KYTC contract 26-1113 bid tabulation
ASPHALT SURFACE WITH GRADE & DRAIN BRANNON ROAD (KY 1980). Let by Kentucky Transportation Cabinet on March 26, 2026. 2 bids received; low bid $28,532,686 by The Allen Company Inc, -22% against the engineer's estimate of $36,491,583.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 26 MAR 2026
- Pay items
- 280
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | The Allen Company Inc | $28,532,686 | Low | -22% |
| 2 | Louisville Paving Company Inc | $35,486,848 | +24% | -3.0% |
Engineer's estimate: $36,491,583.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. The Allen Company Inc | 2. Louisville Paving Company Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 62,006 | $32.65 | $40.50 |
| 0020 | Traffic bound base | TON A A | 146 | $32.65 | $50.00 |
| 0030 | Asphalt seal aggregate | TON A A | 184 | $150.00 | $152.00 |
| 0040 | Asphalt seal coat | TON A A | 22 | $1,150.00 | $1,127.50 |
| 0050 | Leveling & wedging PG64-22 | TON A A | 1,497 | $114.25 | $115.00 |
| 0060 | CL2 asph base 1.00D PG64-22 | TON A A | 32,024 | $92.75 | $91.00 |
| 0070 | CL2 asph base 0.75D PG64-22 | TON A A | 2,957 | $98.00 | $97.00 |
| 0080 | Asphalt prime coat | TON A A | 98.60 | $925.00 | $920.00 |
| 0090 | CL2 asph surf 0.38D PG64-22 | TON A A | 4,066 | $114.25 | $115.00 |
| 0100 | CL2 asph surf 0.38B PG64-22 | TON A A | 6,250 | $118.75 | $120.00 |
| 0110 | Asphalt material for tack | TON A A | 82.60 | $800.00 | $790.00 |
| 0120 | Cement concrete island | SQYD A A | 1,266 | $50.20 | $50.17 |
| 0130 | JPC pavement-8 in | SQYD A A | 498 | $143.17 | $143.09 |
| 0140 | Cem conc ent pavement-8 in | SQYD A A | 3,442 | $111.84 | $111.77 |
| 0150 | Mobilization for mill & text | LS A A | 1 | $4,500.00 | $4,000.00 |
| 0160 | Asphalt pave milling & texturing | TON A A | 152 | $85.00 | $88.00 |
| 0170 | Sand for blotter | TON A A | 293 | $35.00 | $32.00 |
| 0180 | Joint adhesive | LF A A | 3,225 | $0.85 | $0.80 |
| 0190 | Crushed aggregate size no 2 | TON A A | 94,230 | $26.00 | $32.00 |
| 0200 | Perforated pipe-4 in | LF A A | 1,006 | $16.50 | $20.00 |
| 0210 | Perforated pipe edge drain-4 in | LF A A | 14,429 | $8.20 | $7.50 |
| 0220 | Non-perforated pipe-4 in | LF A A | 690 | $18.26 | $20.00 |
| 0230 | Inspect & certify edge drain system | LS A A | 1 | $7,500.00 | $9,000.00 |
| 0240 | Perf pipe headwall TY 1-4 in | EACH A A | 10 | $1,025.00 | $550.00 |
| 0250 | Perf pipe headwall TY 2-4 in | EACH A A | 1 | $1,025.00 | $575.00 |
| 0260 | Perf pipe headwall TY 3-4 in | EACH A A | 1 | $1,025.00 | $600.00 |
| 0270 | Perf pipe headwall TY 4-4 in | EACH A A | 3 | $1,025.00 | $600.00 |
| 0280 | Cored hole drainage box con-4 in | EACH A A | 55 | $125.00 | $300.00 |
| 0290 | Standard curb and gutter | LF A A | 16,133 | $29.24 | $29.22 |
| 0300 | Standard curb and gutter mod | LF A A | 241 | $29.93 | $29.92 |
| 0310 | Lip curb and gutter mod | LF A A | 1,104 | $22.81 | $22.80 |
| 0320 | Island curb and gutter | LF A A | 419 | $48.24 | $48.21 |
| 0330 | Standard integral curb | LF A A | 340 | $23.99 | $23.98 |
| 0340 | Standard header curb | LF A A | 612.50 | $45.76 | $45.74 |
| 0350 | Conc terminal section type 1 | EACH A A | 1 | $4,773.88 | $4,771.15 |
| 0360 | Delineator for guardrail BI directional white | EACH A A | 53 | $14.27 | $13.00 |
| 0370 | Delineator for barrier wall-B/W | EACH A A | 33 | $15.50 | $14.90 |
| 0380 | Curb to barrier wall trans | EACH A A | 2 | $7,602.86 | $7,598.52 |
| 0390 | Barricade-type III | EACH A A | 28 | $230.00 | $210.00 |
| 0400 | Remove pavement | SQYD A A | 5,077 | $8.00 | $5.50 |
| 0410 | Paved ditch type 1 | SQYD A A | 8 | $350.00 | $385.04 |
| 0420 | Temp ditch | LF A A | 10,523 | $0.01 | $2.29 |
| 0430 | Clean temp ditch | LF A A | 5,261 | $0.01 | $2.29 |
| 0440 | Granular embankment | CUYD A A | 7,444 | $33.00 | $55.00 |
| 0450 | Embankment in place | CUYD A A | 243,992 | $14.85 | $23.00 |
| 0460 | Water | MGAL A A | 791 | $0.01 | $1.00 |
| 0470 | Guardrail-steel W beam-S face | LF A A | 5,260 | $31.91 | $29.50 |
| 0480 | Guardrail terminal section no 1 | EACH A A | 6 | $87.06 | $85.00 |
| 0490 | Guardrail end treatment type 1 | EACH A A | 9 | $3,409.24 | $3,600.00 |
| 0500 | Guardrail end treatment type 2M | EACH A A | 8 | $1,915.33 | $2,200.00 |
| 0510 | Guardrail end treatment type 4A | EACH A A | 1 | $3,727.28 | $3,600.00 |
| 0520 | Temp guardrail | LF A A | 387.50 | $17.83 | $18.00 |
| 0530 | Extra length guardrail post | EACH A A | 660 | $14.54 | $118.00 |
| 0540 | Right-of-way monument type 1 | EACH A A | 104 | $150.00 | $150.00 |
| 0550 | Witness post | EACH A A | 104 | $130.00 | $110.00 |
| 0560 | Channel lining class II | TON A A | 1,040 | $48.75 | $59.32 |
| 0570 | Channel lining class III | TON A A | 5,628 | $51.75 | $68.41 |
| 0580 | Clearing and grubbing | LS A A | 1 | $200,000 | $400,000 |
| 0590 | Concrete-class B | CUYD A A | 271 | $798.72 | $830.59 |
| 0600 | Temporary signs | SQFT A A | 1,450 | $14.75 | $14.00 |
| 0610 | Edge key | LF A A | 1,287 | $24.50 | $5.83 |
| 0620 | Fabric-geotextile class 1 | SQYD A A | 119,997 | $1.95 | $1.56 |
| 0630 | Fabric-geotextile class 2 | SQYD A A | 33,789 | $2.00 | $1.44 |
| 0640 | Fabric-geotextile class 2 for pipe | SQYD A A | 42,820 | $2.00 | $2.00 |
| 0650 | Fabric-geotextile class 4A | SQYD A A | 131,152 | $2.90 | $2.56 |
| 0660 | Handrail-type A-1 | LF A A | 600 | $91.00 | $91.00 |
| 0670 | Maintain & control traffic | LS A A | 1 | $250,000 | $1,750,000 |
| 0680 | Diversions (by-pass detours) | LS A A | 1 | $5,800.00 | $12,000 |
| 0690 | Diversions (by-pass detours) | LS A A | 1 | $18,750 | $105,000 |
| 0700 | Diversions (by-pass detours) | LS A A | 1 | $15,250 | $65,000 |
| 0710 | Diversions (by-pass detours) | LS A A | 1 | $3,400.00 | $8,000.00 |
| 0720 | Diversions (by-pass detours) | LS A A | 1 | $5,200.00 | $5,500.00 |
| 0730 | Portable changeable message sign | EACH A A | 3 | $15,000 | $11,400 |
| 0740 | Safeloading | CUYD A A | 85.50 | $360.00 | $500.00 |
| 0750 | Settlement platform | EACH A A | 2 | $2,920.00 | $7,000.00 |
| 0760 | Edgeline rumble strips | LF A A | 20,567 | $0.25 | $0.25 |
| 0770 | Temp silt fence | LF A A | 10,523 | $2.90 | $1.82 |
| 0780 | Silt trap type A | EACH A A | 76 | $1.00 | $319.01 |
| 0790 | Silt trap type B | EACH A A | 76 | $195.00 | $866.43 |
| 0800 | Silt trap type C | EACH A A | 76 | $195.00 | $131.60 |
| 0810 | Clean silt trap type A | EACH A A | 152 | $0.01 | $110.61 |
| 0820 | Clean silt trap type B | EACH A A | 152 | $35.00 | $110.61 |
| 0830 | Clean silt trap type C | EACH A A | 152 | $35.00 | $13.73 |
| 0840 | Sidewalk-4 in concrete | SQYD A A | 1,015 | $67.36 | $67.32 |
| 0850 | Staking | LS A A | 1 | $50,000 | $200,000 |
| 0860 | Remove structure | LS A A | 1 | $6,100.00 | $4,422.40 |
| 0870 | Remove structure | LS A A | 1 | $6,100.00 | $11,913 |
| 0880 | Conc barrier wall type 9T | LF A A | 3,225 | $33.50 | $86.73 |
| 0890 | Steel pipe-2 1/2 in | LF A A | 64 | $100.00 | $100.00 |
| 0900 | Steel pipe-4 in | LF A A | 60 | $130.00 | $100.00 |
| 0910 | Temp relocation of signal head | EACH A A | 17 | $510.20 | $250.00 |
| 0920 | Erosion control blanket | SQYD A A | 7,858 | $2.00 | $1.78 |
| 0930 | Temp mulch | SQYD A A | 247,588 | $0.01 | $0.26 |
| 0940 | Temp seeding and protection | SQYD A A | 184,767 | $0.01 | $0.33 |
| 0950 | Initial fertilizer | TON A A | 11 | $2,000.00 | $975.00 |
| 0960 | Maintenance fertilizer | TON A A | 19.10 | $500.00 | $975.00 |
| 0970 | Seeding and protection | SQYD A A | 369,534 | $0.30 | $0.54 |
| 0980 | Special seeding crown vetch | SQYD A A | 71,150 | $0.30 | $0.40 |
| 0990 | Sodding | SQYD A A | 8,922 | $13.25 | $6.33 |
| 1000 | Agricultural limestone | TON A A | 229.10 | $5.00 | $99.00 |
| 1010 | Topsoil furnished and placed | CUYD A A | 81 | $25.00 | $7.76 |
| 1020 | Pave striping-temp paint-4 in | LF A A | 160,000 | $0.16 | $0.16 |
| 1030 | Pave striping-temp paint-12 in | LF A A | 1,100 | $0.50 | $0.50 |
| 1040 | Pave striping-perm paint-4 in | LF A A | 4,870 | $0.26 | $0.26 |
| 1050 | Pave striping-thermo-6 in W | LF A A | 38,790 | $0.90 | $0.90 |
| 1060 | Pave striping-thermo-6 in Y | LF A A | 39,526 | $0.90 | $0.90 |
| 1070 | Pave striping-thermo-12 in W | LF A A | 94 | $6.00 | $6.00 |
| 1080 | Pave striping-thermo-12 in Y | LF A A | 38 | $6.00 | $6.00 |
| 1090 | Pave striping-dur TY 1-6 in W | LF A A | 366 | $8.00 | $8.00 |
| 1100 | Pave striping-dur TY 1-6 in Y | LF A A | 458 | $8.00 | $8.00 |
| 1110 | Pave marking-thermo X-walk-12 in | LF A A | 2,412 | $4.00 | $4.00 |
| 1120 | Pave marking-thermo stop bar-24IN | LF A A | 541 | $8.00 | $8.00 |
| 1130 | Pave marking-thermo cross-hatch | SQFT A A | 2,200 | $3.00 | $3.00 |
| 1140 | Pave marking-thermo STR arrow | EACH A A | 1 | $100.00 | $100.00 |
| 1150 | Pave marking-thermo curv arrow | EACH A A | 133 | $100.00 | $100.00 |
| 1160 | Pave marking-thermo comb arrow | EACH A A | 13 | $145.00 | $145.00 |
| 1170 | Pave marking-thermo merge arrow | EACH A A | 4 | $300.00 | $300.00 |
| 1180 | Inlaid pavement marker-MW | EACH A A | 141 | $30.00 | $30.00 |
| 1190 | Inlaid pavement marker-by | EACH A A | 741 | $30.00 | $30.00 |
| 1200 | Crash cushion TY 6 class T TL2 | EACH A A | 8 | $4,887.67 | $3,200.00 |
| 1210 | Fuel adjustment | DOLL A A | 171,122 | $1.00 | $1.00 |
| 1220 | Asphalt adjustment | DOLL A A | 183,740 | $1.00 | $1.00 |
| 1230 | Object marker TY 3 | EACH A A | 10 | $33.34 | $85.00 |
| 1240 | Sawcut pavement | LF A A | 263 | $4.50 | $2.85 |
| 1250 | Rolled curb and gutter | LF A A | 336 | $25.29 | $25.27 |
| 1260 | Longitudinal edge key | LF A A | 3,225 | $6.50 | $5.25 |
| 1270 | Pave marking-thermo yield bar-36 in | LF A A | 66 | $45.00 | $45.00 |
| 1280 | Detectable warnings | SQFT A A | 771 | $46.00 | $45.97 |
| 1290 | Turf reinforcement mat 1 | SQYD A A | 21,053 | $5.50 | $5.68 |
| 1300 | Stamped concrete | SQYD A A | 178 | $165.00 | $96.70 |
| 1310 | Yellow paint for median safety nose | SQFT A A | 240 | $5.00 | $6.00 |
| 1320 | Island curb and gutter(modified) | LF A A | 110 | $56.50 | $56.46 |
| 1330 | Security plate assembly | EACH A A | 22 | $300.00 | $221.76 |
| 1340 | Railroad coordination | LS A A | 1 | $432,000 | $425,000 |
| 1350 | Pave marking-thermo dotted lane exten | LF A A | 82 | $7.00 | $7.00 |
| 1360 | Pipeline inspection | LF A A | 6,916 | $2.35 | $2.35 |
| 1370 | Utility coordination | LS A A | 1 | $6,500.00 | $75,000 |
| 1380 | Thrie beam guardrail transition TL-2 | EACH A A | 2 | $3,550.00 | $2,500.00 |
| 1390 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,000.00 | $0.01 |
| 1400 | Roadway gate | EACH A A | 1 | $8,350.00 | $7,500.00 |
| 1410 | Entrance pipe-15 in | LF A A | 1,317 | $50.75 | $107.00 |
| 1420 | Entrance pipe-18 in | LF A A | 697 | $62.60 | $140.00 |
| 1430 | Entrance pipe-24 in | LF A A | 97 | $75.01 | $135.00 |
| 1440 | Culvert pipe-15 in | LF A A | 46 | $56.85 | $125.00 |
| 1450 | Culvert pipe-18 in | LF A A | 318 | $80.50 | $102.00 |
| 1460 | Culvert pipe-24 in | LF A A | 110 | $79.30 | $100.00 |
| 1470 | Culvert pipe-30 in | LF A A | 85 | $141.58 | $195.00 |
| 1480 | Culvert pipe-48 in | LF A A | 237 | $155.23 | $240.00 |
| 1490 | Culvert pipe-60 in | LF A A | 106 | $290.75 | $350.00 |
| 1500 | Culvert pipe-42 in equiv | LF A A | 202 | $307.26 | $280.00 |
| 1510 | Storm sewer pipe-12 in | LF A A | 61 | $51.25 | $110.00 |
| 1520 | Storm sewer pipe-15 in | LF A A | 1,830 | $52.90 | $70.00 |
| 1530 | Storm sewer pipe-18 in | LF A A | 4,074 | $66.30 | $70.00 |
| 1540 | Storm sewer pipe-24 in | LF A A | 1,906 | $85.40 | $82.00 |
| 1550 | Storm sewer pipe-30 in | LF A A | 945 | $104.50 | $115.00 |
| 1560 | Storm sewer pipe-36 in | LF A A | 397 | $171.03 | $160.00 |
| 1570 | Storm sewer pipe-42 in | LF A A | 137 | $206.80 | $205.00 |
| 1580 | Storm sewer pipe-48 in | LF A A | 162 | $178.78 | $210.00 |
| 1590 | Pipe culvert headwall-15 in | EACH A A | 1 | $1,600.00 | $4,500.00 |
| 1600 | Pipe culvert headwall-18 in | EACH A A | 5 | $1,825.00 | $3,000.00 |
| 1610 | Pipe culvert headwall-30 in | EACH A A | 2 | $3,000.00 | $6,500.00 |
| 1620 | Pipe culvert headwall-42 in | EACH A A | 2 | $3,600.00 | $8,000.00 |
| 1630 | Pipe culvert headwall-48 in | EACH A A | 5 | $10,750 | $5,000.00 |
| 1640 | Pipe culvert headwall-60 in | EACH A A | 2 | $13,500 | $7,500.00 |
| 1650 | Remove pipe | LF A A | 126 | $20.00 | $52.00 |
| 1660 | Plug pipe | EACH A A | 1 | $1,000.00 | $1,100.00 |
| 1670 | Sloped box outlet type 1-15 in | EACH A A | 8 | $2,000.00 | $4,000.00 |
| 1680 | Sloped box outlet type 1-18 in | EACH A A | 4 | $2,175.00 | $4,500.00 |
| 1690 | Sloped box outlet type 1-24 in | EACH A A | 1 | $2,750.00 | $5,250.00 |
| 1700 | S & F box inlet-outlet-18 in | EACH A A | 1 | $2,550.00 | $5,500.00 |
| 1710 | S & F box inlet-outlet-24 in | EACH A A | 1 | $4,350.00 | $7,500.00 |
| 1720 | S & F box inlet-outlet-30 in | EACH A A | 1 | $6,500.00 | $10,000 |
| 1730 | S & F box inlet-outlet-36 in | EACH A A | 5 | $8,000.00 | $8,000.00 |
| 1740 | Curb box inlet type A | EACH A A | 41 | $7,525.00 | $7,000.00 |
| 1750 | Curb box inlet type A mod | EACH A A | 3 | $7,850.00 | $7,500.00 |
| 1760 | Curb box inlet type B | EACH A A | 3 | $8,200.00 | $7,250.00 |
| 1770 | Drop box inlet type 1 | EACH A A | 3 | $7,250.00 | $10,500 |
| 1780 | Drop box inlet type 2 | EACH A A | 1 | $8,500.00 | $15,000 |
| 1790 | Drop box inlet type 3 | EACH A A | 10 | $6,800.00 | $10,000 |
| 1800 | Drop box inlet type 5D | EACH A A | 1 | $7,850.00 | $13,000 |
| 1810 | Drop box inlet type 6B | EACH A A | 3 | $9,050.00 | $14,000 |
| 1820 | Drop box inlet type 6C | EACH A A | 1 | $8,450.00 | $14,500 |
| 1830 | Drop box inlet type 6D | EACH A A | 2 | $8,450.00 | $12,500 |
| 1840 | Drop box inlet type 6F | EACH A A | 7 | $8,550.00 | $10,500 |
| 1850 | Drop box inlet type 7 | EACH A A | 3 | $7,550.00 | $13,500 |
| 1860 | Drop box inlet type 11 | EACH A A | 15 | $3,000.00 | $9,000.00 |
| 1870 | Drop box inlet type 12A | LF A A | 24 | $750.00 | $1,500.00 |
| 1880 | Drop box inlet type 13G | EACH A A | 11 | $4,750.00 | $3,636.45 |
| 1890 | Drop box inlet type 13S | EACH A A | 2 | $5,400.00 | $5,600.00 |
| 1900 | Remove drop box inlet | EACH A A | 1 | $750.00 | $2,500.00 |
| 1910 | Junction box-24 in | EACH A A | 3 | $2,300.00 | $6,000.00 |
| 1920 | Junction box-36 in | EACH A A | 3 | $3,550.00 | $5,000.00 |
| 1930 | Junction box-48 in | EACH A A | 1 | $4,800.00 | $9,500.00 |
| 1940 | Manhole type A | EACH A A | 1 | $3,750.00 | $4,500.00 |
| 1950 | Manhole type B | EACH A A | 3 | $3,750.00 | $5,750.00 |
| 1960 | Remove headwall | EACH A A | 2 | $750.00 | $1,750.00 |
| 1970 | Concrete-class A | CUYD A A | 79.60 | $1,290.00 | $1,044.64 |
| 1980 | Steel reinforcement | LB A A | 1,898 | $1.15 | $1.68 |
| 1990 | Curb box inlet type B modified | EACH A A | 1 | $8,700.00 | $8,000.00 |
| 2000 | Entrance pipe-36 in | LF A A | 39 | $157.00 | $275.00 |
| 2010 | Bore and jack pipe-48 in | LF A A | 50 | $1,484.85 | $1,560.71 |
| 2020 | Bore and jack pipe-18 in | LF A A | 127 | $590.63 | $642.48 |
| 2030 | Drainage junction box TY B | EACH A A | 1 | $3,000.00 | $4,500.00 |
| 2040 | Bore and jack pipe-36 in | LF A A | 280 | $898.54 | $912.09 |
| 2050 | Bore and jack pipe-60 in | LF A A | 50 | $2,869.85 | $2,945.71 |
| 2060 | Structure granular backfill | CUYD A A | 468 | $85.00 | $71.00 |
| 2070 | Armored edge for concrete | LF A A | 127.30 | $125.00 | $113.50 |
| 2080 | Conduit-3 in | LF A A | 366 | $50.00 | $42.00 |
| 2090 | Foundation preparation | LS A A | 1 | $55,000 | $77,500 |
| 2100 | Reinf conc slope wall-6 in | SQYD A A | 876 | $195.00 | $402.50 |
| 2110 | Test piles | LF A A | 89 | $225.00 | $218.00 |
| 2120 | Piles-steel HP12X53 | LF A A | 790 | $105.00 | $100.00 |
| 2130 | Pile points-12 in | EACH A A | 22 | $250.00 | $188.00 |
| 2140 | Concrete-class A | CUYD A A | 303.40 | $1,035.00 | $1,157.50 |
| 2150 | Concrete-class AA | CUYD A A | 480 | $1,360.00 | $1,386.00 |
| 2160 | Steel reinforcement | LB A A | 33,822 | $1.87 | $1.80 |
| 2170 | Steel reinforcement-epoxy coated | LB A A | 155,279 | $1.84 | $1.83 |
| 2180 | Bridge chain link fence-7 FT | LF A A | 183 | $157.00 | $182.75 |
| 2190 | Bridge chain link fence-8 FT | LF A A | 183 | $177.00 | $205.00 |
| 2200 | Rock soundings | LF A A | 224 | $65.00 | $79.00 |
| 2210 | Rock corings | LF A A | 224 | $150.00 | $115.00 |
| 2220 | Drilled shaft-66 in (common) | LF A A | 128 | $2,140.00 | $2,529.38 |
| 2230 | Drilled shaft-60 in (solid rock) | LF A A | 88 | $2,415.00 | $3,150.00 |
| 2240 | Concrete sealing | SQFT A A | 26,673 | $2.10 | $1.60 |
| 2250 | Bicycle rail | LF A A | 183 | $112.00 | $187.00 |
| 2260 | PPC I-beam type HN 42-49 | LF A A | 1,434.70 | $851.00 | $797.00 |
| 2270 | Rail system single slope - 36 in | LF A A | 183 | $190.00 | $182.00 |
| 2280 | Rail system single slope - 40 in | LF A A | 183 | $190.00 | $189.00 |
| 2290 | Mobilization for concrete surf treatment | LS A A | 1 | $2,750.00 | $125.00 |
| 2300 | Flowable fill | CUYD A A | 75 | $270.00 | $375.00 |
| 2310 | Structure excav-solid rock | CUYD A A | 2.70 | $500.00 | $165.00 |
| 2320 | Foundation preparation | LS A A | 1 | $25,000 | $12,000 |
| 2330 | Concrete-class A | CUYD A A | 132.80 | $1,095.00 | $1,910.00 |
| 2340 | Steel reinforcement | LB A A | 14,564 | $2.05 | $1.90 |
| 2350 | Flowable fill | CUYD A A | 7.10 | $795.00 | $462.00 |
| 2360 | Structure excav-solid rock | CUYD A A | 72.50 | $155.00 | $140.00 |
| 2370 | Foundation preparation | LS A A | 1 | $35,000 | $25,000 |
| 2380 | Concrete-class A | CUYD A A | 497.70 | $840.00 | $860.00 |
| 2390 | Steel reinforcement | LB A A | 41,056 | $1.87 | $1.85 |
| 2400 | SBM alum sheet signs .080 in | SQFT A A | 536.60 | $42.10 | $37.00 |
| 2410 | SBM alum sheet signs .125 in | SQFT A A | 24 | $46.09 | $37.00 |
| 2420 | Steel post type 1 | LF A A | 1,002 | $26.43 | $24.00 |
| 2430 | Remove-store and reinstall sign | EACH A A | 8 | $170.89 | $500.00 |
| 2450 | GMSS type D | EACH A A | 9 | $456.98 | $450.00 |
| 2460 | Barcode sign inventory | EACH A A | 129 | $21.26 | $34.00 |
| 2470 | Trenching and backfilling | LF A A | 20 | $8.16 | $7.00 |
| 2480 | Cable-no. 14/5C | LF A A | 3,075 | $3.32 | $3.00 |
| 2490 | Cable-no. 14/7C | LF A A | 2,765 | $3.32 | $3.00 |
| 2500 | Messenger-10800 LB | LF A A | 1,225 | $10.20 | $10.50 |
| 2510 | Install steel strain pole | EACH A A | 8 | $11,224 | $11,500 |
| 2520 | Install pedestrian head-LED | EACH A A | 8 | $459.18 | $500.00 |
| 2530 | Install LED signal-3 section | EACH A A | 25 | $663.27 | $600.00 |
| 2540 | Install LED signal- 4 section | EACH A A | 7 | $867.35 | $825.00 |
| 2550 | Install ped detector-audible | EACH A A | 8 | $306.12 | $380.00 |
| 2560 | Span/pole-mounted sign | EACH A A | 5 | $306.12 | $375.00 |
| 2570 | Remove & reinstall coordinating unit | EACH A A | 2 | $2,551.02 | $2,500.00 |
| 2580 | Traffic signal pole base | CUYD A A | 36 | $663.27 | $620.00 |
| 2590 | Tether wire | LF A A | 1,225 | $10.20 | $8.00 |
| 2600 | PVC conduit-2 in-schedule 80 | LF A A | 80 | $10.20 | $9.00 |
| 2610 | Install signal controller-TY atc | EACH A A | 2 | $20,408 | $17,500 |
| 2620 | Remove signal equipment | EACH A A | 2 | $10,204 | $14,000 |
| 2630 | Install radar presence detector type A | EACH A A | 8 | $2,040.82 | $1,600.00 |
| 2640 | Install radar advance detector type B | EACH A A | 4 | $2,040.82 | $1,600.00 |
| 2650 | Pole 40 FT MTG HT | EACH A A | 42 | $3,571.43 | $3,800.00 |
| 2660 | Bracket 15 FT | EACH A A | 42 | $765.31 | $825.00 |
| 2670 | Pole base | EACH A A | 42 | $1,530.61 | $2,000.00 |
| 2680 | Transformer base | EACH A A | 42 | $1,530.61 | $1,100.00 |
| 2690 | Pole W/secondary control equip | EACH A A | 3 | $25,510 | $14,000 |
| 2700 | Fused connector kit | EACH A A | 84 | $229.59 | $250.00 |
| 2710 | Conduit-2 in | LF A A | 925 | $15.31 | $12.00 |
| 2720 | Trenching and backfilling | LF A A | 4,375 | $8.16 | $10.00 |
| 2730 | Open cut roadway | LF A A | 750 | $21.43 | $25.00 |
| 2740 | Wire-no. 12 | LF A A | 2,550 | $1.28 | $1.07 |
| 2750 | Electrical junction box type A | EACH A A | 14 | $2,040.82 | $3,000.00 |
| 2760 | Wire-no. 10 | LF A A | 19,000 | $3.06 | $2.85 |
| 2770 | LED luminaire | EACH A A | 42 | $663.27 | $1,000.00 |
| 2780 | PVC conduit-1 1/4 in-schedule 80 | LF A A | 4,435 | $8.16 | $7.00 |
| 2790 | PVC conduit-2 in-schedule 80 | LF A A | 120 | $10.20 | $8.50 |
| 2800 | Mobilization | LS A A | 1 | $1,300,000 | $1,600,000 |
| 2810 | Demobilization | LS A A | 1 | $397,210 | $540,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.