KYTC contract 25-1009 bid tabulation
ASPHALT REHAB WITH BRIDGE (S) I-64. Let by Kentucky Transportation Cabinet on April 24, 2025, Franklin, District 5. 2 bids received; low bid $10,498,241 by H G Mays Corporation, -6.5% against the engineer's estimate of $11,222,294.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 APR 2025
- Pay items
- 82
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | H G Mays Corporation | $10,498,241 | Low | -6.0% |
| 2 | Louisville Paving Company Inc | $11,677,792 | +11% | +4.0% |
Engineer's estimate: $11,222,294.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. H G Mays Corporation | 2. Louisville Paving Company Inc |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A | 2,430 | $40.00 | $53.00 |
| 0020 | Asphalt seal aggregate | TON A | 577 | $110.00 | $99.00 |
| 0030 | Asphalt seal coat | TON A | 70 | $1,000.00 | $275.00 |
| 0040 | Leveling & wedging PG76-22 | TON A | 227 | $243.00 | $95.00 |
| 0050 | CL3 asph base 1.00D PG76-22 | TON A | 10,600 | $80.00 | $99.00 |
| 0060 | CL4 asph base 1.00D PG76-22 | TON A | 29,680 | $80.00 | $100.00 |
| 0070 | CL3 asph surf 0.38D PG64-22 | TON A | 4,543 | $88.00 | $95.00 |
| 0080 | CL4 asph surf 0.38A PG76-22 | TON A | 14,560 | $98.50 | $106.00 |
| 0090 | Asphalt material for tack | TON A | 219 | $1.00 | $0.01 |
| 0100 | Asphalt pave milling & texturing | TON A | 36,434 | $14.50 | $12.00 |
| 0110 | Joint adhesive | LF A | 100,062 | $0.75 | $0.47 |
| 0120 | Pave mount infrared temp equipment | SF A | 3,967,174 | $0.01 | $0.01 |
| 0140 | Sloped box outlet type 1-18 in | EACH A | 1 | $4,000.00 | $4,100.00 |
| 0150 | Drop box inlet type 5A | EACH A | 1 | $9,000.00 | $9,500.00 |
| 0160 | Flume inlet type 1 | EACH A | 2 | $7,500.00 | $6,286.37 |
| 0170 | Remove curb & gutter box inlet | EACH A | 4 | $500.00 | $1,800.00 |
| 0180 | Island header curb type 1 | LF A | 100 | $75.00 | $72.37 |
| 0190 | Delineator for guardrail mono directional white | EACH A | 33 | $16.03 | $16.03 |
| 0200 | Delineator for guardrail mono directional yello | EACH A | 290 | $16.03 | $16.03 |
| 0210 | Relocate temp conc barrier | LF A | 2,739 | $2.00 | $27.37 |
| 0220 | Roadway excavation | CUYD A | 650 | $35.00 | $90.00 |
| 0230 | Guardrail-steel W beam-S face | LF A | 14,838 | $30.46 | $30.46 |
| 0240 | Guardrail end treatment type 1 | EACH A | 13 | $3,698.29 | $3,698.29 |
| 0250 | Guardrail end treatment type 2A | EACH A | 11 | $1,361.80 | $1,361.80 |
| 0260 | Remove guardrail con to BR end | EACH A | 27 | $359.11 | $359.11 |
| 0270 | Remove guardrail | LF A | 15,318 | $3.23 | $3.23 |
| 0280 | Guardrail end treatment type 4A | EACH A | 3 | $3,863.84 | $3,863.84 |
| 0285 | Remove concrete masonry | CUYD A | 104 | $445.00 | $105.23 |
| 0290 | Temporary signs | SQFT A | 3,000 | $7.42 | $5.00 |
| 0300 | Ditching and shouldering | LF A | 24,779 | $13.96 | $16.50 |
| 0310 | Maintain & control traffic | LS A | 1 | $526,702 | $433,000 |
| 0320 | Truck mounted attenuator | EACH A | 2 | $3,710.00 | $2,120.00 |
| 0330 | Portable changeable message sign | EACH A | 5 | $8,165.00 | $636.00 |
| 0340 | Mobilization for mill & text | LS A | 1 | $2,500.00 | $7,500.00 |
| 0350 | Safeloading | CUYD A | 12 | $400.00 | $450.00 |
| 0360 | Shoulder rumble strips | LF A | 113,571 | $0.13 | $0.13 |
| 0370 | Staking | LS A | 1 | $50,000 | $10,000 |
| 0380 | Relocate crash cushion | EACH A | 2 | $3,616.72 | $3,616.72 |
| 0390 | Conc barrier wall type 9T | LF A | 2,739 | $25.00 | $37.00 |
| 0400 | Pave striping-temp paint-6 in | LF A | 262,376 | $0.35 | $0.35 |
| 0410 | Pave striping-thermo-6 in W | LF A | 69,967 | $1.30 | $1.30 |
| 0420 | Pave striping-thermo-6 in Y | LF A | 54,381 | $1.30 | $1.30 |
| 0430 | Pave striping-thermo-12 in W | LF A | 3,616 | $2.60 | $2.60 |
| 0432 | Pave striping-dur TY 1-6 in W | LF A | 900 | $9.00 | $9.00 |
| 0434 | Pave striping-dur TY 1-6 in Y | LF A | 600 | $9.00 | $9.00 |
| 0440 | Inlaid pavement marker-B W/R | EACH A | 729 | $35.00 | $35.00 |
| 0450 | Inlaid pavement marker-B Y/R | EACH A | 57 | $35.00 | $35.00 |
| 0470 | Fuel adjustment | DOLL A | 92,786 | $1.00 | $1.00 |
| 0480 | Asphalt adjustment | DOLL A | 233,051 | $1.00 | $1.00 |
| 0490 | Object marker TY 3 | EACH A | 13 | $37.72 | $38.00 |
| 0495 | Remove crash cushion | EACH A | 2 | $1,414.79 | $1,414.79 |
| 0496 | Bore and jack pipe-18 in | LF A | 94 | $750.00 | $940.00 |
| 0500 | End anchors | EACH A | 1 | $16,761 | $16,761 |
| 0505 | Crash cushion TY VI class C TL3 | EACH A | 4 | $8,831.82 | $8,832.00 |
| 0510 | Remove cable guardrail barrier system | LF A | 135 | $6.72 | $6.72 |
| 0520 | Pave mark thermo-wrong way arrow | EACH A | 4 | $350.00 | $350.00 |
| 0530 | Queue protection vehicle | HOUR A | 250 | $75.00 | $75.00 |
| 0540 | Thrie beam guardrail transition TL-3 | EACH A | 27 | $4,003.33 | $3,201.61 |
| 0550 | Furnish queue protection vehicles | MONT A | 8 | $10,000 | $4,717.00 |
| 0560 | Portable queue warning alert system | MONT A | 8 | $3,000.00 | $1,484.00 |
| 0570 | Queue warning PCMS | MONT A | 32 | $550.00 | $530.00 |
| 0580 | Queue warning portable radar sensors | MONT A | 32 | $50.00 | $1.00 |
| 0590 | Mobilization for concrete surf treatment | LS A | 1 | $1,000.00 | $72,123 |
| 0600 | Thrie beam bullnose terminal | EACH A | 6 | $28,705 | $28,705 |
| 0610 | Connected arrow panel | MONT A | 8 | $312.50 | $1,272.00 |
| 0620 | Structure excavation-common | CUYD A | 106 | $95.00 | $60.00 |
| 0630 | Concrete-class A | CUYD A | 198 | $1,230.00 | $1,925.00 |
| 0640 | Steel reinforcement | LB A | 9,444 | $3.60 | $2.25 |
| 0650 | Bridge barrier retrofit | LF A | 1,360 | $425.00 | $425.00 |
| 0660 | Concrete sealing | SQFT A | 7,452 | $3.00 | $2.75 |
| 0670 | Concrete coating | SQFT A | 10,880 | $3.60 | $40.00 |
| 0680 | Conduit-1 1/4 in | LF A | 80 | $6.44 | $14.00 |
| 0690 | Conduit-2 in | LF A | 20 | $8.93 | $18.00 |
| 0700 | Trenching and backfilling | LF A | 90 | $15.00 | $7.67 |
| 0710 | Piezoelectric sensor | EACH A | 4 | $4,500.00 | $2,562.96 |
| 0720 | Loop wire | LF A | 1,680 | $0.25 | $0.86 |
| 0730 | Loop saw slot and fill | LF A | 400 | $29.85 | $30.78 |
| 0740 | Galvanized steel cabinet | EACH A | 2 | $1,000.85 | $1,145.90 |
| 0750 | Wood post | EACH A | 4 | $500.00 | $570.59 |
| 0760 | Electrical junction box type A | EACH A | 2 | $3,500.00 | $1,459.79 |
| 0770 | Mobilization | LS A | 1 | $414,013 | $296,050 |
| 0780 | Demobilization | LS A | 1 | $150,700 | $174,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of April 24, 2025. Compiled by Mirage Metrics.