KYTC contract 25-1006 bid tabulation

WIDENING BETHEL GROVE-BETHEL CHURCH ROAD(KY-56). Let by Kentucky Transportation Cabinet on March 20, 2025, Mclean, District 2. 3 bids received; low bid $1,338,618 by Scotty'S Contracting & Stone LLC, -40% against the engineer's estimate of $2,239,704.

Owner
Kentucky Transportation Cabinet
Letting
20 MAR 2025
Pay items
75
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Scotty'S Contracting & Stone LLC$1,338,618Low-40%
2Envision Contractors LLC$2,172,603+62%-3.0%
3Cleary Construction Inc$2,275,000+70%+2.0%
KYTC contract 25-1006: bids by rank

Engineer's estimate: $2,239,704.

Bid tabulation

LinePay itemUnitQuantity1. Scotty'S Contracting & Stone LLC2. Envision Contractors LLC3. Cleary Construction Inc
0010Crushed stone baseTON A1,705$36.89$48.59$58.65
0020Crushed aggregate size no 2TON A2,957$39.81$46.52$51.00
0030Asphalt seal aggregateTON A28$197.01$350.00$350.00
0040Asphalt seal coatTON A5$891.11$1,000.00$1,000.00
0050Leveling & wedging PG64-22TON A19$166.78$185.00$185.00
0060CL2 asph base 0.75D PG64-22TON A1,119$114.75$156.20$153.85
0070CL2 asph surf 0.50D PG64-22TON A482$115.28$161.79$158.65
0080Asphalt material for tackTON A7$696.19$200.00$200.00
0090Joint adhesiveLF A3,200$1.50$1.50$1.50
0100Perforated pipe-4 inLF A54$7.72$72.40$30.00
0110Non-perforated pipe-4 inLF A20$15.96$73.27$38.00
0120Perf pipe headwall TY 3-4 inEACH A2$466.69$1,328.36$1,300.00
0130Remove pavementSQYD A45$16.31$15.68$85.00
0140Temp ditchLF A750$0.01$1.93$1.00
0150Clean temp ditchLF A375$0.01$0.97$0.01
0160Roadway excavationCUYD A30,520$10.38$22.88$29.00
0170WaterMGAL A60$0.01$150.00$0.01
0180Right-of-way monument type 1EACH A12$225.75$158.02$160.00
0190Witness postEACH A3$134.38$131.00$125.00
0200Plug water wellEACH A1$8,500.00$3,500.00$5,000.00
0210Channel lining class IITON A255$56.02$60.64$88.00
0220Clearing and grubbingLS A1$23,983$180,500$54,000
0230Temporary signsSQFT A150$6.38$33.21$15.00
0240Edge keyLF A62$28.85$63.75$63.75
0250Fabric-geotextile class 1SQYD A4,032$2.52$2.85$3.00
0260Fabric-geotextile class 1ASQYD A4,032$3.65$4.68$4.25
0270Fabric-geotextile class 2 for pipeSQYD A363$2.00$2.00$2.00
0280Maintain & control trafficLS A1$18,977$154,833$135,000
0290Portable changeable message signEACH A2$4,442.34$6,283.03$4,500.00
0300SafeloadingCUYD A8.25$344.33$500.00$400.00
0310Edgeline rumble stripsLF A2,867$1.75$1.85$1.75
0320Temp silt fenceLF A750$1.82$10.52$3.00
0330Silt trap type AEACH A3$0.01$451.52$300.00
0340Silt trap type BEACH A3$492.89$454.56$160.00
0350Silt trap type CEACH A3$0.01$242.85$285.00
0360Clean silt trap type AEACH A3$0.01$144.76$1.00
0370Clean silt trap type BEACH A3$129.00$144.76$1.00
0380Clean silt trap type CEACH A3$0.01$154.52$1.00
0390StakingLS A1$13,254$21,528$65,000
0400Erosion control blanketSQYD A1,242$1.85$2.71$1.85
0410Temp mulchSQYD A9,200$0.25$0.39$0.25
0420Temp seeding and protectionSQYD A6,900$0.35$0.41$0.35
0430Initial fertilizerTON A0.60$1,500.00$1,231.50$1,500.00
0440Maintenance fertilizerTON A1.10$1,500.00$1,231.50$1,500.00
0450Seeding and protectionSQYD A20,300$0.40$0.71$0.40
0460Agricultural limestoneTON A9$85.00$71.23$85.00
0470Pave striping-temp paint-4 inLF A1,535$0.50$0.50$0.50
0480Pave striping-perm paint-6 inLF A5,129$0.40$0.40$0.40
0490Pave marking-thermo stop bar-24INLF A9$20.00$20.00$20.00
0500Fuel adjustmentDOLL A4,945$1.00$1.00$1.00
0510Joint adhesiveLF A3,200$1.50$1.50$1.50
0520Temporary pipeLF A100$73.90$132.79$100.00
0530Centerline rumble stripsLF A1,500$2.25$2.35$2.25
0540Remove-store and reinstall signEACH A17$134.38$564.92$350.00
0550Longitudinal edge keyLF A330$25.70$48.75$48.75
0560Entrance pipe-18 inLF A236$80.49$144.73$110.00
0570Sloped and mitered headwall-18 inEACH A10$2,800.00$2,800.00$3,500.00
0580Remove concrete masonryCUYD A1$350.00$350.00$8,500.00
0590Structure excav-solid rockCUYD A13$350.00$350.00$550.00
0600Foundation preparationLS A1$6,000.00$6,000.00$20,000
0610Concrete-class ACUYD A37.10$1,700.00$1,700.00$1,700.00
0620Steel reinforcementLB A3,695$1.75$1.75$4.00
0630SafeloadingCUYD A1.25$100.00$1,533.51$2,000.00
0640W air release valve 1 inchEACH A1$6,000.00$6,353.30$6,206.00
0650W cap existing mainEACH A4$3,000.00$933.15$1,200.00
0660W directional boreLF A150$435.00$160.10$300.00
0670W flush hydrant assemblyEACH A1$12,000$8,926.16$13,303
0680W pipe PVC 06 inchLF A885$118.00$73.11$86.50
0690W pipe polyethylene/plastic 06 inchLF A150$75.00$104.72$78.00
0700W tie-in 06 inchEACH A3$3,220.00$5,328.66$4,378.00
0710W valve 06 inchEACH A4$2,950.00$3,644.59$2,636.00
0720W valve specialEACH A3$10,000$19,167$11,775
0730W valve box removeEACH A3$100.00$726.43$500.00
0740W encasement steel open cut range 3 instLF A70$550.00$451.63$250.00
0750DemobilizationLS A1$20,103$32,292$35,577
KYTC contract 25-1006: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of March 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy