KYTC contract 25-1035 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE FAIRVIEW DRIVE (KY298) / FOORS LANE (KY3143). Let by Kentucky Transportation Cabinet on November 20, 2025. 2 bids received; low bid $3,215,724 by Ragle Inc, +5.2% against the engineer's estimate of $3,057,971.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 NOV 2025
- Pay items
- 129
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ragle Inc | $3,215,724 | Low | +5.0% |
| 2 | Scotty'S Contracting & Stone LLC | $3,364,673 | +5.0% | +10% |
Engineer's estimate: $3,057,971.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ragle Inc | 2. Scotty'S Contracting & Stone LLC |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 1,510 | $77.50 | $61.63 |
| 0020 | Leveling & wedging PG76-22 | TON A A | 304 | $130.75 | $130.75 |
| 0030 | CL3 asph base 1.00D PG64-22 | TON A A | 825 | $105.75 | $105.75 |
| 0040 | CL3 asph base 1.00D PG76-22 | TON A A | 635 | $119.50 | $119.50 |
| 0050 | CL3 asph surf 0.50B PG64-22 | TON A A | 161 | $130.75 | $130.75 |
| 0060 | CL3 asph surf 0.50B PG76-22 | TON A A | 532 | $130.75 | $130.75 |
| 0070 | JPC pavement-8 in | SQYD A A | 247 | $153.50 | $168.96 |
| 0080 | Cem conc ent pavement-8 in | SQYD A A | 391 | $91.75 | $123.41 |
| 0090 | Mobilization for mill & text | LS A A | 1 | $10,000 | $10,000 |
| 0100 | Asphalt pave milling & texturing | TON A A | 151 | $171.87 | $125.00 |
| 0110 | Sidewalk-4 in concrete | SQYD A A | 311 | $104.50 | $119.75 |
| 0120 | Joint adhesive | LF A A | 2,130 | $1.75 | $1.75 |
| 0130 | Asphalt material for tack non-tracking | TON A A | 4.39 | $10.00 | $10.00 |
| 0140 | Crushed aggregate size no 2 | TON A A | 3,979 | $58.38 | $50.13 |
| 0150 | Inspect & certify edge drain system | LS A A | 1 | $7,500.00 | $2,500.00 |
| 0160 | Remove pipe | LF A A | 379 | $40.73 | $8.74 |
| 0170 | Remove drop box inlet | EACH A A | 1 | $476.51 | $985.24 |
| 0180 | Remove manhole | EACH A A | 1 | $2,233.00 | $985.24 |
| 0190 | Adjust manhole frame to grade | EACH A A | 3 | $600.00 | $499.88 |
| 0200 | Standard curb and gutter | LF A A | 2,693 | $36.95 | $33.44 |
| 0210 | Island curb and gutter | LF A A | 420 | $41.85 | $35.09 |
| 0220 | Standard header curb | LF A A | 370 | $28.85 | $34.42 |
| 0230 | Barricade-type III | EACH A A | 10 | $125.00 | $392.38 |
| 0240 | Remove pavement | SQYD A A | 101 | $22.50 | $18.01 |
| 0250 | Cem conc ent pavement-8 in | SQYD A A | 215 | $92.50 | $123.41 |
| 0260 | Temp ditch | LF A A | 6,778 | $1.00 | $0.01 |
| 0270 | Clean temp ditch | LF A A | 3,389 | $0.50 | $0.01 |
| 0280 | Roadway excavation | CUYD A A | 6,806 | $32.00 | $49.50 |
| 0290 | Water | MGAL A A | 357 | $21.90 | $0.01 |
| 0300 | Remove guardrail | LF A A | 115 | $5.57 | $5.57 |
| 0310 | Right-of-way monument type 1 | EACH A A | 21 | $491.26 | $275.20 |
| 0320 | Witness post | EACH A A | 21 | $161.46 | $161.25 |
| 0330 | Clearing and grubbing | LS A A | 1 | $40,250 | $68,864 |
| 0340 | Temporary signs | SQFT A A | 275 | $17.96 | $11.65 |
| 0350 | Edge key | LF A A | 112 | $12.00 | $95.00 |
| 0360 | Fabric-geotextile class 2 | SQYD A A | 578 | $4.00 | $3.12 |
| 0370 | Fabric-geotextile class 4A | SQYD A A | 10,401 | $3.84 | $3.84 |
| 0380 | Remove headwall | EACH A A | 4 | $415.00 | $458.60 |
| 0390 | Maintain & control traffic | LS A A | 1 | $60,340 | $194,341 |
| 0400 | Portable changeable message sign | EACH A A | 4 | $4,970.00 | $9,180.72 |
| 0410 | Safeloading | CUYD A A | 13 | $775.00 | $400.00 |
| 0420 | Temp silt fence | LF A A | 6,778 | $4.00 | $1.97 |
| 0430 | Silt trap type A | EACH A A | 5 | $227.00 | $164.48 |
| 0440 | Silt trap type B | EACH A A | 5 | $415.00 | $604.15 |
| 0450 | Silt trap type C | EACH A A | 5 | $347.00 | $379.48 |
| 0460 | Clean silt trap type A | EACH A A | 5 | $55.00 | $0.01 |
| 0470 | Clean silt trap type B | EACH A A | 5 | $37.50 | $0.01 |
| 0480 | Clean silt trap type C | EACH A A | 5 | $50.00 | $0.01 |
| 0490 | Staking | LS A A | 1 | $70,120 | $56,764 |
| 0500 | Conc barrier wall type 9T | LF A A | 250 | $42.00 | $145.35 |
| 0510 | Erosion control blanket | SQYD A A | 1,286 | $3.16 | $1.75 |
| 0520 | Temp mulch | SQYD A A | 17,025 | $0.25 | $0.25 |
| 0530 | Temp seeding and protection | SQYD A A | 12,705 | $0.38 | $0.30 |
| 0540 | Initial fertilizer | TON A A | 0.80 | $1,032.00 | $1,500.00 |
| 0550 | Maintenance fertilizer | TON A A | 1.30 | $1,032.00 | $1,500.00 |
| 0560 | Seeding and protection | SQYD A A | 25,410 | $0.48 | $0.42 |
| 0570 | Sodding | SQYD A A | 1,572 | $9.78 | $9.00 |
| 0580 | Agricultural limestone | TON A A | 15.80 | $104.00 | $85.00 |
| 0590 | Pave striping-temp paint-4 in | LF A A | 8,363 | $0.32 | $0.32 |
| 0600 | Pave striping-perm paint-4 in | LF A A | 8,363 | $0.35 | $0.35 |
| 0610 | Pave striping-thermo-12 in W | LF A A | 50 | $10.00 | $10.00 |
| 0620 | Pave marking-thermo stop bar-24IN | LF A A | 33 | $20.00 | $20.00 |
| 0630 | Pave marking-thermo cross-hatch | SQFT A A | 172 | $10.00 | $10.00 |
| 0640 | Pave marking-thermo STR arrow | EACH A A | 8 | $150.00 | $150.00 |
| 0650 | Pave marking-thermo curv arrow | EACH A A | 3 | $150.00 | $150.00 |
| 0660 | Pave marking-thermo comb arrow | EACH A A | 10 | $300.00 | $300.00 |
| 0670 | Fuel adjustment | DOLL A A | 13,460 | $1.00 | $1.00 |
| 0680 | Asphalt adjustment | DOLL A A | 23,305 | $1.00 | $1.00 |
| 0690 | Longitudinal edge key | LF A A | 2,002 | $1.20 | $7.10 |
| 0700 | Wood plank fence | LF A A | 250 | $60.28 | $35.72 |
| 0710 | Pave marking-thermo yield bar-36 in | LF A A | 72 | $20.00 | $20.00 |
| 0720 | Pave mark temp paint stop bar-24 in | LF A A | 350 | $5.00 | $5.00 |
| 0730 | Turf reinforcement mat 1 | SQYD A A | 389 | $7.24 | $7.00 |
| 0740 | Pipeline inspection | LF A A | 2,015 | $2.00 | $2.35 |
| 0750 | Electronic delivery MGMT system - agg | LS A A | 1 | $1.00 | $0.01 |
| 0760 | Storm sewer pipe-18 in | LF A A | 1,173 | $197.00 | $132.64 |
| 0770 | Storm sewer pipe-24 in | LF A A | 534 | $241.00 | $162.56 |
| 0780 | Storm sewer pipe-30 in | LF A A | 252 | $246.00 | $234.24 |
| 0790 | Storm sewer pipe-36 in | LF A A | 56 | $300.00 | $479.77 |
| 0800 | Perforated pipe-4 in | LF A A | 775 | $23.75 | $20.59 |
| 0810 | Perforated pipe edge drain-4 in | LF A A | 2,537 | $13.50 | $13.90 |
| 0820 | Non-perforated pipe-4 in | LF A A | 180 | $28.75 | $32.21 |
| 0830 | Curb box inlet type A | EACH A A | 8 | $8,500.00 | $6,800.00 |
| 0840 | Drop box inlet type 3 | EACH A A | 9 | $7,500.00 | $6,200.00 |
| 0850 | Drop box inlet type 13G | EACH A A | 1 | $7,000.00 | $6,000.00 |
| 0860 | Drop box inlet type 13S | EACH A A | 5 | $9,500.00 | $8,000.00 |
| 0870 | Junction box-24 in | EACH A A | 2 | $3,812.00 | $3,500.00 |
| 0880 | Cored hole drainage box con-4 in | EACH A A | 19 | $139.00 | $300.00 |
| 0890 | Manhole type A | EACH A A | 4 | $9,440.00 | $5,000.00 |
| 0900 | Fabric-geotextile class 2 for pipe | SQYD A A | 6,737 | $2.00 | $2.00 |
| 0910 | Sloped and mitered headwall-18 in | EACH A A | 1 | $2,201.00 | $3,200.00 |
| 0920 | Sloped and mitered headwall-24 in | EACH A A | 1 | $3,508.00 | $4,000.00 |
| 0930 | Sloped and mitered headwall-36 in | EACH A A | 1 | $4,901.00 | $5,200.00 |
| 0940 | SBM alum sheet signs .080 in | SQFT A A | 238 | $25.00 | $47.40 |
| 0950 | SBM alum sheet signs .125 in | SQFT A A | 122 | $30.00 | $59.40 |
| 0960 | Steel post type 1 | LF A A | 108 | $16.00 | $30.84 |
| 0970 | Steel post type 2 | LF A A | 392 | $19.00 | $29.19 |
| 0980 | Remove & relocate signs | EACH A A | 1 | $125.00 | $575.43 |
| 0990 | GMSS type D | EACH A A | 12 | $250.00 | $488.44 |
| 1000 | Barcode sign inventory | EACH A A | 62 | $25.00 | $46.08 |
| 1010 | Pole 30 FT MTG HT | EACH A A | 13 | $6,318.05 | $2,978.39 |
| 1020 | Bracket 4 FT | EACH A A | 2 | $250.00 | $618.25 |
| 1030 | Bracket 8 FT | EACH A A | 3 | $400.00 | $733.48 |
| 1040 | Bracket 10 FT | EACH A A | 3 | $625.00 | $930.35 |
| 1050 | Bracket 12 FT | EACH A A | 3 | $750.00 | $1,026.38 |
| 1060 | Bracket 15 FT | EACH A A | 2 | $800.00 | $1,066.40 |
| 1070 | Pole base | EACH A A | 13 | $2,000.00 | $3,865.72 |
| 1080 | Transformer base | EACH A A | 13 | $1,000.00 | $1,794.63 |
| 1090 | Lighting control equipment | EACH A A | 1 | $15,000 | $41,984 |
| 1100 | Fused connector kit | EACH A A | 26 | $250.00 | $264.27 |
| 1110 | Trenching and backfilling | LF A A | 1,625 | $22.00 | $14.11 |
| 1120 | Wire-no. 8 | LF A A | 4,680 | $4.88 | $3.22 |
| 1130 | Electrical junction box type A | EACH A A | 16 | $3,500.00 | $1,685.37 |
| 1140 | Bore and jack conduit | LF A A | 445 | $23.00 | $41.24 |
| 1150 | LED luminaire | EACH A A | 13 | $2,000.00 | $1,002.37 |
| 1160 | PVC conduit-2 in-schedule 80 | LF A A | 1,775 | $1.50 | $14.83 |
| 1170 | Remove signal equipment | EACH A A | 1 | $7,000.00 | $4,719.29 |
| 1180 | W encasement steel open cut range 4 | LF A A | 111 | $400.00 | $565.00 |
| 1190 | W encasement steel open cut range 5 | LF A A | 45 | $650.00 | $607.00 |
| 1200 | W pipe ductile iron 08 inch | LF A A | 17 | $111.00 | $245.00 |
| 1210 | W pipe PVC 08 inch | LF A A | 956 | $101.00 | $157.00 |
| 1220 | W pipe PVC 12 inch | LF A A | 79 | $152.00 | $210.00 |
| 1230 | W tie-in 08 inch | EACH A A | 5 | $2,146.00 | $5,500.00 |
| 1240 | W tie-in 12 inch | EACH A A | 1 | $2,776.00 | $9,200.00 |
| 1250 | W valve 08 inch | EACH A A | 7 | $2,454.00 | $3,200.00 |
| 1260 | W valve 08 inch | EACH A A | 4 | $12,700 | $13,500 |
| 1270 | W valve 12 inch | EACH A A | 1 | $14,900 | $20,000 |
| 1280 | Mobilization | LS A A | 1 | $147,000 | $129,593 |
| 1290 | Demobilization | LS A A | 1 | $63,800 | $48,590 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of November 20, 2025. Compiled by Mirage Metrics.