KYTC contract 25-5392 bid tabulation
BRIDGE REPLACEMENT KY 2057. Let by Kentucky Transportation Cabinet on September 25, 2025. 2 bids received; low bid $1,685,298 by M & M Services Co Inc, -7.4% against the engineer's estimate of $1,820,265.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 SEP 2025
- Pay items
- 53
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | M & M Services Co Inc | $1,685,298 | Low | -7.0% |
| 2 | Jave LLC | $1,754,355 | +4.0% | -4.0% |
Engineer's estimate: $1,820,265.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M & M Services Co Inc | 2. Jave LLC |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 37 | $65.00 | $197.20 |
| 0020 | Asphalt seal aggregate | TON A A | 2.02 | $2,500.00 | $10.10 |
| 0030 | Asphalt seal coat | TON A A | 0.24 | $2,500.00 | $10.10 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 71 | $165.00 | $453.64 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 67 | $165.00 | $463.84 |
| 0060 | Asphalt material for tack non-tracking | TON A A | 0.48 | $1,500.00 | $11.23 |
| 0070 | Delineator for guardrail BI directional white | EACH A A | 8 | $16.00 | $17.25 |
| 0080 | Embankment in place | CUYD A A | 76 | $175.00 | $97.66 |
| 0090 | Guardrail-steel W beam-S face | LF A A | 50 | $34.00 | $34.22 |
| 0100 | Guardrail-steel W beam-S face A | LF A A | 75 | $65.00 | $64.67 |
| 0110 | Guardrail terminal section no 1 | EACH A A | 2 | $80.00 | $79.90 |
| 0120 | Guardrail end treatment type 7 | EACH A A | 1 | $2,000.00 | $1,877.06 |
| 0130 | Remove guardrail | LF A A | 75 | $5.00 | $4.93 |
| 0140 | Right-of-way monument type 1 | EACH A A | 7 | $170.00 | $168.28 |
| 0150 | Witness post | EACH A A | 7 | $155.00 | $151.56 |
| 0160 | Clearing and grubbing | LS A A | 1 | $9,800.00 | $20,766 |
| 0170 | Edge key | LF A A | 20.10 | $15.00 | $92.42 |
| 0180 | Maintain & control traffic | LS A A | 1 | $85,000 | $82,366 |
| 0190 | Portable changeable message sign | EACH A A | 3 | $3,900.00 | $4,164.48 |
| 0200 | Staking | LS A A | 1 | $15,000 | $5,612.50 |
| 0210 | Remove structure | LS A A | 1 | $45,000 | $49,789 |
| 0220 | Conc barrier wall type 9T | LF A A | 40 | $35.00 | $197.56 |
| 0230 | Pave striping-perm paint-4 in | LF A A | 704 | $2.00 | $2.12 |
| 0240 | Pave striping-dur TY 1-4 in Y | LF A A | 196 | $4.00 | $12.73 |
| 0250 | Crash cushion TY 6 class B TL2 | EACH A A | 2 | $6,000.00 | $5,575.85 |
| 0252 | W serv PE/PLST long side 3/4 in | EACH A A | 1 | $15,000 | $6,735.00 |
| 0256 | W meter with PRV 3/4 inch | EACH A A | 1 | $15,000 | $4,490.00 |
| 0260 | Sawcut pavement | LF A A | 67 | $15.00 | $28.06 |
| 0270 | Remove-store and reinstall sign | EACH A A | 1 | $600.00 | $1,010.00 |
| 0280 | Erosion control | LS A A | 1 | $15,000 | $7,857.50 |
| 0290 | Structure granular backfill | CUYD A A | 365 | $65.00 | $118.99 |
| 0300 | Concrete-class B | CUYD A A | 31 | $1,250.00 | $477.06 |
| 0310 | Armored edge for concrete | LF A A | 56 | $105.00 | $163.89 |
| 0320 | Foundation preparation | LS A A | 1 | $49,000 | $53,768 |
| 0330 | Cyclopean stone rip rap | TON A A | 270 | $95.00 | $81.94 |
| 0340 | Test piles | LF A A | 66 | $350.00 | $233.48 |
| 0350 | Pre-drilling for piles | LF A A | 470 | $200.00 | $357.89 |
| 0360 | Piles-steel HP18X204 | LF A A | 196 | $290.00 | $351.34 |
| 0370 | Piles-steel HP14X117 | LF A A | 365 | $255.00 | $233.48 |
| 0380 | Pile points-14 in | EACH A A | 15 | $245.00 | $184.09 |
| 0390 | Concrete-class A | CUYD A A | 131 | $1,205.00 | $1,480.58 |
| 0400 | Concrete-class AA | CUYD A A | 67 | $1,450.00 | $1,617.52 |
| 0410 | Mechanical reinf coupler #5 epoxy coated | EACH A A | 115 | $150.00 | $59.49 |
| 0420 | Steel reinforcement-epoxy coated | LB A A | 23,708 | $2.35 | $2.66 |
| 0430 | Precast PC box beam CB42-48 | LF A A | 686 | $675.00 | $653.30 |
| 0440 | Concrete sealing | SQFT A A | 4,316 | $3.00 | $1.50 |
| 0450 | Mechanical reinf coupler #8-epoxy coated | EACH A A | 18 | $205.00 | $142.56 |
| 0460 | Remove stone masonry wall | LF A A | 128 | $500.00 | $355.83 |
| 0470 | Reconstruct stone masonry wall | LF A A | 15 | $1,050.00 | $323.28 |
| 0480 | Deep beam bridge guardrail | LF A A | 196 | $265.00 | $258.95 |
| 0490 | Concrete coating | SQFT A A | 690 | $10.00 | $4.18 |
| 0500 | Mobilization for concrete surf treatment | LS A A | 1 | $15,000 | $3,928.75 |
| 0510 | Demobilization | LS A A | 1 | $25,000 | $25,926 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.