INDOT contract B-43652-A bid tabulation
BRIDGE REHABILITATION OR REPAIR. Let by Indiana DOT on January 15, 2025, Harrison, Seymour. 3 bids received; low bid $1,056,000 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 67
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $1,056,000 | Low |
| 2 | American Contracting & Services Inc | $1,495,352 | +42% |
| 3 | Pace Contracting LLC | $3,202,965 | +203% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. American Contracting & Services Inc | 3. Pace Contracting LLC |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $18,229 | $17,000 | $70,271 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $1,348.48 | $750.00 | $2,761.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $52,800 | $74,768 | $152,714 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $10,595 | $29,907 | $209,607 |
| 0012 | Pavement removal (202-02240) | SYS | 140 | $88.00 | $55.00 | $206.05 |
| 0013 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $140,000 | $130,000 | $391,672 |
| 0014 | Excavation, common (203-02000) | CYS | 51 | $110.00 | $450.00 | $546.67 |
| 0015 | Excavation, rock (203-02010) | CYS | 10 | $500.00 | $250.00 | $3,458.00 |
| 0016 | Stormwater management budget (205-12108) | DOL | 2,200 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $7,863.51 | $25,000 | $51,699 |
| 0018 | Cofferdam (206-51235) | LS | 1 | $45,000 | $60,000 | $320,611 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 319 | $55.00 | $55.00 | $110.26 |
| 0020 | B borrow (211-02050) | CYS | 11 | $150.00 | $100.00 | $861.32 |
| 0021 | Geotextile for pavement, type 2B (214-12239) | SYS | 140 | $13.00 | $15.00 | $93.53 |
| 0022 | Compacted aggregate, no. 53 (301-12234) | CYS | 10 | $115.00 | $125.00 | $1,057.00 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 36 | $238.00 | $130.00 | $356.82 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 194 | $66.00 | $50.00 | $123.99 |
| 0025 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 746 | $15.00 | $12.00 | $7.27 |
| 0026 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 65 | $283.00 | $265.00 | $325.56 |
| 0027 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 29 | $300.00 | $280.00 | $590.78 |
| 0028 | QC/QA-HMA, 2, 58S, base, 25.0 MM (401-000046) | TON | 36 | $300.00 | $235.00 | $495.68 |
| 0029 | Joint adhesive, surface (401-10258) | LFT | 739 | $0.65 | $0.25 | $1.00 |
| 0030 | Joint adhesive, intermediate (401-10259) | LFT | 30 | $0.10 | $0.25 | $1.00 |
| 0031 | Liquid asphalt sealant (401-11785) | LFT | 739 | $0.55 | $0.25 | $1.00 |
| 0032 | Asphalt for tack coat (406-05521) | SYS | 815 | $0.01 | $0.25 | $1.00 |
| 0033 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $2,800.00 | $2,800.00 | $2,800.00 |
| 0034 | Guardrail, remove (601-02241) | LFT | 457 | $11.00 | $11.00 | $11.00 |
| 0035 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 25 | $22.00 | $22.00 | $110.00 |
| 0036 | Guardrail, MGS W-beam, shop curved, 6 FT 3 in. spacing (601-12286) | LFT | 93 | $36.00 | $36.00 | $36.00 |
| 0037 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0038 | Guardrail transition, MGS without curb (601-12292) | EACH | 1 | $2,600.00 | $2,600.00 | $2,600.00 |
| 0039 | Guardrail transition, MGS without curb , modified (601-12292) | EACH | 2 | $2,900.00 | $2,900.00 | $1,450.00 |
| 0040 | Guardrail end treatment, type OS (601-94689) | EACH | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0041 | Guardrail end treatment, type OS , modified (601-94689) | EACH | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0042 | Barrier delineator (602-06729) | EACH | 10 | $28.35 | $50.00 | $195.00 |
| 0043 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 140 | $200.00 | $250.00 | $394.00 |
| 0044 | Mailbox assembly, single (611-06497) | EACH | 1 | $350.00 | $350.00 | $350.00 |
| 0045 | Clean and coat steel piling, bridge no. 1 (619-12507) | LS | 1 | $29,000 | $29,000 | $56,342 |
| 0046 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $900.00 | $975.00 | $900.00 |
| 0047 | Mulched seeding, type R (621-06559) | SYS | 373 | $3.00 | $8.33 | $3.00 |
| 0048 | Field office, type C (628-09403) | MOS | 10 | $2,850.00 | $3,500.00 | $3,185.00 |
| 0049 | Field drilled hole in concrete (702-51863) | EACH | 84 | $16.00 | $25.00 | $173.00 |
| 0050 | Reinforcing bars, epoxy coated (703-06029) | LBS | 101,303 | $1.25 | $1.45 | $1.41 |
| 0051 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 32 | $50.00 | $45.00 | $35.00 |
| 0052 | Concrete, C, superstructure (704-51002) | CYS | 289.40 | $1,180.00 | $2,375.00 | $4,054.53 |
| 0053 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $2,100.00 | $1,210.00 | $6,639.00 |
| 0054 | Railing, concrete type C (706-51020) | CYS | 26.10 | $530.00 | $849.00 | $2,062.00 |
| 0055 | Surface seal (709-51821) | LS | 1 | $1.00 | $6,000.00 | $41,585 |
| 0056 | Longitudinal grooving (722-12732) | SYS | 553 | $8.35 | $15.00 | $5.06 |
| 0057 | Road closure sign assembly (801-04308) | EACH | 5 | $258.00 | $175.00 | $357.00 |
| 0058 | Detour route marker assembly (801-06625) | EACH | 40 | $158.00 | $75.00 | $145.00 |
| 0059 | Construction sign, type A (801-06640) | EACH | 22 | $209.00 | $175.00 | $245.01 |
| 0060 | Maintaining traffic (801-06775) | LS | 1 | $25,500 | $16,000 | $72,372 |
| 0061 | Barricade, type III-A (801-07118) | LFT | 72 | $15.58 | $15.00 | $85.01 |
| 0062 | Barricade, type III-B (801-07119) | LFT | 72 | $15.58 | $15.00 | $85.01 |
| 0063 | Sign, ground mounted, reset (802-91122) | EACH | 3 | $350.00 | $350.00 | $1,393.00 |
| 0064 | Delineator post, flexible, type I (804-11920) | EACH | 10 | $55.00 | $55.00 | $125.00 |
| 0065 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 846 | $1.53 | $1.00 | $1.00 |
| 0066 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 846 | $1.53 | $1.00 | $1.00 |
| 0067 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $2,825.00 | $2,825.00 | $2,825.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.