ASPHALT RESURFACING CARROLLTON - WARSAW ROAD (US 42). Let by Kentucky Transportation Cabinet on February 20, 2025, Gallatin, District 6. 4 bids received; low bid $579,412 by Mac Construction & Excavating Inc, -14% against the engineer's estimate of $676,233.

Owner
Kentucky Transportation Cabinet
Letting
20 FEB 2025
Pay items
23
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Mac Construction & Excavating Inc$579,412Low-14%
2Eaton Asphalt Paving Co Inc$598,353+3.0%-12%
3Hinkle Contracting Company LLC$605,533+5.0%-10%
4Riegler Blacktop Inc$637,493+10%-6.0%
KYTC contract 25-2065: bids by rank

Engineer's estimate: $676,233.

Bid tabulation

LinePay itemUnitQuantity1. Mac Construction & Excavating Inc2. Eaton Asphalt Paving Co Inc3. Hinkle Contracting Company LLC4. Riegler Blacktop Inc
0010Dga baseTON A300$46.00$46.00$43.00$75.00
0020Leveling & wedging PG64-22TON A892$96.00$92.00$93.85$89.00
0030CL2 asph surf 0.38D PG64-22TON A4,085$83.00$92.00$93.85$98.00
0040Asphalt material for tackTON A40$0.01$1.00$1.00$1.00
0050Temporary signsSQFT A290$8.56$5.00$4.25$8.50
0060Maintain & control trafficLS A1$2,500.00$22,575$9,550.00$18,200
0070Mobilization for mill & textLS A1$2,950.00$5,500.00$2,950.00$7,700.00
0080Asphalt pave milling & texturingTON A100$17.35$1.00$55.00$50.00
0090Edgeline rumble stripsLF A33,370$0.20$0.18$0.18$0.18
0100Base failure repairSQYD A70$138.00$68.00$120.00$120.00
0110Pave striping-temp paint-4 inLF A30,000$0.18$0.18$0.18$0.18
0120Pave striping-perm paint-6 inLF A77,050$0.26$0.24$0.24$0.24
0130Pave marking-thermo stop bar-24INLF A24$10.00$12.50$12.50$12.50
0140Pave marking-thermo cross-hatchSQFT A4,435$3.00$3.25$3.25$3.25
0150Pave marking-thermo STR arrowEACH A1$100.00$115.00$115.00$115.00
0160Pave marking-thermo curv arrowEACH A30$115.00$100.00$100.00$100.00
0170Pave marking-thermo onlyEACH A14$275.00$300.00$300.00$300.00
0180Fuel adjustmentDOLL A7,747$1.00$1.00$1.00$1.00
0190Asphalt adjustmentDOLL A19,458$1.00$1.00$1.00$1.00
0200Centerline rumble stripsLF A16,685$0.28$0.20$0.20$0.20
0210Adjust drainage structureEACH A1$782.53$1,200.00$6,450.00$1,500.00
0220Electronic delivery MGMT systemLS A1$4,475.26$0.01$1.00$1.00
0230DemobilizationLS A1$31,410$8,575.00$8,948.76$9,500.00
KYTC contract 25-2065: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of February 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy