KYTC contract 25-1040 bid tabulation

TRIM & REMOVAL OF TREE & BRUSH NEW ROUTE. Let by Kentucky Transportation Cabinet on December 11, 2025. 4 bids received; low bid $186,588 by Keetech Constr Horizontal Directional Drilling & Utilities, -22% against the engineer's estimate of $238,156.

Owner
Kentucky Transportation Cabinet
Letting
11 DEC 2025
Pay items
14
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Keetech Constr Horizontal Directional Drilling & Utilities$186,588Low-22%
2S & M Contracting LLC$238,790+28%0.0%
3Innovative Demolition Service LLC$374,674+101%+57%
4Swartz Mowing Inc$572,685+207%+140%
KYTC contract 25-1040: bids by rank

Engineer's estimate: $238,156.

Bid tabulation

LinePay itemUnitQuantity1. Keetech Constr Horizontal Directional Drilling & Utilities2. S & M Contracting LLC3. Innovative Demolition Service LLC4. Swartz Mowing Inc
0010Clearing and grubbingLS A A1$54,000$100,000$255,000$454,000
0020Temporary signsSQFT A A54$120.00$26.50$18.00$22.00
0030Maintain & control trafficLS A A1$5,000.00$20,000$7,500.00$10,000
0040Temp silt fenceLF A A4,350$4.00$5.00$6.25$5.75
0050Silt trap type AEACH A A17$310.00$700.00$650.00$400.00
0060Silt trap type BEACH A A17$310.00$500.00$950.00$400.00
0070Silt trap type CEACH A A17$310.00$200.00$1,200.00$350.00
0080Clean silt trap type AEACH A A17$250.00$100.00$35.00$50.00
0090Clean silt trap type BEACH A A17$250.00$100.00$35.00$50.00
0100Clean silt trap type CEACH A A17$250.00$50.00$35.00$50.00
0110StakingLS A A1$10,000$10,000$5,400.00$20,000
0120Temp mulchSQYD A A11,060$1.00$0.95$0.45$0.45
0130Temp seeding and protectionSQYD A A41,450$0.75$1.05$0.45$0.65
0140DemobilizationLS A A1$23,000$3,529.00$5,600.00$8,465.00
KYTC contract 25-1040: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.