KYTC contract 25-1110 bid tabulation
WIDENING LEFT AND RIGHT TURN LANE EXTENSIONS ON KY 234 AT LOVERS LANE. Let by Kentucky Transportation Cabinet on June 5, 2025. 2 bids received; low bid $403,780 by Scotty'S Contracting & Stone LLC, -29% against the engineer's estimate of $565,886.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 05 JUN 2025
- Pay items
- 59
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $403,780 | Low | -29% |
| 2 | Cleary Construction Inc | $670,000 | +66% | +18% |
Engineer's estimate: $565,886.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 312 | $30.68 | $55.00 |
| 0020 | Crushed stone base | TON A A | 564 | $34.60 | $56.00 |
| 0030 | Crushed aggregate size no 2 | TON A A | 796 | $33.36 | $40.00 |
| 0040 | Asphalt seal aggregate | TON A A | 4 | $659.22 | $1,120.00 |
| 0050 | Asphalt seal coat | TON A A | 1 | $1,263.68 | $6,500.00 |
| 0060 | CL2 asph base 1.00D PG64-22 | TON A A | 593 | $122.07 | $150.00 |
| 0070 | Asphalt material for tack | TON A A | 3 | $683.30 | $1,000.00 |
| 0080 | CL3 asph surf 0.38A PG64-22 | TON A A | 308 | $144.19 | $180.00 |
| 0090 | Adjust manhole frame to grade | EACH A A | 1 | $1,590.00 | $1,500.00 |
| 0100 | Temp ditch | LF A A | 200 | $0.01 | $1.00 |
| 0110 | Clean temp ditch | LF A A | 100 | $0.01 | $0.10 |
| 0120 | Roadway excavation | CUYD A A | 1,480 | $26.17 | $70.00 |
| 0130 | Water | MGAL A A | 1 | $0.01 | $0.10 |
| 0140 | Clearing and grubbing | LS A A | 1 | $1,750.84 | $15,000 |
| 0150 | Temporary signs | SQFT A A | 600 | $5.31 | $7.00 |
| 0160 | Fabric-geotextile class 1A | SQYD A A | 4,684 | $3.59 | $5.00 |
| 0170 | Maintain & control traffic | LS A A | 1 | $20,335 | $67,000 |
| 0180 | Portable changeable message sign | EACH A A | 4 | $966.30 | $6,000.00 |
| 0190 | Mobilization for mill & text | LS A A | 1 | $4,344.60 | $3,500.00 |
| 0200 | Asphalt pave milling & texturing | TON A A | 132 | $48.61 | $95.00 |
| 0210 | Temp silt fence | LF A A | 200 | $3.50 | $5.00 |
| 0220 | Silt trap type A | EACH A A | 1 | $172.66 | $300.00 |
| 0230 | Silt trap type B | EACH A A | 1 | $126.01 | $250.00 |
| 0240 | Silt trap type C | EACH A A | 1 | $79.51 | $250.00 |
| 0250 | Clean silt trap type A | EACH A A | 1 | $0.01 | $1.00 |
| 0260 | Clean silt trap type B | EACH A A | 1 | $0.01 | $1.00 |
| 0270 | Clean silt trap type C | EACH A A | 1 | $0.01 | $1.00 |
| 0280 | Staking | LS A A | 1 | $10,256 | $35,000 |
| 0290 | Arrow panel | EACH A A | 2 | $419.34 | $5,000.00 |
| 0300 | Erosion control blanket | SQYD A A | 259 | $5.00 | $7.60 |
| 0310 | Temp mulch | SQYD A A | 781 | $0.50 | $0.35 |
| 0320 | Temp seeding and protection | SQYD A A | 583 | $0.75 | $0.37 |
| 0330 | Initial fertilizer | TON A A | 0.04 | $2,500.00 | $1,500.00 |
| 0340 | Maintenance fertilizer | TON A A | 0.07 | $2,500.00 | $1,500.00 |
| 0350 | Agricultural limestone | TON A A | 0.84 | $100.00 | $85.00 |
| 0355 | Topsoil furnished and placed | CUYD A A | 44 | $207.29 | $235.00 |
| 0360 | Pave striping-temp paint-4 in | LF A A | 4,986 | $0.32 | $0.32 |
| 0370 | Pave striping-thermo-6 in W | LF A A | 2,493 | $1.35 | $1.35 |
| 0380 | Pave striping-thermo-6 in Y | LF A A | 1,454 | $1.35 | $1.35 |
| 0390 | Pave striping-temp rem tape-B | LF A A | 600 | $3.00 | $3.00 |
| 0400 | Pave striping-temp rem tape-W | LF A A | 600 | $3.00 | $3.00 |
| 0410 | Pave marking-thermo stop bar-24IN | LF A A | 41 | $15.00 | $15.00 |
| 0420 | Pave marking-thermo cross-hatch | SQFT A A | 54 | $8.00 | $8.00 |
| 0430 | Pave marking-thermo curv arrow | EACH A A | 21 | $150.00 | $150.00 |
| 0440 | Inlaid pavement marker-MW | EACH A A | 42 | $30.00 | $30.00 |
| 0450 | Inlaid pavement marker-by | EACH A A | 25 | $30.00 | $30.00 |
| 0460 | Concrete-class A | CUYD A A | 0.30 | $9,000.00 | $15,000 |
| 0470 | Steel reinforcement | LB A A | 36 | $10.00 | $2.50 |
| 0480 | Joint adhesive | LF A A | 2,877 | $2.00 | $2.00 |
| 0490 | Frame and lid TY 2 | EACH A A | 1 | $1,500.00 | $1,000.00 |
| 0500 | Longitudinal edge key | LF A A | 1,275 | $6.86 | $10.00 |
| 0510 | Remove sign | EACH A A | 2 | $16.67 | $450.00 |
| 0520 | Barrier curb and gutter-mod | LF A A | 249 | $57.25 | $63.90 |
| 0530 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 | $1.00 |
| 0540 | Pole base | EACH A A | 4 | $3,900.00 | $3,900.00 |
| 0550 | Conduit-1 1/2 in | LF A A | 522 | $12.50 | $12.50 |
| 0560 | Electrical junction box | EACH A A | 1 | $3,000.00 | $3,000.00 |
| 0570 | Install luminaire pole | EACH A A | 4 | $5,850.00 | $5,850.00 |
| 0580 | Demobilization | LS A A | 1 | $5,971.63 | $10,077 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of June 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way