Oglesby Construction Inc: KYTC bid record
Oglesby Construction Inc submitted 94 bids on Kentucky Transportation Cabinet contracts in the data, from 24 JAN 2020 to 19 FEB 2026, and was the low bidder on 21 of them (22%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Kentucky Transportation Cabinet
- Low bid volume
- $49,131,683
- Latest bid
- 19 FEB 2026
- Data through
- 22 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 19 | 5 | 26% |
| 2021 | 13 | 0 | 0% |
| 2022 | 14 | 7 | 50% |
| 2023 | 12 | 2 | 17% |
| 2024 | 12 | 2 | 17% |
| 2025 | 12 | 4 | 33% |
| 2026 | 12 | 1 | 8% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 9 | 8 | 1 | 13% |
| District 10 | 8 | 4 | 50% |
| District 12 | 8 | 4 | 50% |
| District 5 | 8 | 4 | 50% |
| District 6 | 8 | 2 | 25% |
| District 8 | 7 | 2 | 29% |
| District 1 | 6 | 0 | 0% |
| District 3 | 6 | 0 | 0% |
| District 11 | 6 | 2 | 33% |
| District 2 | 6 | 0 | 0% |
| District 4 | 6 | 1 | 17% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Law enforcement officer | HR | 67 | 57 (85%) | $90.00 | $85.00 | |
| Pave striping-WB paint-4 in W | MI | 136 | 42 (31%) | $506.50 | $508.00 | |
| Pave striping-WB paint-4 in Y | MI | 136 | 30 (22%) | $570.00 | $550.00 | |
| Water blasting existing stripe | LF | 67 | 24 (36%) | $6.00 | $2.00 | |
| Durable waterborne marking-6 in W | MI | 54 | 19 (35%) | $1,257.50 | $1,257.50 | |
| Durable waterborne marking-6 in Y | MI | 54 | 18 (33%) | $1,370.00 | $1,365.00 | |
| Pave striping-WB paint-6 in W | MI | 32 | 13 (41%) | $830.00 | $810.00 | |
| Law enforcement officer | HOUR A | 12 | 12 (100%) | $100.00 | $100.00 | |
| Pave striping-WB paint-6 in Y | MI | 32 | 9 (28%) | $912.80 | $900.00 | |
| Pave striping-WB paint-4 in Y | MILE A | 25 | 9 (36%) | $575.00 | $575.00 | |
| Pave striping-WB paint-4 in W | MILE A | 25 | 8 (32%) | $545.00 | $535.00 | |
| Water blasting existing stripe | LF A A | 8 | 8 (100%) | $3.00 | $1.25 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Reynolds-Central Seal A Joint Venture | 93 | 70 of 93 |
| Pavement Marking Specialist LLC | 14 | 4 of 14 |
| Mullen'S Markings Inc | 12 | 3 of 12 |
| A & A Safety Inc | 3 | 2 of 3 |
| The Aero-Mark Company LLC DBA Pavement Marking Specialist LL | 3 | 0 of 3 |
| M & M Services Co Inc | 1 | 0 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 19 FEB 2026 | 26-2002 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 2 | 1 of 4 | $3,211,145 | Low, 1.0% under the second | |
| 19 FEB 2026 | 26-2004 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 4 | 2 of 4 | $1,204,499 | +8.0% | |
| 19 FEB 2026 | 26-2006 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 6 | 2 of 4 | $4,273,450 | +4.0% | |
| 19 FEB 2026 | 26-2008 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 8 | 3 of 4 | $1,469,000 | +10% | |
| 19 FEB 2026 | 26-2010 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 10 | 3 of 4 | $1,744,361 | +4.0% | |
| 19 FEB 2026 | 26-2012 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 12 | 2 of 4 | $1,644,000 | +10% | |
| 29 JAN 2026 | 26-2001 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 1 | 2 of 4 | $1,537,471 | +11% | |
| 29 JAN 2026 | 26-2003 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 3 | 3 of 4 | $2,148,389 | +31% | |
| 29 JAN 2026 | 26-2005 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 5 | 2 of 4 | $3,996,743 | +2.0% | |
| 29 JAN 2026 | 26-2007 | PAINTED PAVEMENT STRIPING VARIOUS ROUTES IN DISTRICT 7 & DISTRICT 6 (OWEN COUNTY) | 3 of 4 | $2,144,769 | +34% | |
| 29 JAN 2026 | 26-2009 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 9 | 2 of 4 | $398,203 | +5.0% | |
| 29 JAN 2026 | 26-2011 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 11 (& 10 PERRY COUNTY KY 484) | 2 of 4 | $3,044,386 | +4.0% | |
| 20 FEB 2025 | 25-2002 | District 2 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 2 | 2 of 2 | $2,181,167 | +10% |
| 20 FEB 2025 | 25-2004 | District 4 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 4 | 1 of 2 | $1,565,274 | Low, 2.0% under the second |
| 20 FEB 2025 | 25-2006 | District 6 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 6 | 2 of 2 | $4,971,607 | +5.0% |
| 20 FEB 2025 | 25-2008 | District 8 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 8 | 1 of 2 | $1,390,444 | Low, 5.0% under the second |
| 20 FEB 2025 | 25-2010 | District 10 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 10 | 1 of 2 | $1,654,968 | Low, 7.0% under the second |
| 20 FEB 2025 | 25-2012 | District 12 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 12 | 1 of 2 | $1,069,959 | Low, 6.0% under the second |
| 23 JAN 2025 | 25-2011 | District 11 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 11 | 2 of 2 | $2,779,650 | +4.0% |
| 23 JAN 2025 | 25-2001 | District 1 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 1 | 2 of 2 | $2,373,245 | +10% |
| 23 JAN 2025 | 25-2003 | District 3 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 3 | 2 of 2 | $1,814,896 | +10% |
| 23 JAN 2025 | 25-2005 | District 5 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 5 | 2 of 2 | $4,749,968 | +1.0% |
| 23 JAN 2025 | 25-2007 | District 7 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 7 | 2 of 2 | $2,055,371 | +23% |
| 23 JAN 2025 | 25-2009 | District 9 | WATERBOURNE PAINT STRIPING VARIOUS ROADS IN DISTRICT 9 | 2 of 3 | $639,649 | +1.0% |
| 22 FEB 2024 | 24-2002 | District 2 | WATERBOURNE PAINT STRIPING VARIOUS ROUTES IN DISTRICT 2 | 2 of 2 | $4,529,876 | +14% |
How this record was read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; KYTC's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.