KYTC contract 25-1113 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE U.S. 79. Let by Kentucky Transportation Cabinet on August 21, 2025. 2 bids received; low bid $7,723,699 by Scotty'S Contracting & Stone LLC, -4.3% against the engineer's estimate of $8,067,223.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 157
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $7,723,699 | Low | -4.0% |
| 2 | Cleary Construction Inc | $9,375,000 | +21% | +16% |
Engineer's estimate: $8,067,223.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 20,304 | $35.51 | $35.00 |
| 0020 | Traffic bound base | TON A A | 165 | $42.07 | $50.00 |
| 0030 | Asphalt seal aggregate | TON A A | 370 | $130.35 | $95.00 |
| 0040 | Asphalt seal coat | TON A A | 45 | $847.63 | $1,000.00 |
| 0050 | Leveling & wedging PG64-22 | TON A A | 3,558 | $95.98 | $140.00 |
| 0060 | CL3 asph base 1.00D PG64-22 | TON A A | 10,422 | $92.01 | $116.00 |
| 0070 | CL3 asph surf 0.38B PG64-22 | TON A A | 5,050 | $112.98 | $160.00 |
| 0080 | Cem conc ent pavement-8 in | SQYD A A | 221 | $115.23 | $115.23 |
| 0090 | Asphalt pave milling & texturing | TON A A | 2,145 | $39.04 | $15.00 |
| 0100 | Asphalt material for tack non-tracking | TON A A | 34 | $626.73 | $700.00 |
| 0110 | Crushed aggregate size no 2 | TON A A | 33,945 | $31.71 | $36.00 |
| 0120 | Standard curb and gutter | LF A A | 128 | $58.74 | $58.74 |
| 0130 | Standard curb and gutter mod | LF A A | 680 | $33.92 | $33.92 |
| 0140 | Standard header curb | LF A A | 792 | $51.66 | $51.66 |
| 0150 | Delineator for guardrail BI directional white | EACH A A | 9 | $16.19 | $16.19 |
| 0160 | Barricade-type III | EACH A A | 4 | $256.39 | $159.00 |
| 0170 | Temp ditch | LF A A | 5,831 | $0.67 | $1.00 |
| 0180 | Clean temp ditch | LF A A | 2,915 | $0.01 | $0.01 |
| 0190 | Roadway excavation | CUYD A A | 31,823 | $19.84 | $28.00 |
| 0200 | Water | MGAL A A | 100 | $0.01 | $0.01 |
| 0210 | Guardrail-steel W beam-S face | LF A A | 1,125 | $33.34 | $33.34 |
| 0220 | Guardrail terminal section no 1 | EACH A A | 2 | $90.16 | $90.16 |
| 0230 | Guardrail end treatment type 1 | EACH A A | 3 | $3,532.73 | $3,532.73 |
| 0240 | Remove guardrail | LF A A | 432 | $3.39 | $3.39 |
| 0250 | Guardrail end treatment type 4A | EACH A A | 7 | $3,863.84 | $3,863.84 |
| 0260 | Right-of-way monument type 1 | EACH A A | 50 | $166.61 | $166.61 |
| 0270 | Witness post | EACH A A | 25 | $150.06 | $150.06 |
| 0280 | Channel lining class II | TON A A | 852 | $51.74 | $68.00 |
| 0290 | Clearing and grubbing | LS A A | 1 | $59,640 | $62,000 |
| 0300 | Temporary signs | SQFT A A | 500 | $8.08 | $10.60 |
| 0310 | Edge key | LF A A | 295 | $56.95 | $55.00 |
| 0320 | Fabric-geotextile class 1 | SQYD A A | 35,228 | $2.28 | $2.50 |
| 0330 | Fabric-geotextile class 1A | SQYD A A | 35,228 | $2.97 | $3.75 |
| 0340 | Maintain & control traffic | LS A A | 1 | $295,314 | $157,000 |
| 0345 | Portable changeable message sign | EACH A A | 4 | $7,976.50 | $8,750.00 |
| 0350 | Mobilization for mill & text | LS A A | 1 | $2,349.72 | $7,500.00 |
| 0360 | Safeloading | CUYD A A | 5 | $600.00 | $600.00 |
| 0370 | Shoulder rumble strips | LF A A | 14,541 | $0.30 | $0.30 |
| 0380 | Temp silt fence | LF A A | 5,831 | $2.53 | $3.00 |
| 0390 | Silt trap type A | EACH A A | 23 | $300.47 | $275.00 |
| 0400 | Silt trap type B | EACH A A | 23 | $137.61 | $175.00 |
| 0410 | Silt trap type C | EACH A A | 23 | $166.09 | $300.00 |
| 0420 | Clean silt trap type A | EACH A A | 23 | $135.99 | $0.01 |
| 0430 | Clean silt trap type B | EACH A A | 23 | $82.25 | $0.01 |
| 0440 | Clean silt trap type C | EACH A A | 23 | $82.25 | $0.01 |
| 0450 | Staking | LS A A | 1 | $48,999 | $150,000 |
| 0460 | Remove structure | LS A A | 1 | $10,046 | $2,800.00 |
| 0470 | Erosion control blanket | SQYD A A | 13,590 | $1.75 | $3.25 |
| 0480 | Temp mulch | SQYD A A | 71,965 | $0.20 | $0.40 |
| 0490 | Temp seeding and protection | SQYD A A | 53,974 | $0.30 | $0.42 |
| 0500 | Initial fertilizer | TON A A | 5.60 | $1,500.00 | $1,382.14 |
| 0510 | Maintenance fertilizer | TON A A | 3.40 | $1,500.00 | $1,382.14 |
| 0520 | Seeding and protection | SQYD A A | 46,802 | $0.42 | $0.80 |
| 0530 | Sodding | SQYD A A | 1,056 | $8.50 | $13.39 |
| 0540 | Agricultural limestone | TON A A | 67 | $85.00 | $87.45 |
| 0550 | Pave striping-temp paint-4 in | LF A A | 3,500 | $0.52 | $0.32 |
| 0560 | Pave striping-thermo-6 in W | LF A A | 25,579 | $1.35 | $1.35 |
| 0570 | Pave striping-thermo-6 in Y | LF A A | 33,582 | $1.35 | $1.35 |
| 0580 | Pave striping-thermo-12 in Y | LF A A | 587 | $8.00 | $8.00 |
| 0590 | Pave marking-thermo stop bar-24IN | LF A A | 177 | $15.00 | $15.00 |
| 0600 | Pave marking-thermo curv arrow | EACH A A | 28 | $140.00 | $140.00 |
| 0610 | Fuel adjustment | DOLL A A | 54,597 | $1.00 | $1.00 |
| 0620 | Asphalt adjustment | DOLL A A | 74,318 | $1.00 | $1.00 |
| 0630 | Object marker TY 3 | EACH A A | 8 | $257.67 | $257.67 |
| 0640 | Centerline rumble strips | LF A A | 7,290 | $0.45 | $0.45 |
| 0650 | Sawcut pavement | LF A A | 13,075 | $0.92 | $1.35 |
| 0660 | Longitudinal edge key | LF A A | 11,150 | $3.17 | $4.45 |
| 0670 | Remove light pole | EACH A A | 4 | $2,500.00 | $2,381.10 |
| 0680 | Inlaid pavement marker | EACH A A | 281 | $23.00 | $23.00 |
| 0690 | Remove signal equipment | EACH A A | 2 | $26,744 | $12,016 |
| 0700 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 | $1.00 |
| 0710 | Entrance pipe-15 in | LF A A | 1,004 | $85.98 | $95.00 |
| 0720 | Entrance pipe-18 in | LF A A | 44 | $105.99 | $180.00 |
| 0730 | Entrance pipe-15 in equiv | LF A A | 228 | $89.05 | $100.00 |
| 0740 | Entrance pipe-18 in equiv | LF A A | 103 | $91.20 | $105.00 |
| 0750 | Culvert pipe-18 in | LF A A | 97 | $213.09 | $128.00 |
| 0760 | Culvert pipe-42 in | LF A A | 58 | $416.47 | $365.00 |
| 0770 | Storm sewer pipe-12 in | LF A A | 316 | $91.50 | $125.00 |
| 0780 | Storm sewer pipe-15 in | LF A A | 56 | $88.16 | $230.00 |
| 0790 | Storm sewer pipe-18 in | LF A A | 748 | $122.01 | $160.00 |
| 0800 | Pipe culvert headwall-18 in | EACH A A | 1 | $2,060.00 | $2,500.00 |
| 0810 | Pipe culvert headwall-42 in | EACH A A | 2 | $5,150.00 | $4,000.00 |
| 0820 | Remove pipe | LF A A | 30 | $26.12 | $40.00 |
| 0830 | Sloped box outlet type 1-18 in | EACH A A | 5 | $2,800.00 | $3,000.00 |
| 0840 | Sloped and parallel headwall-12 in | EACH A A | 1 | $2,200.00 | $2,750.00 |
| 0850 | S & F box inlet-outlet-18 in | EACH A A | 2 | $3,500.00 | $3,000.00 |
| 0860 | Drop box inlet type 1 | EACH A A | 2 | $6,000.00 | $8,000.00 |
| 0870 | Drop box inlet type 13G | EACH A A | 6 | $5,700.00 | $3,750.00 |
| 0880 | Remove drop box inlet | EACH A A | 1 | $1,005.56 | $900.00 |
| 0890 | Manhole type A | EACH A A | 3 | $3,500.00 | $4,000.00 |
| 0900 | Fabric-geotextile class 2 for pipe | SQYD A A | 4,076 | $2.00 | $2.00 |
| 0910 | Remove headwall | EACH A A | 2 | $373.78 | $750.00 |
| 0920 | Drainage junction box TY B | EACH A A | 1 | $5,000.00 | $4,000.00 |
| 0930 | Pipeline inspection | LF A A | 1,275 | $2.35 | $2.35 |
| 0940 | PVC fold and form pipe liner-18 in | LF A A | 180 | $137.54 | $193.10 |
| 0950 | Remove headwall | EACH A A | 2 | $425.00 | $425.00 |
| 0960 | Structure excav-solid rock | CUYD A A | 13 | $125.00 | $125.00 |
| 0970 | Foundation preparation | LS A A | 1 | $7,500.00 | $7,500.00 |
| 0980 | Concrete-class A | CUYD A A | 38.20 | $2,162.00 | $2,162.00 |
| 0990 | Steel reinforcement | LB A A | 4,030 | $1.90 | $1.90 |
| 1000 | S encasement steel open cut range 1 | LF A A | 80 | $489.00 | $950.00 |
| 1010 | S encasement steel open cut range 1 | LF A A | 50 | $492.00 | $990.00 |
| 1020 | S lateral short side 04 inch | EACH A A | 1 | $1,660.00 | $14,000 |
| 1030 | S manhole | EACH A A | 1 | $7,510.00 | $24,000 |
| 1040 | S manhole | EACH A A | 1 | $8,275.00 | $28,000 |
| 1050 | S manhole | EACH A A | 2 | $6,615.00 | $14,000 |
| 1060 | S manhole | EACH A A | 1 | $6,460.00 | $16,000 |
| 1070 | S manhole abandon/remove | EACH A A | 4 | $1,555.00 | $2,000.00 |
| 1080 | S pipe PVC 08 inch | LF A A | 139 | $124.00 | $190.00 |
| 1090 | S pipe PVC 10 inch | LF A A | 102 | $108.00 | $198.00 |
| 1100 | Topsoil and seeding of trenches | LF A A | 241 | $15.00 | $20.00 |
| 1110 | SBM alum sheet signs .080 in | SQFT A A | 307.45 | $46.21 | $46.21 |
| 1120 | SBM alum sheet signs .125 in | SQFT A A | 62 | $47.86 | $47.86 |
| 1130 | Steel post type 1 | LF A A | 626 | $32.03 | $32.03 |
| 1140 | Steel post mile markers | EACH A A | 2 | $432.56 | $432.56 |
| 1150 | Class A concrete for signs | CUYD A A | 2.50 | $1,887.68 | $1,887.68 |
| 1160 | GMSS type D | EACH A A | 5 | $369.77 | $369.77 |
| 1170 | Install LED sign | EACH A A | 4 | $985.23 | $5,163.14 |
| 1180 | W cap existing main | EACH A A | 3 | $3,300.00 | $2,000.00 |
| 1190 | W cap existing main | EACH A A | 1 | $3,385.00 | $3,000.00 |
| 1200 | W cap existing main | EACH A A | 1 | $3,500.00 | $4,000.00 |
| 1210 | W directional bore | LF A A | 62 | $129.00 | $150.00 |
| 1220 | W encasement steel bored range 1 | LF A A | 120 | $365.00 | $375.00 |
| 1230 | W encasement steel bored range 1 | LF A A | 100 | $374.00 | $420.00 |
| 1240 | W encasement steel bored range 1 | LF A A | 60 | $570.00 | $470.00 |
| 1250 | W encasement steel open cut range 1 | LF A A | 30 | $264.00 | $300.00 |
| 1260 | W encasement steel open cut range 1 | LF A A | 55 | $282.00 | $370.00 |
| 1270 | W fire hydrant assembly | EACH A A | 2 | $9,875.00 | $12,000 |
| 1280 | W fire hydrant relocate | EACH A A | 1 | $5,105.00 | $6,000.00 |
| 1290 | W fire hydrant remove | EACH A A | 3 | $830.00 | $3,000.00 |
| 1300 | W meter relocate | EACH A A | 4 | $9,550.00 | $10,000 |
| 1310 | W meter relocate | EACH A A | 1 | $4,435.00 | $4,000.00 |
| 1320 | W meter relocate | EACH A A | 6 | $2,190.00 | $2,000.00 |
| 1330 | W pipe ductile iron 04 inch | LF A A | 334 | $110.00 | $107.00 |
| 1340 | W pipe PVC 04 inch | LF A A | 1,741 | $48.00 | $67.00 |
| 1350 | W pipe PVC 04 inch | LF A A | 325 | $44.00 | $75.00 |
| 1360 | W pipe PVC 06 inch | LF A A | 2,550 | $54.00 | $72.00 |
| 1370 | W pipe PVC 06 inch | LF A A | 225 | $64.00 | $81.00 |
| 1380 | W pipe PVC 08 inch | LF A A | 1,840 | $62.00 | $80.00 |
| 1390 | W pipe PVC 08 inch | LF A A | 70 | $106.00 | $105.00 |
| 1400 | W tapping sleeve and valve size 1 | EACH A A | 1 | $8,610.00 | $8,000.00 |
| 1410 | W tie-in 04 inch | EACH A A | 3 | $3,640.00 | $2,000.00 |
| 1420 | W tie-in 06 inch | EACH A A | 3 | $3,850.00 | $3,000.00 |
| 1430 | W tie-in 08 inch | EACH A A | 2 | $4,115.00 | $4,000.00 |
| 1440 | W valve 04 inch | EACH A A | 5 | $2,045.00 | $2,000.00 |
| 1450 | W valve 06 inch | EACH A A | 5 | $2,620.00 | $3,000.00 |
| 1460 | W valve 08 inch | EACH A A | 1 | $3,660.00 | $4,000.00 |
| 1470 | W valve cut-in 06 inch | EACH A A | 1 | $4,625.00 | $8,000.00 |
| 1480 | W meter special | EACH A A | 1 | $8,360.00 | $6,000.00 |
| 1490 | W meter special | EACH A A | 2 | $1,270.00 | $1,200.00 |
| 1500 | W blowoff assembly | EACH A A | 2 | $4,735.00 | $3,000.00 |
| 1510 | W valve box remove | EACH A A | 12 | $460.00 | $100.00 |
| 1520 | Pavement repair | SQYD A A | 110 | $109.00 | $106.00 |
| 1530 | Topsoil and seeding of trenches | LF A A | 6,393 | $4.00 | $6.00 |
| 1540 | Special ditch crossing protection | LF A A | 25 | $124.00 | $100.00 |
| 1550 | Mobilization | LS A A | 1 | $229,103 | $432,000 |
| 1560 | Demobilization | LS A A | 1 | $111,263 | $139,635 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.