KYTC contract 26-1514 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE HIGHWAY 15 (KY 15). Let by Kentucky Transportation Cabinet on May 21, 2026. 2 bids received; low bid $43,489,000 by Triton Construction Inc, -0.7% against the engineer's estimate of $43,785,138.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 MAY 2026
- Pay items
- 109
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Triton Construction Inc | $43,489,000 | Low | -1.0% |
| 2 | Bizzack Construction LLC | $46,918,218 | +8.0% | +7.0% |
Engineer's estimate: $43,785,138.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Triton Construction Inc | 2. Bizzack Construction LLC |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 22,692 | $49.95 | $49.95 |
| 0020 | Asphalt seal aggregate | TON A A | 101 | $136.75 | $136.75 |
| 0030 | Asphalt seal coat | TON A A | 12 | $965.00 | $965.00 |
| 0040 | Leveling & wedging PG64-22 | TON A A | 903 | $180.45 | $180.45 |
| 0050 | CL2 asph base 1.00D PG64-22 | TON A A | 4,063 | $162.15 | $162.15 |
| 0060 | CL3 asph base 1.00D PG64-22 | TON A A | 8,212 | $164.45 | $164.45 |
| 0070 | CL2 asph surf 0.38D PG64-22 | TON A A | 1,073 | $180.45 | $180.45 |
| 0080 | CL3 asph surf 0.38D PG64-22 | TON A A | 1,864 | $180.45 | $180.45 |
| 0090 | Asphalt pave milling & texturing | TON A A | 514 | $43.85 | $43.85 |
| 0100 | Joint adhesive | LF A A | 18,065 | $0.60 | $0.60 |
| 0110 | Asphalt material for tack non-tracking | TON A A | 20 | $775.00 | $775.00 |
| 0120 | Crushed aggregate size no 2 | TON A A | 1 | $110.00 | $90.00 |
| 0130 | Perforated pipe-4 in | LF A A | 513 | $10.00 | $24.88 |
| 0140 | Non-perforated pipe-4 in | LF A A | 7 | $60.00 | $26.74 |
| 0150 | Inspect & certify edge drain system | LS A A | 1 | $2,500.00 | $2,500.00 |
| 0160 | Perf pipe headwall TY 1-4 in | EACH A A | 1 | $805.00 | $1,000.00 |
| 0170 | Delineator for barrier - white | EACH A A | 81 | $16.67 | $14.32 |
| 0180 | Delineator for G/R BI directional white | EACH A A | 28 | $14.24 | $13.00 |
| 0190 | Relocate temp conc barrier | LF A A | 4,120 | $8.50 | $9.06 |
| 0200 | Remove pavement | SQYD A A | 642 | $16.00 | $7.12 |
| 0210 | Temp ditch | LF A A | 2,800 | $2.65 | $1.75 |
| 0220 | Clean temp ditch | LF A A | 1,400 | $2.40 | $0.01 |
| 0230 | Roadway excavation | CUYD A A | 3,053,981 | $10.00 | $11.40 |
| 0240 | Granular embankment | CUYD A A | 6,157 | $18.00 | $70.51 |
| 0250 | Water | MGAL A A | 200 | $69.00 | $10.00 |
| 0260 | Fence-4 FT chain link | LF A A | 180 | $36.83 | $36.83 |
| 0270 | Double vehicular chain link gate | EACH A A | 1 | $6,868.90 | $6,868.90 |
| 0280 | G/R-W beam-S face TL-3 | LF A A | 1,687.50 | $31.89 | $29.00 |
| 0290 | G/R end treatment type 1 | EACH A A | 5 | $3,397.56 | $3,900.00 |
| 0300 | Remove G/R | LF A A | 1,285 | $3.06 | $4.00 |
| 0310 | Remove & reset G/R | LF A A | 2,973 | $24.93 | $18.00 |
| 0320 | Temp G/R | LF A A | 100 | $17.92 | $20.00 |
| 0330 | Right-of-way monument type 1 | EACH A A | 54 | $325.00 | $147.48 |
| 0340 | Witness post | EACH A A | 54 | $325.00 | $131.33 |
| 0350 | Channel lining class IV | CUYD A A | 818 | $65.00 | $24.98 |
| 0360 | Clearing and grubbing | LS A A | 1 | $1,250,000 | $550,000 |
| 0370 | Concrete-class B | CUYD A A | 2.25 | $2,200.00 | $1,652.44 |
| 0380 | Temporary signs | SQFT A A | 650 | $21.00 | $16.96 |
| 0390 | Edge key | LF A A | 159 | $42.65 | $42.65 |
| 0400 | Fabric-geotextile class 1 | SQYD A A | 10,030 | $4.02 | $3.12 |
| 0410 | Fabric-geotextile class 2 for pipe | SQYD A A | 1,072 | $2.00 | $2.00 |
| 0420 | Fabric-geotextile class 4A | SQYD A A | 64,082 | $4.75 | $3.33 |
| 0430 | Maintain & control traffic | LS A A | 1 | $354,074 | $600,000 |
| 0440 | Portable changeable message sign | EACH A A | 2 | $18,000 | $14,000 |
| 0450 | Mobilization for mill & text | LS A A | 1 | $10,800 | $10,800 |
| 0460 | Safeloading | CUYD A A | 20.10 | $700.00 | $540.00 |
| 0470 | Shoulder rumble strips | LF A A | 9,830 | $0.25 | $0.26 |
| 0480 | Temp silt fence | LF A A | 2,800 | $4.00 | $3.28 |
| 0490 | Silt trap type A | EACH A A | 152 | $360.00 | $85.00 |
| 0500 | Silt trap type B | EACH A A | 152 | $140.00 | $150.00 |
| 0510 | Silt trap type C | EACH A A | 152 | $200.00 | $180.00 |
| 0520 | Clean silt trap type A | EACH A A | 152 | $360.00 | $0.01 |
| 0530 | Clean silt trap type B | EACH A A | 152 | $140.00 | $0.01 |
| 0540 | Clean silt trap type C | EACH A A | 152 | $200.00 | $0.01 |
| 0550 | Staking | LS A A | 1 | $350,000 | $450,000 |
| 0560 | Conc barrier wall type 9T | LF A A | 1,177 | $45.00 | $30.00 |
| 0570 | Erosion control blanket | SQYD A A | 67,768 | $1.85 | $1.96 |
| 0580 | Temp mulch | SQYD A A | 488,000 | $0.30 | $0.36 |
| 0590 | Temp seeding and protection | SQYD A A | 366,000 | $0.43 | $0.38 |
| 0600 | Initial fertilizer | TON A A | 76 | $1,400.00 | $1,588.60 |
| 0610 | Maintenance fertilizer | TON A A | 38 | $1,400.00 | $1,588.60 |
| 0620 | Seeding and protection | SQYD A A | 665,700 | $0.65 | $0.67 |
| 0630 | Agricultural limestone | TON A A | 454 | $110.00 | $77.78 |
| 0640 | SBM alum sheet signs .080 in | SQFT A A | 163 | $41.31 | $41.31 |
| 0650 | SBM alum sheet signs .125 in | SQFT A A | 162 | $42.93 | $42.93 |
| 0660 | Steel post type 1 | LF A A | 669 | $22.12 | $22.12 |
| 0670 | Steel post mile markers | EACH A A | 1 | $335.37 | $335.37 |
| 0680 | Pave striping-temp paint-4 in | LF A A | 4,640 | $0.18 | $0.14 |
| 0690 | Pave striping-temp paint-6 in | LF A A | 43,200 | $0.22 | $0.20 |
| 0700 | Pave striping-perm paint-4 in | LF A A | 2,821 | $0.30 | $0.24 |
| 0710 | Pave striping removal-4 in | LF A A | 710 | $0.55 | $0.65 |
| 0720 | Pave striping removal-6 in | LF A A | 11,620 | $0.55 | $0.65 |
| 0730 | Pave striping-thermo-6 in W | LF A A | 11,450 | $1.12 | $1.00 |
| 0740 | Pave striping-thermo-6 in Y | LF A A | 11,760 | $1.12 | $1.00 |
| 0750 | Pave marking-thermo stop bar-24IN | LF A A | 42 | $15.00 | $12.00 |
| 0760 | Pave marking-thermo curv arrow | EACH A A | 12 | $110.00 | $120.00 |
| 0770 | Pavement marker TY iva-by temp | EACH A A | 2,160 | $8.00 | $5.00 |
| 0780 | Inlaid pavement marker-MW | EACH A A | 144 | $28.00 | $35.00 |
| 0790 | Inlaid pavement marker-by | EACH A A | 75 | $28.00 | $35.00 |
| 0800 | Concrete-class A | CUYD A A | 12.62 | $2,500.00 | $1,100.00 |
| 0810 | Crash cushion TY 6 class T TL3 | EACH A A | 2 | $5,161.20 | $3,900.00 |
| 0820 | Fuel adjustment | DOLL A A | 560,772 | $1.00 | $1.00 |
| 0830 | Asphalt adjustment | DOLL A A | 59,473 | $1.00 | $1.00 |
| 0840 | Tree | EACH A A | 111 | $357.55 | $357.55 |
| 0850 | Object marker TY 3 | EACH A A | 5 | $27.98 | $27.98 |
| 0860 | Saw cut | LF A A | 4,765 | $3.00 | $2.25 |
| 0870 | Centerline rumble strips | LF A A | 5,216 | $0.32 | $0.35 |
| 0880 | Longitudinal edge key | LF A A | 2,272 | $6.45 | $6.45 |
| 0890 | Pave mark temp paint stop bar-24 in | LF A A | 59 | $15.00 | $8.00 |
| 0900 | Turf reinforcement mat 1 | SQYD A A | 2,460 | $5.00 | $12.63 |
| 0910 | Remove and reset crash cushion | EACH A A | 2 | $3,302.97 | $2,500.00 |
| 0920 | Barcode sign inventory | EACH A A | 46 | $18.69 | $18.69 |
| 0930 | Pipeline inspection | LF A A | 793 | $4.00 | $3.16 |
| 0940 | PGR grout | CUYD A A | 6 | $1,200.00 | $600.00 |
| 0950 | Electronic delivery MGMT system - agg | LS A A | 1 | $2,300.00 | $1,725.00 |
| 0955 | Temporary rock catchment fence | LF A A | 5,360 | $152.00 | $166.67 |
| 0960 | Culvert pipe-18 in | LF A A | 81 | $250.00 | $137.27 |
| 0970 | Culvert pipe-24 in | LF A A | 172 | $290.00 | $218.71 |
| 0980 | Culvert pipe-30 in | LF A A | 86 | $310.00 | $198.63 |
| 0990 | Culvert pipe-36 in | LF A A | 210 | $375.00 | $292.23 |
| 1000 | Pipe culvert headwall-18 in | EACH A A | 2 | $2,500.00 | $1,700.00 |
| 1010 | Pipe culvert headwall-24 in | EACH A A | 6 | $2,600.00 | $1,850.00 |
| 1020 | Pipe culvert headwall-30 in | EACH A A | 2 | $3,400.00 | $2,550.00 |
| 1030 | Pipe culvert headwall-36 in | EACH A A | 4 | $3,800.00 | $2,900.00 |
| 1040 | Bore and jack pipe-24 in | LF A A | 118 | $968.00 | $595.60 |
| 1050 | Bore and jack pipe-30 in | LF A A | 82 | $1,135.00 | $734.72 |
| 1060 | Bore and jack pipe-36 in | LF A A | 98 | $1,380.00 | $899.70 |
| 1070 | Mobilization | LS A A | 1 | $2,000,000 | $1,600,000 |
| 1080 | Demobilization | LS A A | 1 | $618,000 | $660,600 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of May 21, 2026. Compiled by Mirage Metrics.