KYTC contract 25-1309 bid tabulation
ASPHALT REHAB WITH BRIDGE (S) LOUISVILLE-CINCINNATI ROAD (I-71). Let by Kentucky Transportation Cabinet on April 24, 2025, Boone, District 6. 2 bids received; low bid $12,794,227 by Eaton Asphalt Paving Co Inc, -6.1% against the engineer's estimate of $13,619,346.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 APR 2025
- Pay items
- 92
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eaton Asphalt Paving Co Inc | $12,794,227 | Low | -6.0% |
| 2 | Riegler Blacktop Inc | $15,401,677 | +20% | +13% |
Engineer's estimate: $13,619,346.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eaton Asphalt Paving Co Inc | 2. Riegler Blacktop Inc |
|---|---|---|---|---|---|
| 0010 | Asphalt seal aggregate | TON A | 14 | $870.00 | $500.00 |
| 0020 | Asphalt seal coat | TON A | 2 | $1,930.00 | $2,000.00 |
| 0030 | Leveling & wedging PG64-22 | TON A | 8,221 | $81.00 | $125.00 |
| 0035 | Leveling & wedging PG76-22 | TON A | 500 | $155.00 | $140.00 |
| 0040 | CL4 asph base 1.00D PG76-22 | TON A | 28,798 | $88.00 | $111.10 |
| 0050 | CL4 asph surf 0.38A PG76-22 | TON A | 25,670 | $123.67 | $115.00 |
| 0060 | Mobilization for mill & text | LS A | 1 | $15,000 | $25,000 |
| 0070 | Asphalt pave milling & texturing | TON A | 57,218 | $25.00 | $30.70 |
| 0080 | Fiber reinforcement for HMA | TON A | 13,995 | $9.75 | $8.75 |
| 0090 | Pave mount infrared temp equipment | SF A | 675,563 | $0.01 | $0.03 |
| 0100 | Asphalt material for tack non-tracking | TON A | 167 | $1.00 | $1.00 |
| 0110 | Geocomposite reinforcement for asphalt | SQYD A | 89,749 | $9.75 | $10.00 |
| 0120 | Crushed stone base | TON A | 77 | $105.00 | $70.00 |
| 0125 | Dga base | TON A | 40 | $125.00 | $75.00 |
| 0130 | Crushed aggregate size no 57 | TON A | 200 | $50.00 | $60.00 |
| 0140 | Crushed aggregate size no 2 | TON A | 2,712 | $39.00 | $60.00 |
| 0150 | Standard integral curb | LF A | 30 | $300.00 | $250.00 |
| 0160 | Delineator for guardrail mono directional white | EACH A | 20 | $15.00 | $15.00 |
| 0170 | Delineator for guardrail mono directional yello | EACH A | 20 | $15.00 | $15.00 |
| 0180 | Delineator for barrier wall-B/Y | EACH A | 50 | $10.00 | $6.00 |
| 0190 | Delineator for barrier wall-B/W | EACH A | 50 | $10.00 | $6.00 |
| 0200 | Relocate temp conc barrier | LF A | 2,000 | $15.00 | $7.50 |
| 0210 | Barricade-type III | EACH A | 10 | $150.00 | $150.00 |
| 0220 | Special excavation | CUYD A | 260 | $85.00 | $40.00 |
| 0230 | Embankment in place | CUYD A | 1,800 | $55.00 | $50.00 |
| 0240 | Guardrail-steel W beam-S face | LF A | 850 | $57.00 | $57.00 |
| 0250 | Guardrail end treatment type 1 | EACH A | 12 | $3,700.00 | $3,700.00 |
| 0260 | Guardrail end treatment type 2A | EACH A | 2 | $1,800.00 | $1,800.00 |
| 0270 | Remove guardrail | LF A | 2,062 | $4.90 | $4.90 |
| 0280 | Remove concrete masonry | CUYD A | 145 | $450.00 | $525.00 |
| 0290 | Channel lining class II | TON A | 611 | $104.00 | $100.00 |
| 0300 | Clearing and grubbing | LS A | 1 | $55,000 | $48,975 |
| 0310 | Temporary signs | SQFT A | 816 | $7.50 | $7.50 |
| 0320 | Ditching and shouldering | LF A | 690 | $25.00 | $12.00 |
| 0330 | Maintain & control traffic | LS A | 1 | $195,000 | $1,000,000 |
| 0340 | Truck mounted attenuator | EACH A | 2 | $27,984 | $14,500 |
| 0350 | Portable changeable message sign | EACH A | 5 | $5,194.00 | $3,500.00 |
| 0360 | Silt trap type B | EACH A | 10 | $300.00 | $175.00 |
| 0370 | Silt trap type C | EACH A | 10 | $275.00 | $200.00 |
| 0380 | Clean silt trap type B | EACH A | 10 | $175.00 | $40.00 |
| 0390 | Clean silt trap type C | EACH A | 10 | $150.00 | $40.00 |
| 0400 | Staking | LS A | 1 | $35,000 | $50,000 |
| 0410 | Relocate crash cushion | EACH A | 4 | $4,100.00 | $4,000.00 |
| 0420 | Conc barrier wall type 9T | LF A | 2,000 | $56.00 | $50.00 |
| 0430 | Conduit-1 1/4 in | LF A | 80 | $12.00 | $12.00 |
| 0440 | Conduit-2 in | LF A | 20 | $18.00 | $18.00 |
| 0450 | Trenching and backfilling | LF A | 90 | $15.00 | $15.00 |
| 0460 | Piezoelectric sensor | EACH A | 4 | $2,950.00 | $2,950.00 |
| 0470 | Loop wire | LF A | 1,600 | $1.25 | $1.25 |
| 0480 | Loop saw slot and fill | LF A | 360 | $12.00 | $12.00 |
| 0490 | Erosion control blanket | SQYD A | 96,728 | $2.10 | $2.10 |
| 0500 | Pave striping-temp paint-6 in | LF A | 419,740 | $0.26 | $0.33 |
| 0510 | Pave striping-thermo-6 in W | LF A | 117,805 | $1.15 | $0.59 |
| 0520 | Pave striping-thermo-6 in Y | LF A | 96,728 | $1.15 | $0.54 |
| 0530 | Pave striping-thermo-12 in W | LF A | 5,754 | $2.50 | $2.10 |
| 0540 | Pave striping-dur TY 1-6 in W | LF A | 1,000 | $9.00 | $9.03 |
| 0550 | Pave striping-dur TY 1-6 in Y | LF A | 920 | $9.00 | $9.03 |
| 0560 | Pave marking-thermo stop bar-12IN | LF A | 101 | $12.00 | $4.35 |
| 0570 | Pave marking-thermo cross-hatch | SQFT A | 1,963 | $6.00 | $4.05 |
| 0580 | Pave marking-dotted lane exten | LF A | 1,311 | $4.00 | $2.00 |
| 0590 | Pave marking-thermo merge arrow | EACH A | 4 | $300.00 | $350.00 |
| 0600 | Inlaid pavement marker-B W/R | EACH A | 1,254 | $30.00 | $32.87 |
| 0610 | Inlaid pavement marker-B Y/R | EACH A | 178 | $30.00 | $32.87 |
| 0620 | Concrete-class A | CUYD A | 30 | $2,580.00 | $1,350.00 |
| 0630 | Crash cushion TY VI class C | EACH A | 4 | $9,500.00 | $10,000 |
| 0640 | Fuel adjustment | DOLL A | 147,000 | $1.00 | $1.00 |
| 0650 | Asphalt adjustment | DOLL A | 275,000 | $1.00 | $1.00 |
| 0660 | Joint adhesive | LF A | 186,780 | $0.50 | $0.50 |
| 0670 | Object marker TY 3 | EACH A | 12 | $95.00 | $95.00 |
| 0680 | Galvanized steel cabinet | EACH A | 2 | $1,800.00 | $1,800.00 |
| 0690 | Wood post | EACH A | 4 | $750.00 | $750.00 |
| 0700 | Shoulder rumble strips-sawed | LF A | 169,865 | $0.15 | $0.15 |
| 0710 | Electrical junction box type A | EACH A | 2 | $2,500.00 | $2,500.00 |
| 0720 | Law enforcement officer | HOUR A | 1,000 | $100.00 | $100.00 |
| 0730 | Guardrail thrie beam | LF A | 615 | $68.00 | $68.00 |
| 0740 | High friction surface treatment | SQYD A | 11,931 | $18.30 | $20.88 |
| 0750 | Pave mark thermo chevron | SQFT A | 1,282 | $6.00 | $4.05 |
| 0760 | Pave mark thermo-wrong way arrow | EACH A | 4 | $300.00 | $325.00 |
| 0770 | Queue protection vehicle | HOUR A | 400 | $75.00 | $125.00 |
| 0780 | Thrie beam guardrail transition TL-3 | EACH A | 3 | $3,700.00 | $3,700.00 |
| 0790 | Thrie beam guardrail transition TL-2 | EACH A | 2 | $2,500.00 | $2,500.00 |
| 0800 | Furnish queue protection vehicles | MONT A | 14 | $4,717.00 | $5,000.00 |
| 0810 | Portable queue warning alert system | MONT A | 14 | $1,749.00 | $2,000.00 |
| 0820 | Queue warning PCMS | MONT A | 14 | $530.00 | $750.00 |
| 0830 | Queue warning portable radar sensors | MONT A | 14 | $1.06 | $400.00 |
| 0840 | Thrie beam bullnose terminal | EACH A | 5 | $25,000 | $25,000 |
| 0850 | Connected arrow panel | MONT A | 28 | $318.00 | $400.00 |
| 0860 | Concrete-class A | CUYD A | 312.20 | $1,025.00 | $1,850.00 |
| 0870 | Steel reinforcement | LB A | 11,138 | $6.25 | $8.50 |
| 0880 | Concrete sealing | SQFT A | 5,360 | $2.25 | $2.50 |
| 0890 | Mobilization | LS A | 1 | $229,845 | $650,000 |
| 0900 | Demobilization | LS A | 1 | $185,600 | $230,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of April 24, 2025. Compiled by Mirage Metrics.