KYTC contract 25-1040 bid tabulation
TRIM & REMOVAL OF TREE & BRUSH NEW ROUTE. Let by Kentucky Transportation Cabinet on December 11, 2025. 4 bids received; low bid $186,588 by Keetech Constr Horizontal Directional Drilling & Utilities, -22% against the engineer's estimate of $238,156.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 11 DEC 2025
- Pay items
- 14
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Keetech Constr Horizontal Directional Drilling & Utilities | $186,588 | Low | -22% |
| 2 | S & M Contracting LLC | $238,790 | +28% | 0.0% |
| 3 | Innovative Demolition Service LLC | $374,674 | +101% | +57% |
| 4 | Swartz Mowing Inc | $572,685 | +207% | +140% |
Engineer's estimate: $238,156.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Keetech Constr Horizontal Directional Drilling & Utilities | 2. S & M Contracting LLC | 3. Innovative Demolition Service LLC | 4. Swartz Mowing Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing | LS A A | 1 | $54,000 | $100,000 | $255,000 | $454,000 |
| 0020 | Temporary signs | SQFT A A | 54 | $120.00 | $26.50 | $18.00 | $22.00 |
| 0030 | Maintain & control traffic | LS A A | 1 | $5,000.00 | $20,000 | $7,500.00 | $10,000 |
| 0040 | Temp silt fence | LF A A | 4,350 | $4.00 | $5.00 | $6.25 | $5.75 |
| 0050 | Silt trap type A | EACH A A | 17 | $310.00 | $700.00 | $650.00 | $400.00 |
| 0060 | Silt trap type B | EACH A A | 17 | $310.00 | $500.00 | $950.00 | $400.00 |
| 0070 | Silt trap type C | EACH A A | 17 | $310.00 | $200.00 | $1,200.00 | $350.00 |
| 0080 | Clean silt trap type A | EACH A A | 17 | $250.00 | $100.00 | $35.00 | $50.00 |
| 0090 | Clean silt trap type B | EACH A A | 17 | $250.00 | $100.00 | $35.00 | $50.00 |
| 0100 | Clean silt trap type C | EACH A A | 17 | $250.00 | $50.00 | $35.00 | $50.00 |
| 0110 | Staking | LS A A | 1 | $10,000 | $10,000 | $5,400.00 | $20,000 |
| 0120 | Temp mulch | SQYD A A | 11,060 | $1.00 | $0.95 | $0.45 | $0.45 |
| 0130 | Temp seeding and protection | SQYD A A | 41,450 | $0.75 | $1.05 | $0.45 | $0.65 |
| 0140 | Demobilization | LS A A | 1 | $23,000 | $3,529.00 | $5,600.00 | $8,465.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.