KYTC contract 25-1120 bid tabulation

GRADE & DRAIN WITH ASPHALT SURFACE KY 1. Let by Kentucky Transportation Cabinet on November 20, 2025. 3 bids received; low bid $3,446,611 by Allard Excavation LLC, +6.4% against the engineer's estimate of $3,240,389.

Owner
Kentucky Transportation Cabinet
Letting
20 NOV 2025
Pay items
113
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allard Excavation LLC$3,446,611Low+6.0%
2Mountain Enterprises Inc$3,924,148+14%+21%
3Hinkle Construction Services LLC$4,421,291+28%+36%
KYTC contract 25-1120: bids by rank

Engineer's estimate: $3,240,389.

Bid tabulation

LinePay itemUnitQuantity1. Allard Excavation LLC2. Mountain Enterprises Inc3. Hinkle Construction Services LLC
0010Crushed stone baseTON A A4,982$41.00$40.90$43.00
0020Traffic bound baseTON A A3,025$40.00$45.45$42.00
0030Asphalt seal aggregateTON A A15.90$330.00$330.00$347.00
0040Asphalt seal coatTON A A2$1,925.00$1,925.00$2,025.00
0050Leveling & wedging PG64-22TON A A200$198.60$198.60$209.00
0060CL2 asph base 1.00D PG64-22TON A A4,324$178.50$178.50$188.00
0070CL2 asph surf 0.38D PG64-22TON A A925$198.60$198.60$209.00
0080Cem conc ent pavement-8 inSQYD A A371$135.00$116.15$155.00
0090Joint adhesiveLF A A3,843$1.00$1.00$1.05
0100Asphalt material for tack non-trackingTON A A14.40$925.00$925.00$975.00
0110Crushed aggregate size no 2TON A A1,502$52.00$42.65$45.30
0120Perforated pipe-4 inLF A A73$20.00$26.45$42.75
0130Non-perforated pipe-4 inLF A A70$21.00$51.65$30.30
0140Perf pipe headwall TY 1-4 inEACH A A1$502.00$1,544.85$862.00
0150Perf pipe headwall TY 3-4 inEACH A A1$796.00$1,544.85$862.00
0160Plug pipeEACH A A2$1,046.00$2,782.30$1,900.00
0170Standard curb and gutter modLF A A1,371$44.00$54.10$41.00
0180Standard header curbLF A A62$65.00$73.60$75.00
0190Standard barrier median type 2SQYD A A204$132.00$167.10$170.00
0200Delineator for guardrail BI directional whiteEACH A A30$30.00$13.00$26.25
0210Barricade-type IIIEACH A A5$181.00$185.00$200.00
0220Remove pavementSQYD A A45$9.00$28.75$17.60
0230Temp ditchLF A A1,455$11.00$1.75$2.40
0240Clean temp ditchLF A A728$10.00$0.40$0.01
0250Granular embankmentCUYD A A500$46.00$68.75$95.00
0260Embankment in placeCUYD A A24,327$17.00$32.80$50.00
0270WaterMGAL A A28$1.00$0.25$0.01
0280Guardrail terminal section no 1EACH A A6$100.00$65.00$105.00
0290Guardrail end treatment type 7EACH A A6$2,000.00$2,100.00$2,100.00
0300Remove & reset guardrailLF A A587.50$24.00$25.00$26.00
0310Temp guardrailLF A A2,500$20.00$18.00$21.00
0320Right-of-way monument type 1EACH A A39$150.00$420.00$215.00
0330Witness postEACH A A3$150.00$420.00$88.00
0340Plug water wellEACH A A1$5,419.00$8,810.00$3,160.00
0350Channel lining class IITON A A602$40.00$55.40$52.00
0360Channel lining class IIITON A A1,050$49.00$59.25$58.00
0370Clearing and grubbingLS A A1$24,180$47,100$75,000
0380Temporary signsSQFT A A634$12.00$10.60$10.50
0390Edge keyLF A A112$59.75$59.75$62.50
0400Fabric-geotextile class 1SQYD A A2,025$2.00$2.40$2.50
0410Fabric-geotextile class 2SQYD A A9,000$2.00$2.40$2.50
0420Fabric-geotextile class 2 for pipeSQYD A A275$2.00$2.00$2.00
0430Maintain & control trafficLS A A1$54,139$95,000$175,000
0440Diversions (by-pass detours)LS A A1$173,350$215,000$42,000
0450Temp silt fenceLF A A1,455$5.00$2.95$5.90
0460Silt trap type AEACH A A3$452.00$425.00$300.00
0470Silt trap type BEACH A A3$452.00$425.00$375.00
0480Silt trap type CEACH A A3$69.00$550.00$635.00
0490Clean silt trap type AEACH A A3$70.00$23.00$48.00
0500Clean silt trap type BEACH A A3$70.00$23.00$48.00
0510Clean silt trap type CEACH A A3$70.00$23.00$48.00
0520Sidewalk-4 in concreteSQYD A A601$98.00$58.50$88.00
0530StakingLS A A1$24,782$47,500$46,000
0540Conduit-2 inLF A A392$23.11$23.11$24.25
0550Cable-no. 14/5CLF A A70$6.50$6.03$6.35
0560Remove lightingLS A A1$5,600.00$5,539.15$5,830.00
0570Erosion control blanketSQYD A A1,273$4.00$6.50$6.85
0580Temp mulchSQYD A A9,423$0.44$0.33$0.35
0590Temp seeding and protectionSQYD A A7,067$1.00$0.35$0.37
0600Initial fertilizerTON A A1$1,685.00$1,600.00$1,685.00
0610Maintenance fertilizerTON A A1$1,685.00$1,600.00$1,685.00
0620Seeding and protectionSQYD A A14,134$1.00$0.70$0.75
0630SoddingSQYD A A474$30.00$15.00$15.80
0640Agricultural limestoneTON A A9$120.00$95.00$100.00
0650Pave striping-temp paint-4 inLF A A23,500$0.18$0.18$0.19
0660Pave striping-perm paint-4 inLF A A9,779$0.22$0.22$0.23
0670Pave striping-thermo-8 in WLF A A736$5.00$5.00$5.25
0680Pave marking-thermo X-walk-6 inLF A A149$4.00$3.50$3.70
0690Pave marking-thermo stop bar-24INLF A A76$12.00$12.00$12.60
0700Pave marking-thermo cross-hatchSQFT A A1,178$5.00$5.00$5.25
0710Pave marking-thermo curv arrowEACH A A7$120.00$120.00$126.00
0720Fuel adjustmentDOLL A A15,569$1.00$1.00$1.00
0730Asphalt adjustmentDOLL A A21,303$1.00$1.00$1.00
0740Longitudinal edge keyLF A A1,130$15.60$15.60$16.40
0750Pave mark thermo cone cap-solid yellowSQFT A A48$7.00$7.00$7.35
0760Detectable warningsSQFT A A40$51.00$71.30$51.00
0770Turf reinforcement mat 1SQYD A A1,058$10.00$12.00$12.60
0780Pave striping-chevron markingsSQFT A A1,094$5.00$5.00$5.25
0790Remove and reset end treatmentEACH A A6$300.00$1,500.00$1,575.00
0800Object marker type 4EACH A A1$100.00$500.00$525.00
0810Electronic delivery MGMT system - aggLS A A1$2,500.00$2,500.00$2,630.00
0820Entrance pipe-15 inLF A A352$114.00$115.85$132.00
0830Entrance pipe-18 inLF A A187$123.00$120.70$143.00
0840Entrance pipe-24 inLF A A73$167.00$268.00$155.00
0850Entrance pipe-30 inLF A A44$240.00$284.60$184.00
0860Culvert pipe-18 inLF A A50$142.00$229.95$140.00
0870Storm sewer pipe-15 inLF A A28$101.00$130.25$155.00
0880Storm sewer pipe-18 inLF A A151$128.00$159.35$130.00
0890Storm sewer pipe-24 inLF A A18$153.00$238.75$235.00
0900Pipe culvert headwall-18 inEACH A A2$4,331.00$3,472.00$2,250.00
0910Pipe culvert headwall-24 inEACH A A1$4,827.00$3,813.00$2,350.00
0920Metal end section TY 1-30 inEACH A A1$6,552.00$6,820.00$2,260.00
0930Sloped box outlet type 1-18 inEACH A A1$4,764.00$4,225.00$2,750.00
0940Curb box inlet type AEACH A A4$10,647$7,085.00$8,630.00
0950Drop box inlet type 1EACH A A1$5,345.00$6,185.00$6,500.00
0960Drop box inlet type 13GEACH A A2$5,383.00$7,340.00$3,800.00
0970Drop box inlet type 14EACH A A2$5,102.00$7,454.00$3,860.00
0980Drainage junction box TY BEACH A A1$7,367.00$4,966.50$3,450.00
0990Pipeline inspectionLF A A600$5.00$4.17$4.40
1000Foundation preparationLS A A1$19,140$28,650$54,000
1010Concrete-class ACUYD A A40.20$5,304.00$2,143.90$3,130.00
1020Steel reinforcementLB A A4,531$3.00$2.90$2.30
1030Lightweight fillCUYD A A76$121.00$298.35$340.00
1040Remove store & reinstall poleEACH A A2$3,041.00$2,525.20$2,660.00
1050SBM alum sheet signs .080 inSQFT A A32$60.00$65.00$68.00
1060Steel post type 2LF A A52$60.00$60.00$63.00
1070Remove & relocate signsEACH A A13$1,000.00$750.00$525.00
1080Remove signEACH A A3$500.00$150.00$158.00
1090InstallEACH A A2$4,400.00$4,360.91$4,590.00
1100Barcode sign inventoryEACH A A5$30.00$45.00$47.00
1110Remove signal equipmentEACH A A2$1,700.00$1,346.63$1,425.00
1120MobilizationLS A A1$125,000$180,000$200,000
1130DemobilizationLS A A1$65,000$54,800$62,000
KYTC contract 25-1120: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of November 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy