KYTC contract 25-4205 bid tabulation

ASPHALT SURFACE WITH GRADE & DRAIN BURGIN ROAD (KY 152). Let by Kentucky Transportation Cabinet on August 21, 2025. 3 bids received; low bid $344,828 by Mago Construction Company LLC, -1.5% against the engineer's estimate of $350,194.

Owner
Kentucky Transportation Cabinet
Letting
21 AUG 2025
Pay items
40
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Mago Construction Company LLC$344,828Low-2.0%
2Delmae LLC$361,695+5.0%+3.0%
3Rame Contracting LLC$406,731+18%+16%
KYTC contract 25-4205: bids by rank

Engineer's estimate: $350,194.

Bid tabulation

LinePay itemUnitQuantity1. Mago Construction Company LLC2. Delmae LLC3. Rame Contracting LLC
0010Dga baseTON A A139$125.00$120.00$135.20
0020Asphalt seal aggregateTON A A5$3,000.00$3,000.00$3,244.80
0030Asphalt seal coatTON A A0.60$2,250.00$2,250.00$2,433.60
0040Leveling & wedging PG64-22TON A A312$220.00$220.00$237.95
0050CL2 asph base 1.00D PG64-22TON A A77$220.00$220.00$237.95
0060CL2 asph surf 0.38D PG64-22TON A A139$220.00$220.00$237.95
0070Mobilization for mill & textLS A A1$3,500.00$3,500.00$3,785.60
0080Asphalt pave milling & texturingTON A A56$12.00$12.00$12.98
0090Asphalt material for tack non-trackingTON A A0.90$1.00$1.00$1.08
0100Temp ditchLF A A318$0.50$2.00$0.25
0110Clean temp ditchLF A A159$0.50$1.00$0.10
0120Embankment in placeCUYD A A153$200.00$200.00$425.00
0130Clearing and grubbingLS A A1$5,500.00$20,000$22,533
0140Temporary signsSQFT A A144$6.00$12.00$11.00
0150Maintain & control trafficLS A A1$80,330$75,000$51,848
0160Portable changeable message signEACH A A2$4,550.00$1,600.00$3,200.83
0170Edgeline rumble stripsLF A A1,270$5.00$5.00$5.41
0180Temp silt fenceLF A A318$4.00$6.50$6.00
0190Silt trap type AEACH A A1$200.00$350.00$1,879.76
0200Silt trap type BEACH A A1$250.00$350.00$1,452.94
0210Clean silt trap type AEACH A A1$10.00$50.00$88.98
0220Clean silt trap type BEACH A A1$10.00$50.00$88.98
0230StakingLS A A1$7,000.00$5,000.00$22,000
0240Temp signal 2 phaseEACH A A1$10,000$5,000.00$9,900.00
0250Erosion control blanketSQYD A A530$3.60$5.00$3.89
0260Temp mulchSQYD A A1,940$0.49$0.30$0.53
0270Temp seeding and protectionSQYD A A1,450$0.50$1.50$0.54
0280Initial fertilizerTON A A0.07$1,285.00$5,000.00$1,389.86
0290Maintenance fertilizerTON A A0.04$1,285.00$5,000.00$1,390.00
0300Seeding and protectionSQYD A A670$1.14$5.00$1.24
0310Agricultural limestoneTON A A0.40$46.00$1,500.00$49.78
0320Pave striping-temp paint-4 inLF A A2,500$0.50$0.50$0.54
0330Pave striping-thermo-4 in WLF A A1,270$1.50$1.50$1.62
0340Pave striping-thermo-4 in YLF A A1,270$1.50$1.50$1.62
0350Sawcut pavementLF A A408$7.50$10.00$12.50
0360Remove-store and reinstall signEACH A A2$616.78$1,250.00$984.03
0370Longitudinal edge keyLF A A1,350$7.50$7.50$8.11
0380Entrance pipe-15 inLF A A63$140.00$70.00$134.32
0390Remove pipeLF A A57$20.00$30.00$96.69
0400DemobilizationLS A A1$5,100.00$20,000$6,095.00
KYTC contract 25-4205: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy