INDOT contract B-45038-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on November 13, 2025, Franklin, Seymour. 3 bids received; low bid $2,291,025 by Paul H Rohe Company Inc.
- Owner
- Indiana DOT
- Letting
- 13 NOV 2025
- Pay items
- 89
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Paul H Rohe Company Inc | $2,291,025 | Low |
| 2 | Beaty Construction Inc | $2,301,870 | 0.0% |
| 3 | Dave Omara Contractor Inc | $2,535,337 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Paul H Rohe Company Inc | 2. Beaty Construction Inc | 3. Dave Omara Contractor Inc |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $5,900.00 | $15,000 | $5,900.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $68,882 | $150,000 | $127,000 |
| 0011 | Pavement removal (202-02240) | SYS | 142 | $120.00 | $50.00 | $160.00 |
| 0012 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $261,755 | $95,000 | $225,000 |
| 0013 | Sidewalk concrete, remove (202-52710) | SYS | 84 | $44.00 | $45.40 | $40.00 |
| 0014 | Excavation, common (203-02000) | CYS | 635 | $37.00 | $55.00 | $140.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 4,193 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $2,500.00 | $15,000 | $5,000.00 |
| 0017 | Subgrade treatment, type IC (207-09935) | SYS | 1,800 | $52.00 | $41.00 | $50.00 |
| 0018 | Aggregate for end bent backfill (211-06467) | CYS | 11 | $200.00 | $230.00 | $300.00 |
| 0019 | Geotextile for pavement, type 2B (214-12239) | SYS | 689 | $7.00 | $4.00 | $2.50 |
| 0020 | Compacted aggregate, no. 53 (301-12234) | CYS | 49 | $160.00 | $130.00 | $110.00 |
| 0021 | Subbase for PCCP (302-06464) | CYS | 100 | $140.00 | $185.00 | $150.00 |
| 0022 | Milling, transition (306-08043) | SYS | 734 | $10.00 | $10.00 | $9.75 |
| 0023 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 177 | $185.00 | $120.00 | $120.00 |
| 0024 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 194 | $175.00 | $120.00 | $120.00 |
| 0025 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 667 | $125.00 | $120.00 | $120.00 |
| 0026 | Joint adhesive (401-11526) | LFT | 3,260 | $0.80 | $1.00 | $1.00 |
| 0027 | Asphalt for tack coat (406-05521) | SYS | 4,947 | $0.70 | $0.50 | $0.50 |
| 0028 | Terminal joint, type HMA (503-12477) | LFT | 90 | $500.00 | $540.00 | $550.00 |
| 0029 | Guardrail, remove (601-02241) | LFT | 230 | $0.01 | $2.18 | $2.00 |
| 0030 | Guardrail, reset , modified (601-06035) | LFT | 465 | $68.00 | $68.00 | $68.00 |
| 0031 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 50 | $23.00 | $23.00 | $23.00 |
| 0032 | Guardrail transition, MGS without curb , modified (601-12292) | EACH | 2 | $3,350.00 | $3,350.00 | $3,350.00 |
| 0033 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $2,750.00 | $2,750.00 | $2,750.00 |
| 0034 | Barrier delineator (602-06729) | EACH | 11 | $40.00 | $35.00 | $35.00 |
| 0035 | Sidewalk, concrete (604-06070) | SYS | 68 | $140.00 | $175.00 | $80.00 |
| 0036 | Curb ramp, concrete (604-08086) | SYS | 13 | $230.00 | $280.00 | $300.00 |
| 0037 | Detectable warning surfaces (604-12083) | SYS | 3 | $300.00 | $600.00 | $200.00 |
| 0038 | Reinforced concrete bridge approach, 14 in. , modified (609-06262) | SYS | 395 | $170.00 | $185.00 | $200.00 |
| 0039 | Clean steel bridge, QP-2, bridge no. bridge no. 1 (619-11052) | LS | 1 | $208,000 | $208,000 | $190,000 |
| 0040 | Disposal of cleaning waste, hazardous, bridge no. bridge no. 1 (619-12459) | LS | 1 | $5,000.00 | $5,000.00 | $8,500.00 |
| 0041 | Coat steel bridge, bridge no. bridge no. 1 (619-51859) | LS | 1 | $50,000 | $50,000 | $70,000 |
| 0042 | Computer system equipment (628-11976) | EACH | 2 | $950.00 | $1,000.00 | $900.00 |
| 0043 | Field office, type D (628-12683) | MOS | 10 | $3,700.00 | $3,500.00 | $2,700.00 |
| 0044 | Temporary shoring (702-04325) | LS | 1 | $74,500 | $50,000 | $44,000 |
| 0045 | Field drilled hole in concrete , modified (702-51863) | EACH | 64 | $44.00 | $75.00 | $15.00 |
| 0046 | Reinforcing bars, epoxy coated (703-06029) | LBS | 46,297 | $1.33 | $1.75 | $1.80 |
| 0047 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 274 | $58.00 | $50.00 | $35.00 |
| 0048 | Concrete, C, superstructure (704-51002) | CYS | 94.50 | $2,495.00 | $1,000.00 | $4,000.00 |
| 0049 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 2 | $16,050 | $6,750.00 | $9,000.00 |
| 0050 | Railing, steel type PF-1 (706-11404) | LFT | 305 | $73.00 | $73.00 | $73.00 |
| 0051 | Railing, concrete type PF-1 , modified (706-11602) | CYS | 20 | $1,660.00 | $3,000.00 | $1,877.00 |
| 0052 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $5,720.00 | $8,500.00 | $5,719.97 |
| 0053 | Drilled hole (711-51864) | EACH | 64 | $80.00 | $79.69 | $79.69 |
| 0054 | Jacking and supporting structural steel , bridge no. 1 (711-93035) | LS | 1 | $43,670 | $85,000 | $18,700 |
| 0055 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 142 | $72.00 | $20.00 | $40.00 |
| 0056 | Geotextile for underdrains, type 2A (718-12307) | SYS | 60 | $8.00 | $8.40 | $3.00 |
| 0057 | Bridge deck overlay, rigid (722-000134) | SYS | 1,456 | $170.00 | $98.00 | $135.00 |
| 0058 | Hydrodemolition (722-01066) | SYS | 1,340 | $70.00 | $70.00 | $55.55 |
| 0059 | Bridge deck overlay budget (722-12380) | DOL | 29,700 | $1.00 | $1.00 | $1.00 |
| 0060 | Bridge deck, remove concrete surface (722-12464) | SYS | 1,340 | $8.60 | $12.00 | $13.50 |
| 0061 | Longitudinal grooving (722-12732) | SYS | 1,788 | $3.50 | $12.50 | $3.50 |
| 0062 | Bridge deck patching, full depth (722-51401) | SFT | 363 | $38.00 | $50.00 | $115.00 |
| 0063 | Bridge expansion joint, type PCF (724-12773) | LFT | 16 | $110.00 | $1,500.00 | $600.00 |
| 0064 | Bearing assembly, elastomeric (726-92406) | EACH | 16 | $875.00 | $4,500.00 | $4,150.00 |
| 0065 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 4,032 | $3.25 | $1.94 | $1.98 |
| 0066 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $14.95 | $12.34 | $11.81 |
| 0067 | Construction sign, type A (801-06640) | EACH | 12 | $165.00 | $232.00 | $199.00 |
| 0068 | Construction sign, type B (801-06645) | EACH | 8 | $120.00 | $108.00 | $81.00 |
| 0069 | Maintaining traffic (801-06775) | LS | 1 | $33,925 | $175,000 | $45,000 |
| 0070 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0071 | Barricade, type III-B (801-07119) | LFT | 304 | $16.00 | $18.34 | $16.00 |
| 0072 | Temporary traffic barrier, type 2 (801-08401) | LFT | 330 | $54.00 | $95.00 | $51.28 |
| 0073 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 580 | $49.00 | $65.00 | $69.49 |
| 0074 | Portable signal (801-12081) | LS | 1 | $15,850 | $50,000 | $47,500 |
| 0075 | Temporary pedestrian channelizer (801-12862) | LFT | 745 | $6.30 | $20.50 | $31.13 |
| 0076 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 4 | $1,800.00 | $1,233.00 | $280.00 |
| 0077 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $300.00 | $300.00 | $700.00 |
| 0078 | Conduit, steel, galvanized, 2 in. (805-01844) | LFT | 330 | $35.00 | $35.00 | $35.00 |
| 0079 | Wire, no. 4 copper, in conduit, bridge 1/C (807-01653) | LFT | 1,100 | $4.50 | $6.00 | $4.50 |
| 0080 | Handhole, lighting (807-02191) | EACH | 1 | $1,800.00 | $2,000.00 | $1,800.00 |
| 0081 | Light structure, remove and reset (807-02370) | EACH | 2 | $3,200.00 | $2,200.00 | $3,200.00 |
| 0082 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 25 | $18.00 | $30.00 | $18.00 |
| 0083 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 210 | $3.00 | $2.00 | $3.00 |
| 0084 | Line, remove (808-06716) | LFT | 1,622 | $0.98 | $0.81 | $1.31 |
| 0085 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 1,565 | $1.15 | $1.27 | $2.50 |
| 0086 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 1,295 | $1.15 | $1.27 | $2.50 |
| 0087 | Grooving for pavement markings (808-12032) | LFT | 3,030 | $0.45 | $1.44 | $1.78 |
| 0088 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 170 | $1.45 | $3.81 | $2.50 |
| 0089 | Linear grading (203-08607) | LFT | 500 | $18.00 | $20.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.