KYTC contract 26-1509 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE MUD CREEK ROAD (KY 979). Let by Kentucky Transportation Cabinet on May 21, 2026. 2 bids received; low bid $4,826,985 by Bush & Burchett Inc, -19% against the engineer's estimate of $5,979,950.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 MAY 2026
- Pay items
- 116
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bush & Burchett Inc | $4,826,985 | Low | -19% |
| 2 | Standafer Builders Inc | $4,930,208 | +2.0% | -18% |
Engineer's estimate: $5,979,950.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bush & Burchett Inc | 2. Standafer Builders Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 4,030 | $58.90 | $58.90 |
| 0020 | Traffic bound base | TON A A | 182 | $75.00 | $58.90 |
| 0030 | Asphalt seal aggregate | TON A A | 107 | $225.00 | $225.00 |
| 0040 | Asphalt seal coat | TON A A | 32 | $890.00 | $890.00 |
| 0050 | CL2 asph base 1.00D PG64-22 | TON A A | 3,995 | $162.10 | $162.10 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A A | 1,070 | $189.60 | $189.60 |
| 0070 | JPC pavement-8 in | SQYD A A | 475 | $150.00 | $136.11 |
| 0080 | Fabric-geotextile class 1 | SQYD A A | 12,056 | $1.85 | $1.85 |
| 0090 | Fabric-geotextile class 4A | SQYD A A | 13,433 | $3.00 | $3.75 |
| 0100 | Joint adhesive | LF A A | 9,300 | $0.95 | $0.95 |
| 0110 | Asphalt material for tack non-tracking | TON A A | 8 | $860.00 | $860.00 |
| 0120 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,500.00 | $1,500.00 |
| 0130 | Crushed aggregate size no 2 | TON A A | 706 | $69.00 | $42.00 |
| 0140 | Perforated pipe-4 in | LF A A | 530 | $9.00 | $15.00 |
| 0150 | Non-perforated pipe-4 in | LF A A | 109 | $10.00 | $15.00 |
| 0160 | Perf pipe headwall TY 2-4 in | EACH A A | 1 | $1,100.00 | $1,200.00 |
| 0170 | Perf pipe headwall TY 3-4 in | EACH A A | 5 | $1,350.00 | $1,200.00 |
| 0180 | Cored hole drainage box con-4 in | EACH A A | 2 | $600.00 | $350.00 |
| 0190 | Island header curb type 1 | LF A A | 972 | $100.00 | $41.21 |
| 0200 | Delineator for G/R BI directional white | EACH A A | 7 | $13.00 | $15.42 |
| 0210 | Relocate temp conc barrier | LF A A | 640 | $44.00 | $5.00 |
| 0220 | Barricade-type III | EACH A A | 4 | $200.00 | $200.00 |
| 0230 | Temp ditch | LF A A | 1,550 | $1.65 | $1.00 |
| 0240 | Clean temp ditch | LF A A | 775 | $2.25 | $0.10 |
| 0245 | Structure demolition | EACH A A | 1 | $6,800.00 | $3,500.00 |
| 0250 | Roadway excavation | CUYD A A | 48,269 | $14.00 | $20.00 |
| 0260 | Structure excav-unclassified | CUYD A A | 215 | $13.00 | $25.00 |
| 0270 | Granular embankment | CUYD A A | 6,094 | $50.00 | $50.00 |
| 0280 | Water | MGAL A A | 117 | $1.00 | $1.00 |
| 0290 | G/R terminal section no 1 | EACH A A | 8 | $65.00 | $93.25 |
| 0300 | G/R end treatment type 7 | EACH A A | 2 | $1,700.00 | $2,133.58 |
| 0310 | Remove G/R | LF A A | 1,077 | $3.85 | $3.20 |
| 0320 | Temp G/R | LF A A | 612.50 | $18.75 | $20.79 |
| 0330 | Right-of-way monument type 1 | EACH A A | 61 | $300.00 | $191.43 |
| 0340 | Right-of-way monument type 1A | EACH A A | 3 | $300.00 | $173.55 |
| 0350 | Witness R/W monument type 2 | EACH A A | 3 | $200.00 | $178.92 |
| 0360 | Witness post | EACH A A | 3 | $200.00 | $155.67 |
| 0370 | Channel lining class II | TON A A | 115 | $70.00 | $45.00 |
| 0380 | Channel lining class III | TON A A | 83 | $71.00 | $50.00 |
| 0390 | Clearing and grubbing | LS A A | 1 | $46,500 | $125,000 |
| 0400 | Concrete-class B | CUYD A A | 100 | $2,000.00 | $745.00 |
| 0410 | Temporary signs | SQFT A A | 500 | $15.00 | $40.00 |
| 0420 | Edge key | LF A A | 68 | $53.50 | $53.50 |
| 0430 | Fabric-geotextile class 2 | SQYD A A | 66 | $6.50 | $2.00 |
| 0440 | Fabric-geotextile class 2 for pipe | SQYD A A | 1,997 | $2.00 | $2.00 |
| 0450 | Maintain & control traffic | LS A A | 1 | $100,000 | $185,000 |
| 0460 | Diversions (by-pass detours) | LS A A | 1 | $14,000 | $8,500.00 |
| 0470 | Lane closure | EACH A A | 2 | $1,000.00 | $3,200.00 |
| 0480 | Portable changeable message sign | EACH A A | 2 | $9,000.00 | $11,000 |
| 0490 | Safeloading | CUYD A A | 4 | $230.00 | $350.00 |
| 0500 | Edgeline rumble strips | LF A A | 5,705 | $1.10 | $0.35 |
| 0510 | Temp silt fence | LF A A | 1,550 | $3.00 | $3.55 |
| 0520 | Silt trap type A | EACH A A | 16 | $250.00 | $45.00 |
| 0530 | Silt trap type B | EACH A A | 16 | $250.00 | $45.00 |
| 0540 | Silt trap type C | EACH A A | 16 | $250.00 | $45.00 |
| 0550 | Clean silt trap type A | EACH A A | 16 | $240.00 | $10.00 |
| 0560 | Clean silt trap type B | EACH A A | 16 | $240.00 | $10.00 |
| 0570 | Clean silt trap type C | EACH A A | 16 | $240.00 | $10.00 |
| 0580 | Staking | LS A A | 1 | $35,400 | $36,000 |
| 0590 | Remove structure | LS A A | 1 | $200,000 | $1,800.00 |
| 0600 | Conc barrier wall type 9T | LF A A | 640 | $100.00 | $80.00 |
| 0610 | Temp signal 2 phase | EACH A A | 2 | $5,000.00 | $24,000 |
| 0620 | Erosion control blanket | SQYD A A | 3,292 | $2.55 | $2.66 |
| 0630 | Temp mulch | SQYD A A | 49,713 | $0.25 | $0.40 |
| 0640 | Temp seeding and protection | SQYD A A | 37,285 | $0.27 | $0.42 |
| 0650 | Initial fertilizer | TON A A | 1.80 | $1,700.00 | $1,791.72 |
| 0660 | Maintenance fertilizer | TON A A | 3 | $1,700.00 | $1,791.72 |
| 0670 | Seeding and protection | SQYD A A | 54,887 | $0.57 | $0.77 |
| 0680 | Agricultural limestone | TON A A | 34 | $125.00 | $82.31 |
| 0690 | Pave striping-temp paint-4 in | LF A A | 3,700 | $0.18 | $0.18 |
| 0700 | Pave striping-perm paint-4 in | LF A A | 490 | $0.22 | $0.22 |
| 0710 | Pave striping-perm paint-6 in | LF A A | 14,376 | $0.25 | $0.25 |
| 0720 | Pave marking-thermo stop bar-24IN | LF A A | 36 | $12.00 | $12.00 |
| 0730 | Pave marking-thermo curv arrow | EACH A A | 8 | $125.00 | $125.00 |
| 0740 | Pave marking-thermo only | EACH A A | 1 | $300.00 | $300.00 |
| 0750 | Crash cushion TY 6 class T TL2 | EACH A A | 2 | $15,000 | $5,598.26 |
| 0760 | Fuel adjustment | DOLL A A | 20,939 | $1.00 | $1.00 |
| 0770 | Asphalt adjustment | DOLL A A | 21,284 | $1.00 | $1.00 |
| 0780 | Pave mark temp paint stop bar | LF A A | 23 | $10.00 | $10.00 |
| 0790 | G/R steel W beam-S face (7 FT post) | LF A A | 812.50 | $33.50 | $33.80 |
| 0800 | Water blasting existing stripe | LF A A | 1,000 | $2.50 | $2.50 |
| 0810 | Turf reinforcement mat 1 | SQYD A A | 1,094 | $9.00 | $11.29 |
| 0820 | Pave striping-chevron markings | SQFT A A | 644 | $6.50 | $6.50 |
| 0830 | Entrance pipe-18 in | LF A A | 36 | $86.00 | $32.00 |
| 0840 | Entrance pipe-24 in | LF A A | 60 | $94.00 | $44.00 |
| 0850 | Entrance pipe-15 in equiv | LF A A | 134 | $82.00 | $37.00 |
| 0860 | Culvert pipe-36 in | LF A A | 170 | $161.00 | $200.00 |
| 0870 | Storm sewer pipe-15 in | LF A A | 272 | $103.00 | $33.00 |
| 0880 | Storm sewer pipe-18 in | LF A A | 60 | $110.00 | $37.00 |
| 0890 | Storm sewer pipe-24 in equiv | LF A A | 157 | $118.00 | $48.00 |
| 0900 | Storm sewer pipe-30 in equiv | LF A A | 174 | $136.00 | $68.00 |
| 0910 | Pipe culvert headwall-30 in equiv | EACH A A | 1 | $5,000.00 | $200.00 |
| 0920 | Pipe culvert headwall-36 in | EACH A A | 2 | $3,800.00 | $6,500.00 |
| 0930 | S & F box inlet-outlet-36 in | EACH A A | 2 | $4,900.00 | $6,500.00 |
| 0940 | Drop box inlet type 3 | EACH A A | 1 | $2,900.00 | $3,000.00 |
| 0950 | Drop box inlet type 6D | EACH A A | 7 | $2,800.00 | $4,000.00 |
| 0960 | Drop box inlet type 7 | EACH A A | 1 | $6,800.00 | $2,700.00 |
| 0970 | Drainage junction box TY B | EACH A A | 1 | $3,560.00 | $1,700.00 |
| 0980 | Pipeline inspection | LF A A | 561 | $8.00 | $4.46 |
| 0990 | Foundation preparation | LS A A | 1 | $235,000 | $15,000 |
| 1000 | Concrete-class A | CUYD A A | 125.90 | $2,000.00 | $1,492.00 |
| 1010 | Steel reinforcement | LB A A | 17,681 | $3.00 | $2.00 |
| 1020 | Low flow diversion curb | LS A A | 1 | $20,000 | $5,500.00 |
| 1030 | W encasement steel bored range 2 | LF A A | 110 | $142.00 | $520.00 |
| 1040 | W encasement steel bored range 4 | LF A A | 115 | $163.00 | $560.00 |
| 1050 | W flush hydrant assembly | EACH A A | 5 | $850.00 | $16,500 |
| 1060 | W pipe ductile iron 04 inch | LF A A | 329 | $46.00 | $82.00 |
| 1070 | W pipe ductile iron 08 inch | LF A A | 1,465 | $64.00 | $85.00 |
| 1080 | W pipe PVC 04 inch | LF A A | 500 | $48.00 | $68.00 |
| 1090 | W pipe PVC 08 inch | LF A A | 2,600 | $42.00 | $78.00 |
| 1100 | W serv PE/PLST long side 3/4 in | EACH A A | 25 | $610.00 | $3,200.00 |
| 1110 | W tie-in 08 inch | EACH A A | 3 | $2,310.00 | $6,800.00 |
| 1120 | W valve 04 inch | EACH A A | 4 | $1,880.00 | $2,400.00 |
| 1130 | W valve 08 inch | EACH A A | 11 | $1,820.00 | $4,400.00 |
| 1140 | Mobilization | LS A A | 1 | $200,000 | $200,000 |
| 1150 | Demobilization | LS A A | 1 | $72,000 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of May 21, 2026. Compiled by Mirage Metrics.