KYTC contract 25-3074 bid tabulation
ASPHALT RESURFACING VARIOUS ROADS IN LOGAN CO. Let by Kentucky Transportation Cabinet on July 24, 2025. 2 bids received; low bid $742,149 by Scotty'S Contracting & Stone LLC, -11% against the engineer's estimate of $834,540.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 JUL 2025
- Pay items
- 20
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $742,149 | Low | -11% |
| 2 | Cleary Construction Inc | $798,500 | +8.0% | -4.0% |
Engineer's estimate: $834,540.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 300 | $51.32 | $48.00 |
| 0020 | Leveling & wedging PG64-22 | TON A A | 543 | $99.48 | $108.00 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A A | 3,495 | $95.04 | $109.00 |
| 0040 | Temporary signs | SQFT A A | 560 | $5.45 | $5.00 |
| 0050 | Maintain & control traffic | LS A A | 1 | $10,150 | $3,500.00 |
| 0060 | Maintain & control traffic | LS A A | 1 | $11,712 | $3,500.00 |
| 0070 | Mobilization for mill & text | LS A A | 1 | $6,132.16 | $3,500.00 |
| 0080 | Mobilization for mill & text | LS A A | 1 | $5,845.46 | $3,500.00 |
| 0090 | Asphalt pave milling & texturing | TON A A | 180 | $24.08 | $135.00 |
| 0100 | Edgeline rumble strips | LF A A | 3,500 | $1.85 | $1.75 |
| 0110 | Base failure repair | SQYD A A | 3,460 | $66.46 | $66.00 |
| 0120 | Pave striping-temp paint-4 in | LF A A | 15,000 | $0.01 | $0.31 |
| 0130 | Pave striping-perm paint-4 in | LF A A | 84,500 | $0.32 | $0.32 |
| 0140 | Pave marking-thermo R 6 FT | EACH A A | 4 | $150.00 | $150.00 |
| 0150 | Pave marking-R/R xbucks 16 in | LF A A | 88 | $10.00 | $10.00 |
| 0160 | Pave marking-thermo stop bar-24IN | LF A A | 94 | $15.00 | $15.00 |
| 0170 | Fuel adjustment | DOLL A A | 6,411 | $1.00 | $1.00 |
| 0180 | Asphalt adjustment | DOLL A A | 15,787 | $1.00 | $1.00 |
| 0190 | Asphalt material for tack non-tracking | TON A A | 30 | $0.01 | $1.00 |
| 0200 | Demobilization | LS A A | 1 | $10,640 | $12,108 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of July 24, 2025. Compiled by Mirage Metrics.