INDOT contract T-46121-A bid tabulation
ITS COMMUNICATIONS SYSTEMS. Let by Indiana DOT on May 7, 2025, Hendricks, Marion, Greenfield. 2 bids received; low bid $2,339,000 by William Charles Construction Company.
- Owner
- Indiana DOT
- Letting
- 07 MAY 2025
- Pay items
- 77
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | William Charles Construction Company | $2,339,000 | Low |
| 2 | James H Drew Corporation | $2,871,803 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. William Charles Construction Company | 2. James H Drew Corporation |
|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $22,780 | $30,180 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 10 | $2,000.00 | $5,345.00 |
| 0003 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 25 | $1,500.00 | $2,935.00 |
| 0004 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 |
| 0005 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $115,000 | $135,500 |
| 0009 | Handhole, remove (202-86946) | EACH | 32 | $1,420.00 | $2,410.00 |
| 0010 | Service point, remove (202-95579) | EACH | 2 | $1,560.00 | $2,410.00 |
| 0011 | Excavation, common (203-02000) | CYS | 54 | $250.00 | $226.00 |
| 0012 | B borrow (211-02050) | CYS | 30 | $400.00 | $604.00 |
| 0013 | Compacted aggregate, no. 53 (303-01180) | TON | 72 | $250.00 | $377.00 |
| 0014 | Riprap, class 1 (616-05688) | TON | 23 | $400.00 | $490.00 |
| 0015 | Mobilization and demobilization for seeding (621-01004) | EACH | 10 | $550.00 | $830.00 |
| 0016 | Mulched seeding, type U (621-06560) | SYS | 650 | $21.50 | $32.50 |
| 0017 | Sodding (621-06574) | SYS | 125 | $40.15 | $60.50 |
| 0018 | Field office, type C (628-09403) | MOS | 24 | $4,500.00 | $8,500.00 |
| 0019 | Computer system equipment (628-11976) | EACH | 1 | $2,000.00 | $1,630.00 |
| 0020 | Construction sign, type A (801-06640) | EACH | 80 | $254.00 | $377.00 |
| 0021 | Construction sign, type B (801-06645) | EACH | 10 | $127.00 | $151.00 |
| 0022 | Flashing arrow sign (801-06710) | DAY | 20 | $17.00 | $75.50 |
| 0023 | Maintaining traffic (801-06775) | LS | 1 | $380,000 | $224,950 |
| 0024 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,000 | $49.00 | $74.00 |
| 0025 | Portable changeable message sign (801-11642) | EACH | 5 | $5,383.00 | $7,545.00 |
| 0026 | Truck mounted attenuator (801-12042) | DAY | 100 | $400.00 | $377.00 |
| 0027 | Law enforcement officer (801-12324) | HRS | 40 | $60.00 | $60.00 |
| 0028 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 16 | $921.00 | $2,265.00 |
| 0029 | Transportation of salvageable signal equipment (805-02087) | LS | 1 | $1,490.00 | $7,225.00 |
| 0030 | Conduit , 1 steel, galvanized, 2 in., trench (805-04973) | LFT | 30 | $37.40 | $88.00 |
| 0031 | Conduit , 2 HDPE, 1.5 in., SCH 80, bore (805-04973) | LFT | 1,195 | $62.70 | $46.50 |
| 0032 | Conduit , 2 HDPE, 1.5 in., SCH 80, trench (805-04973) | LFT | 15 | $31.10 | $41.00 |
| 0033 | Conduit , 2 HDPE, 2 in., SCH 80, trench (805-04973) | LFT | 164 | $32.30 | $41.00 |
| 0034 | Conduit , 2 steel, galvanized, 2 in., trench (805-04973) | LFT | 18 | $74.40 | $60.50 |
| 0035 | Conduit , 3 HDPE, 1.5 in., SCH 80, bore (805-04973) | LFT | 1,462 | $59.70 | $57.50 |
| 0036 | Conduit , HDPE, 2 in., SCH 80 (805-04973) | LFT | 138 | $22.80 | $38.00 |
| 0037 | Conduit , HDPE, 2 in., SCH 80, bore (805-04973) | LFT | 928 | $94.60 | $51.00 |
| 0038 | Conduit , HDPE, 2 in., SCH 80, trench (805-04973) | LFT | 190 | $20.90 | $38.00 |
| 0039 | Conduit , HDPE, 3 in., SCH 80 (805-04973) | LFT | 6 | $22.50 | $85.50 |
| 0040 | Controller cabinet foundation, type M (805-78930) | EACH | 4 | $3,510.00 | $5,280.00 |
| 0041 | Wire , XHHW, no. 2 copper, 1 I/C, green jacket (807-04651) | LFT | 1,695 | $4.80 | $10.50 |
| 0042 | Wire , XHHW, no. 2 copper, 3 I/C (807-04651) | LFT | 1,695 | $14.40 | $28.00 |
| 0043 | Handhole, ATMS (807-12733) | EACH | 15 | $2,610.00 | $3,550.00 |
| 0044 | Cable-duct marker , flexible (807-86955) | EACH | 30 | $295.00 | $301.00 |
| 0045 | Fusion splice (809-000108) | EACH | 1,524 | $25.90 | $44.00 |
| 0046 | ITS locator post (809-000109) | EACH | 7 | $433.00 | $2,500.00 |
| 0047 | ITS pole structure , 60 FT height (809-000110) | EACH | 1 | $42,810 | $37,160 |
| 0048 | ITS vault, torsion- assisted (809-000111) | EACH | 2 | $9,000.00 | $10,740 |
| 0049 | ITS core switch (809-000112) | EACH | 2 | $45,200 | $35,070 |
| 0050 | Drop cable, 12 fiber, SM , 1000 LFT (809-000116) | EACH | 1 | $2,150.00 | $3,920.00 |
| 0051 | Drop cable, 12 fiber, SM , 250 LFT (809-000116) | EACH | 4 | $646.00 | $2,785.00 |
| 0052 | Drop cable, 12 fiber, SM , 500 LFT (809-000116) | EACH | 3 | $1,150.00 | $3,165.00 |
| 0053 | Drop cable, 12 fiber, SM , 750 LFT (809-000116) | EACH | 3 | $1,640.00 | $3,540.00 |
| 0054 | Patch cord, SM, LC-SC, 3 FT , 3 FT (809-000117) | EACH | 22 | $43.30 | $216.00 |
| 0055 | Remote power switch (809-000119) | EACH | 8 | $745.00 | $934.00 |
| 0056 | Patch panel assembly, 96 port , 12 port 1U (809-000142) | EACH | 5 | $1,180.00 | $3,555.00 |
| 0057 | Patch panel assembly, 96 port , 12 port, wall mount (809-000142) | EACH | 6 | $498.00 | $3,555.00 |
| 0058 | Service point , ATMS, subpanel (809-04652) | EACH | 3 | $5,980.00 | $8,015.00 |
| 0059 | Service point , ATMS, 120/240V, overhead (809-04652) | EACH | 1 | $15,460 | $10,520 |
| 0060 | Splice enclosure (809-04969) | EACH | 8 | $1,980.00 | $2,800.00 |
| 0061 | Cable , cat 6A (809-04982) | LFT | 1,215 | $2.90 | $15.00 |
| 0062 | Cable , remove (809-04982) | LFT | 3,059 | $1.10 | $2.40 |
| 0063 | ITS pole structure foundation , CCTV monopole (809-06101) | EACH | 1 | $21,600 | $22,240 |
| 0064 | ITS controller cabinet , M stretch (809-08398) | EACH | 4 | $17,720 | $18,740 |
| 0065 | ITS , cabinet remove (809-09343) | EACH | 7 | $1,090.00 | $1,205.00 |
| 0066 | ITS , camera lowering arm assembly (809-09343) | EACH | 1 | $13,380 | $24,680 |
| 0067 | ITS , camera lowering arm replacement (809-09343) | EACH | 6 | $16,240 | $23,170 |
| 0068 | ITS , camera tower remove (809-09343) | EACH | 1 | $5,310.00 | $16,510 |
| 0069 | ITS , cellular modem assembly (809-09343) | EACH | 19 | $3,290.00 | $2,800.00 |
| 0070 | ITS , pole remove (809-09343) | EACH | 1 | $1,060.00 | $10,470 |
| 0071 | ITS , SFP transceiver, SM, medium range (809-09343) | EACH | 22 | $355.00 | $176.00 |
| 0072 | ITS , vault remove (809-09343) | EACH | 1 | $1,850.00 | $4,815.00 |
| 0073 | ITS , vehicle detector (809-09343) | EACH | 2 | $19,130 | $14,660 |
| 0074 | ITS field switch , isw 16804 (809-11707) | EACH | 11 | $4,070.00 | $4,020.00 |
| 0075 | Fiber optic cable , 288F microfiber (809-94971) | LFT | 25,348 | $6.00 | $7.10 |
| 0076 | Fiber optic cable , armored, 216F single mode (809-94971) | LFT | 28,538 | $5.10 | $6.30 |
| 0077 | Fiber optic cable , remove (809-94971) | LFT | 56,869 | $1.10 | $3.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of May 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.