KYTC contract 25-2989 bid tabulation
BRIDGE REPAIR MISCELLANEOUS WORK SIMON KENTON BRIDGE OVER OHIO RIVER (US 62). Let by Kentucky Transportation Cabinet on September 25, 2025. 4 bids received; low bid $22,602,000 by Structural Technologies LLC, -6.3% against the engineer's estimate of $24,115,857.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 SEP 2025
- Pay items
- 24
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Structural Technologies LLC | $22,602,000 | Low | -6.0% |
| 2 | Brayman Construction Corporation | $22,997,400 | +2.0% | -5.0% |
| 3 | American Bridge Company | $29,199,360 | +29% | +21% |
| 4 | American Contracting & Services Inc | $33,039,736 | +46% | +37% |
Engineer's estimate: $24,115,857.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Structural Technologies LLC | 2. Brayman Construction Corporation | 3. American Bridge Company | 4. American Contracting & Services Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Maintain & control traffic | LS A A | 1 | $366,463 | $50,000 | $40,800 | $200,000 |
| 0020 | Portable changeable message sign | EACH A A | 14 | $24,200 | $9,000.00 | $15,555 | $15,000 |
| 0030 | Staking | LS A A | 1 | $334,569 | $152,000 | $90,465 | $100,000 |
| 0040 | Expan joint replace 1 1/2 in | LF A A | 40 | $8,701.00 | $10,000 | $8,915.00 | $6,500.00 |
| 0050 | Eliminate transverse joint | LF A A | 58 | $1,569.00 | $2,000.00 | $1,725.00 | $500.00 |
| 0060 | Concrete-class M 1 | CUYD A A | 4 | $26,051 | $40,000 | $25,395 | $25,000 |
| 0070 | Steel reinforcement-epoxy coated | LB A A | 2,500 | $67.00 | $20.00 | $16.40 | $10.00 |
| 0080 | Blast cleaning | SQYD A A | 457 | $132.00 | $20.00 | $2.00 | $40.00 |
| 0090 | Bridge handrail repair | LF A A | 118 | $301.00 | $1,000.00 | $1,015.00 | $695.00 |
| 0100 | Bridge handrail repair | LF A A | 178 | $641.00 | $2,000.00 | $1,107.00 | $1,200.00 |
| 0110 | Concrete patching repair | SQFT A A | 670 | $453.00 | $450.00 | $290.00 | $400.00 |
| 0120 | Steel repair | LS A A | 1 | $198,742 | $250,000 | $235,000 | $350,000 |
| 0130 | Epoxy-urethane waterproofing | SQFT A A | 4,108 | $10.00 | $20.00 | $7.25 | $15.00 |
| 0140 | Joint seal replacement | LF A A | 60 | $1,427.00 | $500.00 | $1,200.00 | $200.00 |
| 0150 | Handrail connection repair | EACH A A | 3 | $7,550.00 | $10,000 | $8,700.00 | $10,000 |
| 0160 | Handrail connection repair | EACH A A | 30 | $2,876.00 | $2,000.00 | $6,815.00 | $830.00 |
| 0170 | Epoxy injection crack repair | LF A A | 800 | $126.00 | $100.00 | $454.00 | $150.00 |
| 0180 | Bolt repair | EACH A A | 880 | $4,000.00 | $2,000.00 | $4,403.00 | $3,100.00 |
| 0190 | Suspender collar repair | EACH A A | 136 | $96,378 | $111,000 | $133,000 | $170,500 |
| 0200 | Handrail splice replacement | LS A A | 1 | $1,576,042 | $2,000,000 | $2,911,350 | $2,800,000 |
| 0210 | Galvanic anode | EACH A A | 737 | $96.00 | $300.00 | $106.00 | $150.00 |
| 0220 | Concrete coating | SQFT A A | 13,300 | $10.00 | $15.00 | $5.65 | $10.00 |
| 0230 | Mobilization | LS A A | 1 | $1,056,564 | $1,000,000 | $1,370,000 | $1,486,788 |
| 0240 | Demobilization | LS A A | 1 | $339,034 | $350,000 | $411,275 | $488,988 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.