KYTC contract 25-2022 bid tabulation

PAVEMENT (WITH ALTERNATES) CALVERT CITY TO SARATOGA (I-24). Let by Kentucky Transportation Cabinet on January 23, 2025, Lyon, Mccracken, District 1. 2 bids received; low bid $9,272,481 by Strawser Construction Inc, -7.6% against the engineer's estimate of $10,033,300.

Owner
Kentucky Transportation Cabinet
Letting
23 JAN 2025
Pay items
45
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Strawser Construction Inc$9,272,481Low-8.0%
2Jim Smith Contracting Company LLC$10,366,094+12%+3.0%
KYTC contract 25-2022: bids by rank

Engineer's estimate: $10,033,300.

Bid tabulation

LinePay itemUnitQuantity1. Strawser Construction Inc2. Jim Smith Contracting Company LLC
0010Pave striping-temp paint-4 inLF A1,275,000$0.12
0020Microsurfacing-surface course - type ASQYD A999,221$3.20
0030Microsurfacing-leveling courseSQYD A1,146,891$2.46
0040Fiber reinforcement for microsurfacingSQYD A999,221$0.60
0050Leveling & wedging PG64-22TON A6,089$151.00
0060Asphalt material for tackTON A482$750.00
0070Mobilization for mill & textLS A1$2,500.00
0080Mobilization for mill & textLS A1$2,500.00
0090Asphalt pave milling & texturingTON A605$265.00
0100Pave striping-temp paint-4 inLF A700,000$0.10
0110Fiber reinforcement for surf no.4TON A41,225$8.30
0120CL4 asph surf no.4A PG64-22TON A41,225$151.00
0130Temporary signsSQFT A750$16.00$7.30
0140Maintain & control trafficLS A1$129,515$140,000
0150Maintain & control trafficLS A1$129,515$290,000
0160Arrow panelEACH A8$2,320.00$500.00
0170Pave striping removal-6 inLF A582,500$0.35$0.30
0180Pave striping-thermo-6 in WLF A400,000$1.09$0.95
0190Pave striping-thermo-6 in YLF A295,000$1.09$0.95
0200Pave marking-thermo stop bar-24INLF A85$11.50$10.00
0210Pave marking-thermo STR arrowEACH A7$85.00$75.00
0220Pave marking-thermo curv arrowEACH A62$85.00$75.00
0230Pave marking-thermo comb arrowEACH A4$170.00$150.00
0240Pave marking-thermo merge arrowEACH A3$170.00$150.00
0241Conduit-1 1/4 inLF A560$5.90$9.50
0242Conduit-2 inLF A140$8.25$12.00
0243Trenching and backfillingLF A650$17.25$12.00
0244Piezoelectric sensorEACH A36$4,000.00$2,425.00
0245Loop wireLF A11,200$0.35$0.99
0246Loop saw slot and fillLF A2,670$45.00$12.00
0247Galvanized steel cabinetEACH A14$1,100.00$900.00
0248Wood postEACH A28$575.00$350.00
0249Electrical junction box type AEACH A14$2,800.00$1,900.00
0250Law enforcement officerHOUR A250$97.00$100.00
0260Pave marking-thermo yield bar-36 inLF A12$55.00$50.00
0270Overband crack sealingLB A60,000$1.69$1.65
0280Inlaid pavement markerEACH A7,660$21.00$19.00
0290Remove pavement markerEACH A7,660$6.50$10.00
0300Queue protection vehicleHOUR A250$110.00$80.00
0310Furnish queue protection vehiclesMONT A8$5,425.00$8,000.00
0320Portable queue warning alert systemMONT A4$2,375.00$6,404.68
0330Queue warning PCMSMONT A32$610.00$0.01
0340Queue warning portable radar sensorsMONT A32$335.00$0.01
0350MobilizationLS A1$305,000$200,000
0370DemobilizationLS A1$135,000$150,550
KYTC contract 25-2022: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of January 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy