KYTC contract 25-2309 bid tabulation
ASPHALT RESURFACING DIXIE HIGHWAY (US 25). Let by Kentucky Transportation Cabinet on July 24, 2025. 2 bids received; low bid $762,636 by Eaton Asphalt Paving Co Inc, -9.2% against the engineer's estimate of $840,002.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 JUL 2025
- Pay items
- 48
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eaton Asphalt Paving Co Inc | $762,636 | Low | -9.0% |
| 2 | Riegler Blacktop Inc | $858,061 | +13% | +2.0% |
Engineer's estimate: $840,002.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eaton Asphalt Paving Co Inc | 2. Riegler Blacktop Inc |
|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A A | 356 | $118.50 | $122.00 |
| 0020 | CL3 asph surf 0.38B PG64-22 | TON A A | 3,559 | $118.50 | $122.00 |
| 0030 | Temporary signs | SQFT A A | 370 | $5.00 | $10.60 |
| 0040 | Maintain & control traffic | LS A A | 1 | $18,025 | $20,000 |
| 0050 | Portable changeable message sign | EACH A A | 3 | $1,250.00 | $800.00 |
| 0060 | Mobilization for mill & text | LS A A | 1 | $1,875.00 | $6,700.00 |
| 0070 | Asphalt pave milling & texturing | TON A A | 3,559 | $18.75 | $35.00 |
| 0080 | Arrow panel | EACH A A | 2 | $225.00 | $500.00 |
| 0090 | Base failure repair | SQYD A A | 15 | $455.00 | $300.00 |
| 0100 | Pave striping-temp paint-4 in | LF A A | 20,022 | $0.18 | $0.18 |
| 0110 | Pave striping-thermo-6 in W | LF A A | 19,264 | $1.15 | $1.15 |
| 0120 | Pave striping-thermo-6 in Y | LF A A | 24,845 | $1.15 | $1.15 |
| 0130 | Pave striping-thermo-12 in W | LF A A | 300 | $3.50 | $3.50 |
| 0140 | Pave marking-thermo X-walk-6 in | LF A A | 1,703 | $5.00 | $5.00 |
| 0150 | Pave marking-thermo stop bar-24IN | LF A A | 479 | $10.00 | $10.00 |
| 0160 | Pave marking-thermo cross-hatch | SQFT A A | 823 | $4.50 | $4.50 |
| 0170 | Pave marking-thermo STR arrow | EACH A A | 3 | $110.00 | $110.00 |
| 0180 | Pave marking-thermo curv arrow | EACH A A | 54 | $120.00 | $120.00 |
| 0190 | Pave marking-thermo comb arrow | EACH A A | 11 | $140.00 | $140.00 |
| 0200 | Pave marking-thermo only | EACH A A | 2 | $300.00 | $300.00 |
| 0210 | Pavement marking removal | SQFT A A | 46 | $5.00 | $5.00 |
| 0220 | Fuel adjustment | DOLL A A | 6,125 | $1.00 | $1.00 |
| 0230 | Asphalt adjustment | DOLL A A | 15,384 | $1.00 | $1.00 |
| 0240 | Pave mark temp paint stop bar | LF A A | 479 | $15.00 | $15.00 |
| 0250 | Pave mark temp paint line arrow | EACH A A | 68 | $65.00 | $65.00 |
| 0260 | Pave marking-thermo yield bar-36 in | LF A A | 40 | $55.00 | $55.00 |
| 0270 | Water blasting existing stripe | LF A A | 280 | $10.00 | $10.00 |
| 0280 | Pave mark TY 1 tape X-walk-6 in | LF A A | 134 | $10.00 | $10.00 |
| 0290 | Pave mark TY 1 tape cross-hatch | SQFT A A | 28 | $18.00 | $18.00 |
| 0300 | Pave mark TY 1 tape-straight arrow | EACH A A | 1 | $500.00 | $500.00 |
| 0310 | Pave mark-thermo-X-walk-24 in | LF A A | 441 | $12.00 | $12.00 |
| 0320 | Pave mark TY 1 tape stop bar-24 in | LF A A | 23 | $32.00 | $32.00 |
| 0330 | Pave mark TY 1 tape-curv arrow | EACH A A | 1 | $475.00 | $475.00 |
| 0340 | Pave mark-thermo "bus" 8 FT | EACH A A | 2 | $400.00 | $400.00 |
| 0350 | Pave mark thermo chevron | SQFT A A | 138 | $6.00 | $6.00 |
| 0360 | Remove pavement marker | EACH A A | 663 | $6.50 | $5.00 |
| 0370 | Asphalt material for tack non-tracking | TON A A | 21 | $1.00 | $1.00 |
| 0380 | Install radar presence detector type A | EACH A A | 25 | $925.00 | $1,018.00 |
| 0390 | Pave mark TY 1 tape cone cap-solid Y | SQFT A A | 56 | $20.00 | $20.00 |
| 0400 | Temporary signs | SQFT A A | 60 | $5.00 | $10.60 |
| 0410 | Maintain & control traffic | LS A A | 1 | $1,350.00 | $15,000 |
| 0420 | Portable changeable message sign | EACH A A | 3 | $1,250.00 | $800.00 |
| 0430 | Install LED signal-3 section | EACH A A | 7 | $750.00 | $825.00 |
| 0440 | Install LED signal- 4 section | EACH A A | 2 | $450.00 | $495.00 |
| 0450 | Install signal controller-TY atc | EACH A A | 2 | $7,500.00 | $8,250.00 |
| 0460 | Remove signal equipment | EACH A A | 4 | $200.00 | $220.00 |
| 0470 | Remove signal equipment | EACH A A | 2 | $1,000.00 | $1,100.00 |
| 0480 | Demobilization | LS A A | 1 | $11,120 | $12,900 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of July 24, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.