | $500.00 | $500.00 | $500.00 | $500.00 |
| 0034 | Temporary pavement marking, removable, 10 in. (801-12956) | LFT | 75 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0035 | Line, remove (808-06716) | LFT | 409 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0036 | Grooving for pavement markings (808-12032) | LFT | 409 | $6.00 | $6.00 | $6.00 | $6.00 |
| 0037 | Line, preformed plastic, dotted, white, 10 in. (808-12848) | LFT | 409 | $12.00 | $12.00 | $12.00 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.