Lexington Quarry Company: KYTC bid record
Lexington Quarry Company submitted 40 bids on Kentucky Transportation Cabinet contracts in the data, from 22 NOV 2019 to 03 SEP 2026, and was the low bidder on 35 of them (88%). When it was not low, its total sat a median +6.0% above the low bid.
- Owner
- Kentucky Transportation Cabinet
- Low bid volume
- $26,452,509
- Latest bid
- 03 SEP 2026
- Data through
- 22 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2019 | 1 | 1 | 100% |
| 2020 | 3 | 3 | 100% |
| 2021 | 7 | 7 | 100% |
| 2022 | 7 | 6 | 86% |
| 2023 | 9 | 7 | 78% |
| 2024 | 2 | 2 | 100% |
| 2025 | 7 | 6 | 86% |
| 2026 | 4 | 3 | 75% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Maintain & control traffic | LS A | 6 | 6 (100%) | $1,650.00 | $11,500 | |
| Asphalt pave milling & texturing | TON | 7 | 5 (71%) | $15.00 | $36.50 | |
| Asphalt material for tack | TON | 7 | 5 (71%) | $1.00 | $10.00 | |
| Maintain & control traffic | LS A A | 8 | 4 (50%) | $5,850.00 | $10,625 | |
| Leveling & wedging PG64-22 | TON | 6 | 4 (67%) | $69.88 | $94.00 | |
| Demobilization | LS A A | 5 | 4 (80%) | $4,705.00 | $10,682 | |
| Pave marking-thermo stop bar-24IN | LF | 8 | 3 (38%) | $11.89 | $14.00 | |
| Temporary signs | SF | 7 | 3 (43%) | $8.00 | $6.50 | |
| Pave striping-perm paint-4 in | LF | 7 | 3 (43%) | $0.23 | $0.29 | |
| Portable changeable message sign | EACH | 5 | 3 (60%) | $1,200.00 | $1,750.00 | |
| Pave marking-thermo curv arrow | EACH | 5 | 3 (60%) | $98.00 | $125.00 | |
| Temporary signs | SQFT A A | 5 | 2 (40%) | $10.00 | $6.05 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Mago Construction Company LLC | 12 | 5 of 12 |
| H G Mays Corporation | 7 | 3 of 7 |
| Strawser Construction Inc | 5 | 0 of 5 |
| American Pavements Inc | 4 | 0 of 4 |
| Strawser Construction Inc & Subsidiaries | 4 | 0 of 4 |
| Louisville Paving Company Inc | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 03 SEP 2026 | 26-2136 | ASPHALT RESURFACING US 60 & US 60X IN WOODFORD COUNTY | 3 of 4 | $1,581,735 | +4.0% | |
| 29 JAN 2026 | 26-2081 | PAVEMENT (WITH ALTERNATES) UNION MILL ROAD (KY 169) | 1 of 2 | $149,132 | Low, 62% under the second | |
| 29 JAN 2026 | 26-3008 | PAVEMENT (WITH ALTERNATES) VARIOUS ROADS IN JESSAMINE CO | 1 of 2 | $247,159 | Low, 73% under the second | |
| 29 JAN 2026 | 26-3007 | ASPHALT RESURFACING VARIOUS PROJECTS IN WOODFORD CO | 1 of 3 | $318,091 | Low, 2.0% under the second | |
| 20 NOV 2025 | 25-3134 | ASPHALT RESURFACING RIVER ROAD (KY 1541) | 1 of 1 | $232,541 | Low | |
| 24 JUL 2025 | 25-2302 | ASPHALT RESURFACING HARRODSBURG ROAD (US 68) | 1 of 1 | $915,614 | Low | |
| 24 JUL 2025 | 25-2258 | ASPHALT RESURFACING SOUTH MAIN STREET (US 27X) | 1 of 1 | $805,050 | Low | |
| 22 MAY 2025 | 25-2223 | ASPHALT RESURFACING LEXINGTON ROAD (US 60) | 1 of 2 | $327,156 | Low, 17% under the second | |
| 24 APR 2025 | 25-3024 | District 7 | ASPHALT RESURFACING HOOVER PIKE (KY 3374) | 1 of 1 | $154,936 | Low |
| 23 JAN 2025 | 25-2029 | District 7 | PAVEMENT (WITH ALTERNATES) WILMORE ROAD / WEST MAPLE STREET (KY 29) | 1 of 2 | $251,618 | Low, 34% under the second |
| 23 JAN 2025 | 25-2045 | District 7 | PAVEMENT (WITH ALTERNATES) PINKARD PIKE (KY 169) | 2 of 4 | $166,908 | +6.0% |
| 12 DEC 2024 | 24-3135 | District 7 | ASPHALT RESURFACING VARIOUS ROADS IN WOODFORD CO | 1 of 2 | $109,015 | Low, 18% under the second |
| 20 JUN 2024 | 24-2224 | District 7 | ASPHALT RESURFACING NICHOLASVILLE ROAD (US 27) | 1 of 1 | $1,666,598 | Low |
| 14 DEC 2023 | 23-3137 | District 7 | ASPHALT RESURFACING VARIOUS ROADS IN WOODFORD COUNTY | 3 of 3 | $476,055 | +18% |
| 26 OCT 2023 | 23-3133 | District 7 | PAVEMENT (WITH ALTERNATES) VARIOUS ROADS IN JESSAMINE CO | 1 of 2 | $315,780 | Low, 26% under the second |
| 28 SEP 2023 | 23-3113 | District 7 | ASPHALT RESURFACING LOGANA PIKE (KY1981) | 1 of 1 | $127,089 | Low |
| 28 SEP 2023 | 23-2440 | District 7 | ASPHALT PAVEMENT & ROADWAY REHAB CATNIP HILL ROAD (KY 3375) | 1 of 1 | $1,314,883 | Low |
| 22 JUN 2023 | 23-2357 | District 7 | ASPHALT PAVEMENT & ROADWAY REHAB CATNIP HILL ROAD (KY 3375) | 1 of 1 | $1,357,038 | Low |
| 27 APR 2023 | 23-2145 | District 7 | ASPHALT PAVEMENT & ROADWAY REHAB CATNIP HILL ROAD (KY 3375) | 1 of 1 | $1,367,375 | Low |
| 27 APR 2023 | 23-3022 | District 7 | PAVEMENT (WITH ALTERNATES) LITTLE HICKMAN RD (KY 1268) | 1 of 1 | $61,383 | Low |
| 23 MAR 2023 | 23-2014 | District 7 | ASPHALT RESURFACING HARRODSBURG ROAD (US 68) | 1 of 1 | $1,994,297 | Low |
| 26 JAN 2023 | 23-3012 | District 7 | ASPHALT RESURFACING VARIOUS ROADS IN WOODFORD CO | 3 of 3 | $293,387 | +34% |
| 22 SEP 2022 | 22-3074 | District 7 | ASPHALT RESURFACING LOGANA PIKE (KY1981) | 1 of 1 | $124,800 | Low |
| 21 JUL 2022 | 22-1037 | District 7 | ASPHALT REHAB INTERSTATE/PARKWAY BLUEGRASS PARKWAY (PW-9002) | 1 of 2 | $268,729 | Low, 11% under the second |
| 26 MAY 2022 | 22-2372 | District 7 | ASPHALT RESURFACING NICHOLASVILLE ROAD (US 27) | 1 of 1 | $1,454,193 | Low |
How this record was read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; KYTC's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.