KYTC contract 26-1119 bid tabulation
ASPHALT SURFACE WITH GRADE & DRAIN LAFAYETTE ROAD(KY 107). Let by Kentucky Transportation Cabinet on May 21, 2026. 3 bids received; low bid $2,346,915 by Rame Contracting LLC, -15% against the engineer's estimate of $2,759,519.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 MAY 2026
- Pay items
- 88
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rame Contracting LLC | $2,346,915 | Low | -15% |
| 2 | Scotty'S Contracting & Stone LLC | $2,446,407 | +4.0% | -11% |
| 3 | Westate Construction Inc | $2,474,754 | +5.0% | -10% |
Engineer's estimate: $2,759,519.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rame Contracting LLC | 2. Scotty'S Contracting & Stone LLC | 3. Westate Construction Inc |
|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 4,414 | $43.00 | $37.92 | $39.00 |
| 0020 | Crushed aggregate size no 2 | TON A A | 7,732 | $42.00 | $39.94 | $42.00 |
| 0030 | Asphalt seal aggregate | TON A A | 37.80 | $138.62 | $149.71 | $138.62 |
| 0040 | Asphalt seal coat | TON A A | 4.50 | $1,137.04 | $1,137.04 | $1,137.04 |
| 0050 | Leveling & wedging PG64-22 | TON A A | 24 | $144.49 | $144.49 | $144.49 |
| 0060 | CL2 asph base 0.75D PG64-22 | TON A A | 2,173 | $98.76 | $98.76 | $98.76 |
| 0070 | CL2 asph surf 0.38D PG64-22 | TON A A | 742 | $129.42 | $129.42 | $129.42 |
| 0080 | Fabric-geotextile class 1 | SQYD A A | 7,664 | $2.50 | $3.21 | $2.70 |
| 0090 | Fabric-geotextile class 4A | SQYD A A | 7,664 | $3.75 | $2.19 | $4.75 |
| 0100 | Joint adhesive | LF A A | 3,452 | $2.50 | $1.50 | $1.50 |
| 0110 | Sawcut pavement | LF A A | 545 | $7.00 | $3.15 | $1.15 |
| 0120 | Longitudinal edge key | LF A A | 480 | $17.00 | $21.62 | $17.00 |
| 0130 | Asphalt material for tack non-tracking | TON A A | 5.60 | $1,145.00 | $1,145.00 | $1,145.00 |
| 0140 | Electronic delivery MGMT system - agg | LS A A | 1 | $350.00 | $0.01 | $1.00 |
| 0150 | Perforated pipe-4 in | LF A A | 490 | $50.00 | $25.64 | $12.75 |
| 0160 | Non-perforated pipe-4 in | LF A A | 48 | $50.00 | $29.11 | $25.75 |
| 0170 | Perf pipe headwall TY 3-4 in | EACH A A | 4 | $1,550.00 | $1,473.22 | $730.00 |
| 0180 | Remove pavement | SQYD A A | 23 | $55.00 | $21.62 | $13.50 |
| 0190 | Temp ditch | LF A A | 1,206 | $1.00 | $0.01 | $1.00 |
| 0200 | Clean temp ditch | LF A A | 603 | $1.00 | $0.01 | $0.01 |
| 0210 | Roadway excavation | CUYD A A | 11,228 | $18.50 | $31.84 | $26.50 |
| 0220 | Water | MGAL A A | 250 | $1.00 | $0.01 | $1.00 |
| 0230 | Right-of-way monument type 1 | EACH A A | 19 | $295.00 | $257.86 | $517.50 |
| 0240 | Witness post | EACH A A | 3 | $177.00 | $177.60 | $150.00 |
| 0250 | Channel lining class II | TON A A | 971 | $46.00 | $71.02 | $57.00 |
| 0260 | Channel lining class III | TON A A | 9 | $48.00 | $101.40 | $60.00 |
| 0270 | Clearing and grubbing | LS A A | 1 | $1,750.00 | $35,731 | $21,365 |
| 0280 | Temporary signs | SQFT A A | 287 | $10.00 | $7.00 | $9.54 |
| 0290 | Edge key | LF A A | 22 | $500.00 | $565.96 | $656.00 |
| 0300 | Fabric-geotextile class 2 for pipe | SQYD A A | 1,781 | $2.00 | $2.00 | $2.00 |
| 0310 | Maintain & control traffic | LS A A | 1 | $105,000 | $24,149 | $54,800 |
| 0320 | Portable changeable message sign | EACH A A | 2 | $2,600.00 | $5,127.75 | $4,452.00 |
| 0330 | Mobilization for mill & text | LS A A | 1 | $5,500.00 | $3,500.00 | $3,500.00 |
| 0340 | Edgeline rumble strips | LF A A | 4,215 | $1.05 | $1.15 | $1.05 |
| 0350 | Temp silt fence | LF A A | 1,206 | $3.00 | $3.06 | $3.60 |
| 0360 | Silt trap type A | EACH A A | 7 | $350.00 | $328.77 | $50.00 |
| 0370 | Silt trap type B | EACH A A | 7 | $350.00 | $324.90 | $50.00 |
| 0380 | Silt trap type C | EACH A A | 7 | $350.00 | $160.22 | $50.00 |
| 0390 | Clean silt trap type A | EACH A A | 7 | $25.00 | $84.68 | $25.00 |
| 0400 | Clean silt trap type B | EACH A A | 7 | $25.00 | $84.68 | $25.00 |
| 0410 | Clean silt trap type C | EACH A A | 7 | $25.00 | $75.11 | $25.00 |
| 0420 | Staking | LS A A | 1 | $14,400 | $26,453 | $104,700 |
| 0430 | Arrow panel | EACH A A | 2 | $1,250.00 | $1,948.55 | $25.00 |
| 0440 | Erosion control blanket | SQYD A A | 3,778 | $3.14 | $1.95 | $3.50 |
| 0450 | Temp mulch | SQYD A A | 20,005 | $0.28 | $0.20 | $0.10 |
| 0460 | Temp seeding and protection | SQYD A A | 15,004 | $0.52 | $0.30 | $0.10 |
| 0470 | Initial fertilizer | TON A A | 2.20 | $1,959.51 | $1,500.00 | $1,000.00 |
| 0480 | Maintenance fertilizer | TON A A | 1.10 | $2,052.83 | $1,500.00 | $1,000.00 |
| 0490 | Seeding and protection | SQYD A A | 20,812 | $0.81 | $0.42 | $1.10 |
| 0500 | Agricultural limestone | TON A A | 13 | $92.57 | $75.00 | $1,000.00 |
| 0502 | SBM alum sheet signs .080 in | SQFT A A | 15.25 | $67.81 | $67.81 | $48.50 |
| 0504 | SBM alum sheet signs .125 in | SQFT A A | 12.56 | $69.80 | $69.80 | $49.50 |
| 0506 | Steel post type 1 | LF A A | 58 | $45.46 | $45.46 | $38.50 |
| 0510 | Pave striping-perm paint-6 in | LF A A | 8,863 | $0.12 | $0.12 | $0.22 |
| 0520 | Pave marking-thermo stop bar-24IN | LF A A | 55 | $7.95 | $7.95 | $7.95 |
| 0530 | Pave marking-thermo curv arrow | EACH A A | 6 | $50.00 | $50.00 | $50.00 |
| 0540 | Fuel adjustment | DOLL A A | 4,247 | $1.00 | $1.00 | $1.00 |
| 0550 | Centerline rumble strips | LF A A | 2,034 | $1.45 | $1.55 | $1.45 |
| 0552 | Remove and relocate sheet signs | EACH A A | 4 | $457.04 | $457.04 | $100.00 |
| 0554 | Barcode sign inventory | EACH A A | 2 | $57.14 | $57.14 | $50.00 |
| 0560 | Pipeline inspection | LF A A | 359 | $9.00 | $6.96 | $9.49 |
| 0570 | Entrance pipe-18 in | LF A A | 288 | $77.00 | $116.58 | $77.50 |
| 0580 | Culvert pipe-24 in | LF A A | 161 | $115.00 | $228.63 | $100.00 |
| 0590 | Culvert pipe-30 in | LF A A | 54 | $132.00 | $278.25 | $202.00 |
| 0600 | S & F box inlet-outlet-24 in | EACH A A | 3 | $2,050.00 | $5,522.54 | $5,820.00 |
| 0610 | S & F box inlet-outlet-30 in | EACH A A | 2 | $2,600.00 | $8,833.86 | $6,650.00 |
| 0620 | Drop box inlet type 1 | EACH A A | 1 | $8,500.00 | $4,273.00 | $8,604.00 |
| 0630 | Safeloading | CUYD A A | 8 | $695.00 | $695.00 | $695.00 |
| 0640 | W air release valve 3/4 inch | EACH A A | 1 | $2,055.00 | $2,055.00 | $2,055.00 |
| 0650 | W cap existing main | EACH A A | 3 | $4,285.00 | $4,285.00 | $4,285.00 |
| 0660 | W encasement steel bored range 5 | LF A A | 85 | $861.00 | $861.00 | $861.00 |
| 0670 | W fire hydrant assembly | EACH A A | 2 | $12,955 | $12,955 | $12,955 |
| 0680 | W meter 1 inch | EACH A A | 1 | $3,460.00 | $3,460.00 | $3,460.00 |
| 0690 | W meter 2 inch | EACH A A | 1 | $9,080.00 | $9,080.00 | $9,080.00 |
| 0700 | W pipe ductile iron 12 inch | LF A A | 852 | $137.00 | $137.00 | $137.00 |
| 0710 | W pipe DCTL iron RSTRND joint 12 in | LF A A | 1,036 | $214.00 | $214.00 | $214.00 |
| 0720 | W serv PE/PLST long side 1 in | EACH A A | 1 | $6,045.00 | $6,045.00 | $6,045.00 |
| 0730 | W serv PE/PLST long side 2 in | EACH A A | 1 | $7,900.00 | $7,900.00 | $7,900.00 |
| 0740 | W serv PE/PLST long side 3/4 in | EACH A A | 6 | $7,085.00 | $7,085.00 | $7,085.00 |
| 0750 | W serv PE/PLST short side 3/4 in | EACH A A | 2 | $180.00 | $180.00 | $180.00 |
| 0760 | W tapping sleeve and valve size 2 | EACH A A | 3 | $17,250 | $17,250 | $17,250 |
| 0770 | W valve 12 inch | EACH A A | 3 | $7,515.00 | $7,515.00 | $7,515.00 |
| 0780 | W valve special | EACH A A | 3 | $19,975 | $19,975 | $19,975 |
| 0790 | W line marker | EACH A A | 4 | $115.00 | $115.00 | $115.00 |
| 0800 | W meter 5/8 inch | EACH A A | 7 | $3,015.00 | $3,015.00 | $3,015.00 |
| 0810 | Asphalt driveway/parking lot replacement | LF A A | 50 | $145.00 | $145.00 | $145.00 |
| 0820 | Mobilization | LS A A | 1 | $109,899 | $91,277 | $88,000 |
| 0830 | Demobilization | LS A A | 1 | $33,000 | $34,830 | $35,272 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of May 21, 2026. Compiled by Mirage Metrics.