INDOT contract B-43963-A bid tabulation

SMALL STRUCTURE PIPE LINING. Let by Indiana DOT on July 9, 2025, Marion, Greenfield. 4 bids received; low bid $629,000 by Morphey Construction Inc..

Owner
Indiana DOT
Letting
09 JUL 2025
Pay items
38
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Morphey Construction Inc.$629,000Low
2Temple & Temple Excavating & Paving Inc$648,857+3.0%
3Yarberry Companies Inc$708,906+13%
4Infrastructure Systems Inc$758,396+21%
INDOT contract B-43963-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Morphey Construction Inc.2. Temple & Temple Excavating & Paving Inc3. Yarberry Companies Inc4. Infrastructure Systems Inc
0001Construction engineering (105-06845)LS1$4,000.00$3,200.00$10,000$5,500.00
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00
0004Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00
0005Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00
0006Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00
0007Mobilization and demobilization (110-01001)LS1$31,400$62,000$35,000$36,500
0008Clearing right-of-way (201-52370)LS1$10,000$14,000$15,000$12,500
0009Excavation, common (203-02000)CYS10$200.00$300.00$3,000.00$50.00
0010Pump around (205-11626)EACH1$15,000$30,000$15,000$13,500
0011Stormwater management budget (205-12108)DOL3,210$1.00$1.00$1.00$1.00
0012Stormwater management implementation (205-12616)LS1$5,000.00$9,000.00$8,000.00$6,500.00
0013Compacted aggregate, no. 53 (303-01180)TON79$150.00$100.00$85.00$150.00
0014Guardrail, remove (601-02241)LFT682$5.00$13.00$12.00$5.00
0015Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT363$20.00$38.00$34.00$24.00
0016Guardrail, MGS, long span, type 2 (601-12288)EACH2$1,500.00$2,840.00$2,530.00$1,300.00
0017Guardrail end treatment, type OS (601-94689)EACH4$3,000.00$4,320.00$3,835.00$3,000.00
0018Riprap, class 2 (616-05689)TON94$250.00$160.00$175.00$200.00
0019Geotextile for riprap, type 1A (616-12246)SYS133$11.00$13.00$15.00$5.00
0020Mobilization and demobilization for seeding (621-01004)EACH1$400.00$3,200.00$750.00$900.00
0021Mulched seeding, type R (621-06559)SYS376$25.00$5.00$3.00$17.00
0022Seed mixture, emergent wetland (621-06737)LBS2$1,560.00$2,000.00$850.00$1,200.00
0023Cored hole in concrete (702-03607)EACH2$6,000.00$6,000.00$1,000.00$12,500
0024Pipe installation, trenchless, 48 in. (716-07637)LFT80$2,050.00$2,448.00$2,500.00$2,700.00
0025Liner pipe, thermoplastic, deformed, 26.6-28.3 SFT (725-10198)LFT82$2,400.00$1,642.00$2,300.00$3,000.00
0026Temporary pavement message marking, lane indication arrow (801-01504)EACH1$500.00$185.00$200.00$600.00
0027Temporary pavement marking, removable, 6 in. (801-06209)LFT3,667$2.10$2.50$3.00$2.50
0028Temporary pavement marking, removable, 6 in. , black (801-06209)LFT2,753$2.25$2.50$3.50$3.00
0029Construction sign, type A (801-06640)EACH5$205.00$185.00$210.00$250.00
0030Construction sign, type B (801-06645)EACH3$99.00$185.00$210.00$150.00
0031Maintaining traffic (801-06775)LS1$43,939$7,500.00$40,000$15,500
0032Energy absorbing terminal, CZ, TL-2 (801-07023)EACH2$5,000.00$11,700$10,355$10,000
0033Temporary traffic barrier, type 2 (801-08401)LFT662$52.00$64.00$57.00$95.00
0034Temporary worksite speed limit sign assembly, continuous (801-12883)EACH4$304.00$375.00$340.00$375.00
0035Line, thermoplastic, solid, white, 6 in. (808-75043)LFT1,190$1.64$4.00$4.00$2.00
0036Line, thermoplastic, solid, yellow, 6 in. (808-75247)LFT854$1.64$4.00$4.00$2.00
0037Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278)LFT103$6.42$10.00$10.00$7.50
0038Pavement message marking, thermoplastic, lane indication arrow (808-75320)EACH3$291.00$300.00$300.00$325.00
INDOT contract B-43963-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy