KYTC contract 25-4501 bid tabulation
WIDENING DAWSON SPRINGS ROAD (KY 109). Let by Kentucky Transportation Cabinet on February 20, 2025, Christian, District 2. 2 bids received; low bid $2,602,167 by Westate Construction Inc, +6.2% against the engineer's estimate of $2,450,852.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 FEB 2025
- Pay items
- 62
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Westate Construction Inc | $2,602,167 | Low | +6.0% |
| 2 | Cleary Construction Inc | $4,520,000 | +74% | +84% |
Engineer's estimate: $2,450,852.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Westate Construction Inc | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A | 112 | $70.00 | $165.00 |
| 0020 | Crushed aggregate size no 23 | TON A | 200 | $50.00 | $63.00 |
| 0050 | Leveling & wedging PG64-22 | TON A | 795 | $97.00 | $97.00 |
| 0060 | CL2 asph base 1.00D PG64-22 | TON A | 4,634 | $120.00 | $180.00 |
| 0070 | CL2 asph surf 0.38D PG64-22 | TON A | 4,300 | $96.59 | $96.59 |
| 0080 | Cem conc ent pavement-8 in | SQYD A | 29 | $180.00 | $265.00 |
| 0090 | Temporary signs | SQFT A | 290 | $13.23 | $6.00 |
| 0100 | Maintain & control traffic | LS A | 1 | $8,360.84 | $225,000 |
| 0110 | Mobilization for mill & text | LS A | 1 | $2,500.00 | $3,500.00 |
| 0120 | Asphalt pave milling & texturing | TON A | 30 | $300.00 | $22.00 |
| 0130 | Edgeline rumble strips | LF A | 61,000 | $0.28 | $0.28 |
| 0140 | Pave striping-temp paint-4 in | LF A | 120,000 | $0.31 | $0.31 |
| 0150 | Pave striping-perm paint-6 in | LF A | 87,000 | $0.36 | $0.36 |
| 0160 | Fuel adjustment | DOLL A | 13,906 | $1.00 | $1.00 |
| 0170 | Asphalt adjustment | DOLL A | 34,928 | $1.00 | $1.00 |
| 0180 | Shoulder milling/trenching | SQYD A | 14,753 | $25.00 | $33.00 |
| 0190 | Fiber reinforcement for HMA | TON A | 4,300 | $10.87 | $10.87 |
| 0200 | Asphalt material for tack non-tracking | TON A | 37.30 | $1,137.45 | $945.33 |
| 0210 | Electronic delivery MGMT system | LS A | 1 | $1.00 | $1.00 |
| 0220 | Temp ditch | LF A | 15,840 | $1.00 | $1.00 |
| 0230 | Clean temp ditch | LF A | 7,920 | $0.50 | $0.01 |
| 0240 | Embankment in place | CUYD A | 5,661 | $75.00 | $175.00 |
| 0250 | Channel lining class II | TON A | 226 | $55.00 | $70.00 |
| 0260 | Temporary signs | SQFT A | 210 | $13.23 | $6.00 |
| 0270 | Fabric-geotextile class 1 | SQYD A | 193 | $5.25 | $20.00 |
| 0280 | Maintain & control traffic | LS A | 1 | $66,800 | $475,000 |
| 0290 | Portable changeable message sign | EACH A | 2 | $4,815.00 | $2,968.00 |
| 0300 | Temp silt fence | LF A | 15,840 | $2.80 | $5.50 |
| 0310 | Silt trap type A | EACH A | 10 | $50.00 | $400.00 |
| 0320 | Silt trap type B | EACH A | 10 | $200.00 | $200.00 |
| 0330 | Silt trap type C | EACH A | 10 | $450.00 | $360.00 |
| 0340 | Clean silt trap type A | EACH A | 10 | $31.00 | $1.00 |
| 0350 | Clean silt trap type B | EACH A | 10 | $35.00 | $1.00 |
| 0360 | Clean silt trap type C | EACH A | 10 | $30.00 | $1.00 |
| 0370 | Staking | LS A | 1 | $24,800 | $225,000 |
| 0380 | Erosion control blanket | SQYD A | 20,111 | $2.50 | $3.31 |
| 0390 | Temp mulch | SQYD A | 31,657 | $0.40 | $0.42 |
| 0400 | Temp seeding and protection | SQYD A | 23,743 | $0.40 | $0.43 |
| 0410 | Initial fertilizer | TON A | 1.64 | $1,500.00 | $1,265.71 |
| 0420 | Maintenance fertilizer | TON A | 2.74 | $1,500.00 | $1,265.71 |
| 0430 | Seeding and protection | SQYD A | 32,783 | $0.80 | $0.77 |
| 0440 | Agricultural limestone | TON A | 32.79 | $100.00 | $87.32 |
| 0450 | Entrance pipe-15 in | LF A | 135 | $118.00 | $100.00 |
| 0460 | Entrance pipe-18 in | LF A | 79 | $121.00 | $125.00 |
| 0470 | Culvert pipe-18 in | LF A | 69 | $152.00 | $255.00 |
| 0480 | Culvert pipe-24 in | LF A | 5 | $170.00 | $600.00 |
| 0490 | Remove pipe | LF A | 242 | $11.00 | $48.00 |
| 0500 | Safety box inlet-18 in SDB-1 | EACH A | 1 | $6,800.00 | $6,600.00 |
| 0510 | Safety box inlet-24 in DBL SDB-5 | EACH A | 1 | $8,600.00 | $9,500.00 |
| 0520 | Remove headwall | EACH A | 7 | $250.00 | $925.00 |
| 0530 | Fittings | EACH A | 6 | $470.00 | $3,750.00 |
| 0540 | Fittings | EACH A | 1 | $520.00 | $3,750.00 |
| 0550 | Sloped and mitered headwall-18 in | EACH A | 5 | $4,200.00 | $4,250.00 |
| 0560 | SBM alum sheet signs .080 in | SQFT A | 330.70 | $46.21 | $46.21 |
| 0570 | SBM alum sheet signs .125 in | SQFT A | 107.90 | $47.86 | $47.86 |
| 0580 | Steel post type 1 | LF A | 975 | $32.03 | $32.03 |
| 0590 | Class A concrete for signs | CUYD A | 2 | $2,541.80 | $2,541.80 |
| 0600 | Remove-store and reinstall sign | EACH A | 1 | $616.78 | $616.78 |
| 0610 | Remove sign | EACH A | 49 | $92.11 | $92.11 |
| 0620 | GMSS type D | EACH A | 8 | $459.95 | $459.95 |
| 0630 | Barcode sign inventory | EACH A | 135 | $46.06 | $46.06 |
| 0640 | Demobilization | LS A | 1 | $39,033 | $69,087 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of February 20, 2025. Compiled by Mirage Metrics.