KYTC contract 26-1501 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE TAYLOR RD. (KY 3504). Let by Kentucky Transportation Cabinet on January 29, 2026. 2 bids received; low bid $410,022 by Frederick & May Construction Co, +6.0% against the engineer's estimate of $386,956.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 29 JAN 2026
- Pay items
- 49
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $410,022 | Low | +6.0% |
| 2 | Keetech Constr Horizontal Directional Drilling & Utilities | $422,558 | +3.0% | +9.0% |
Engineer's estimate: $386,956.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Keetech Constr Horizontal Directional Drilling & Utilities |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 126 | $86.50 | $72.00 |
| 0020 | Traffic bound base | TON A A | 29 | $45.00 | $74.00 |
| 0030 | CL2 asph base 1.00D PG64-22 | TON A A | 181 | $225.50 | $490.00 |
| 0040 | CL2 asph surf 0.38D PG64-22 | TON A A | 124 | $233.50 | $490.00 |
| 0050 | Asphalt pave milling & texturing | TON A A | 118 | $100.00 | $220.00 |
| 0060 | Longitudinal edge key | LF A A | 230 | $28.75 | $25.00 |
| 0070 | Asphalt material for tack non-tracking | TON A A | 0.49 | $500.00 | $475.00 |
| 0080 | Remove pipe | LF A A | 62 | $30.00 | $28.00 |
| 0090 | Lip header curb | LF A A | 127 | $100.00 | $65.00 |
| 0100 | Barricade-type III | EACH A A | 2 | $125.00 | $200.00 |
| 0110 | Roadway excavation | CUYD A A | 282 | $50.00 | $40.00 |
| 0120 | Right-of-way monument type 1 | EACH A A | 5 | $389.34 | $200.00 |
| 0130 | Witness post | EACH A A | 3 | $336.37 | $200.00 |
| 0140 | Channel lining class II | TON A A | 92 | $60.00 | $82.00 |
| 0150 | Clearing and grubbing | LS A A | 1 | $49,060 | $10,000 |
| 0160 | Temporary signs | SQFT A A | 88 | $25.00 | $25.00 |
| 0170 | Maintain & control traffic | LS A A | 1 | $20,000 | $15,000 |
| 0180 | Mobilization for mill & text | LS A A | 1 | $5,000.00 | $7,500.00 |
| 0190 | Staking | LS A A | 1 | $7,500.00 | $14,000 |
| 0200 | Erosion control blanket | SQYD A A | 150 | $7.00 | $3.50 |
| 0210 | Pave striping-temp paint-4 in | LF A A | 2,670 | $1.50 | $1.80 |
| 0220 | Pave striping-perm paint-4 in | LF A A | 1,335 | $1.75 | $2.00 |
| 0230 | Pave marking-thermo stop bar-24IN | LF A A | 38 | $15.00 | $18.00 |
| 0240 | Pave marking-thermo cross-hatch | SQFT A A | 1,471 | $1.45 | $5.00 |
| 0245 | Joint adhesive | LF A A | 200 | $22.00 | $30.00 |
| 0250 | Erosion control | LS A A | 1 | $6,500.00 | $6,500.00 |
| 0260 | Pavement marking-thermo letters | EACH A A | 4 | $100.00 | $280.00 |
| 0270 | Cored hole drainage conn to headwall | EACH A A | 1 | $1,500.00 | $1,800.00 |
| 0280 | Barcode sign inventory | EACH A A | 2 | $78.09 | $40.00 |
| 0290 | Entrance pipe-15 in | LF A A | 18 | $70.00 | $64.00 |
| 0300 | Culvert pipe-12 in | LF A A | 12 | $100.00 | $58.00 |
| 0310 | Culvert pipe-24 in equiv | LF A A | 115 | $200.00 | $160.00 |
| 0320 | Metal end section TY 1-15 in | EACH A A | 2 | $2,500.00 | $1,200.00 |
| 0330 | S & F box inlet-outlet-24 in | EACH A A | 1 | $5,000.00 | $7,500.00 |
| 0340 | Junction box-special | EACH A A | 1 | $2,500.00 | $8,500.00 |
| 0350 | Safety box inlet-24 in DBL SDB-5 | EACH A A | 1 | $7,500.00 | $9,000.00 |
| 0360 | Fabric-geotextile class 2 for pipe | SQYD A A | 128 | $2.00 | $2.00 |
| 0370 | Concrete-class A | CUYD A A | 2 | $1,500.00 | $620.00 |
| 0380 | Temporary pipe | LF A A | 80 | $60.00 | $50.00 |
| 0390 | Frame and lid TY 2 | EACH A A | 1 | $1,000.00 | $2,200.00 |
| 0400 | Trench drain | LF A A | 50 | $650.00 | $38.00 |
| 0410 | SBM alum sheet signs .080 in | SQFT A A | 12.50 | $99.22 | $45.00 |
| 0420 | Steel post type 1 | LF A A | 20 | $78.94 | $60.00 |
| 0430 | W fire hydrant remove | EACH A A | 1 | $2,000.00 | $12,800 |
| 0440 | W pipe PVC 03 inch | LF A A | 250 | $170.00 | $65.00 |
| 0450 | W tie-in 03 inch | EACH A A | 3 | $6,000.00 | $3,000.00 |
| 0460 | W valve 03 inch | EACH A A | 3 | $2,200.00 | $3,200.00 |
| 0470 | W line marker | EACH A A | 2 | $100.00 | $118.00 |
| 0480 | Demobilization | LS A A | 1 | $6,060.00 | $12,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 29, 2026. Compiled by Mirage Metrics.