KYTC contract 26-1517 bid tabulation
ASPHALT SURFACE WITH GRADE & DRAIN US HIGHWAY 25. Let by Kentucky Transportation Cabinet on August 20, 2026. 2 bids received; low bid $68,397,741 by L-M Asphalt Partners LTD D/B/A Ats Construction, -2.0% against the engineer's estimate of $69,781,388.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 AUG 2026
- Pay items
- 371
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $68,397,741 | Low | -2.0% |
| 2 | Louisville Paving Company Inc | $76,023,112 | +11% | +9.0% |
Engineer's estimate: $69,781,388.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. L-M Asphalt Partners LTD D/B/A Ats Construction | 2. Louisville Paving Company Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 75,788 | $36.75 | $45.44 |
| 0020 | Traffic bound base | TON A A | 760 | $45.00 | $55.81 |
| 0030 | Crushed aggregate size no 57 | TON A A | 3,484 | $47.38 | $125.00 |
| 0040 | Crushed aggregate size no 2 | TON A A | 89,775 | $38.70 | $31.19 |
| 0050 | Asphalt seal aggregate | TON A A | 67 | $250.00 | $217.21 |
| 0060 | Asphalt seal coat | TON A A | 8 | $2,100.00 | $1,450.00 |
| 0070 | Leveling & wedging PG76-22 | TON A A | 8,273 | $130.00 | $115.00 |
| 0080 | CL3 asph base 1.00D PG64-22 | TON A A | 327 | $115.00 | $110.00 |
| 0090 | CL3 asph base 1.00D PG76-22 | TON A A | 6,759 | $115.00 | $110.00 |
| 0100 | CL4 asph base 1.00D PG64-22 | TON A A | 478 | $115.00 | $90.00 |
| 0110 | CL4 asph base 1.00D PG76-22 | TON A A | 18,915 | $110.00 | $90.00 |
| 0120 | CL2 asph base 0.75D PG64-22 | TON A A | 2,253 | $120.00 | $120.00 |
| 0130 | CL3 asph base 0.75D PG64-22 | TON A A | 3,279 | $120.00 | $145.00 |
| 0140 | CL3 asph base 0.75D PG76-22 | TON A A | 3,250 | $124.00 | $120.00 |
| 0150 | Asphalt prime coat | TON A A | 106 | $1,000.00 | $975.00 |
| 0160 | CL2 asph surf 0.38D PG64-22 | TON A A | 1,353 | $150.00 | $130.00 |
| 0170 | CL3 asph surf 0.38D PG64-22 | TON A A | 36 | $150.00 | $125.00 |
| 0180 | CL4 asph surf 0.38A PG76-22 | TON A A | 8,839 | $150.00 | $120.00 |
| 0190 | Asphalt material for tack | TON A A | 161 | $0.01 | $0.01 |
| 0200 | CL3 asph surf 0.38B PG76-22 | TON A A | 2,070 | $140.00 | $105.00 |
| 0210 | CL3 asph surf 0.38D PG76-22 | TON A A | 3,320 | $130.00 | $120.00 |
| 0220 | Cem conc ent pavement-8 in | SQYD A A | 6,278 | $118.76 | $118.76 |
| 0230 | Rubblize pavement | SQYD A A | 12,750 | $2.71 | $3.35 |
| 0240 | Reshaping and compacting | LF A A | 4,677 | $0.01 | $10.28 |
| 0250 | Fabric-geotextile class 1 | SQYD A A | 130,111 | $2.00 | $1.40 |
| 0260 | Fabric-geotextile class 2 | SQYD A A | 18,790 | $2.20 | $1.18 |
| 0270 | Fabric-geotextile class 4A | SQYD A A | 130,111 | $2.50 | $2.71 |
| 0280 | Mobilization for mill & text | LS A A | 1 | $3,000.00 | $8,500.00 |
| 0290 | Asphalt pave milling & texturing | TON A A | 1,637 | $28.00 | $33.21 |
| 0300 | Concrete-class A | CUYD A A | 120 | $516.48 | $516.48 |
| 0310 | Joint adhesive | LF A A | 74,310 | $0.39 | $1.00 |
| 0320 | CL4 asph surf 0.38D PG64-22 | TON A A | 251 | $165.00 | $110.00 |
| 0330 | Fiber reinforcement for HMA | TON A A | 30,493 | $11.07 | $7.00 |
| 0340 | CL3 asph base CK PG64-22 | TON A A | 7,731 | $105.00 | $110.00 |
| 0350 | CL4 asph base CK PG64-22 | TON A A | 22,763 | $105.00 | $110.00 |
| 0360 | Crushed aggregate size no 23 | TON A A | 18,792 | $38.68 | $50.00 |
| 0370 | Inspect & certify edge drain system | LS A A | 1 | $15,000 | $15,000 |
| 0380 | Remove pipe | LF A A | 128 | $0.13 | $2,324.48 |
| 0390 | Standard curb and gutter | LF A A | 8,485 | $36.59 | $36.59 |
| 0400 | Standard curb and gutter mod | LF A A | 31,034 | $39.30 | $39.30 |
| 0410 | Remove curb and gutter | LF A A | 830 | $12.05 | $17.06 |
| 0420 | Standard header curb | LF A A | 2,831 | $55.00 | $55.00 |
| 0430 | Standard barrier median type 5 | SQYD A A | 23,885 | $163.59 | $166.56 |
| 0440 | Conc terminal section type 1 | EACH A A | 1 | $9,234.65 | $9,234.65 |
| 0450 | Delineator for G/R BI directional white | EACH A A | 9 | $11.25 | $11.25 |
| 0460 | Curb to barrier wall trans | EACH A A | 8 | $8,076.76 | $8,076.76 |
| 0470 | Barricade-type III | EACH A A | 66 | $0.01 | $125.00 |
| 0480 | Cement concrete island | SQYD A A | 335 | $173.68 | $173.68 |
| 0490 | Remove concrete island | SQYD A A | 733 | $12.66 | $31.75 |
| 0500 | Remove pavement | SQYD A A | 4,384 | $7.89 | $36.84 |
| 0510 | Paved ditch type 1 | SQYD A A | 226 | $208.25 | $208.25 |
| 0520 | Temp ditch | LF A A | 11,629 | $0.01 | $3.57 |
| 0530 | Clean temp ditch | LF A A | 5,815 | $0.01 | $2.05 |
| 0540 | Roadway excavation | CUYD A A | 174,016 | $35.00 | $45.00 |
| 0550 | Water | MGAL A A | 872 | $0.01 | $35.53 |
| 0560 | Fence-woven wire type 1 | LF A A | 1,192 | $7.69 | $7.69 |
| 0570 | Single vehicular woven wire gate | EACH A A | 1 | $3,331.44 | $3,331.44 |
| 0580 | G/R-W beam-S face TL-3 | LF A A | 825 | $35.44 | $35.44 |
| 0590 | G/R terminal section no 1 | EACH A A | 10 | $74.07 | $74.07 |
| 0600 | G/R end treatment type 1 | EACH A A | 1 | $3,226.71 | $3,226.71 |
| 0610 | Remove G/R | LF A A | 764 | $2.08 | $2.08 |
| 0620 | G/R end treatment type 4A | EACH A A | 3 | $3,503.88 | $3,503.88 |
| 0630 | Remove concrete masonry | CUYD A A | 4.30 | $0.01 | $526.87 |
| 0640 | Right-of-way monument type 1 | EACH A A | 295 | $113.42 | $147.93 |
| 0650 | Witness post | EACH A A | 12 | $209.04 | $129.90 |
| 0660 | Channel lining class II | TON A A | 726 | $56.00 | $69.06 |
| 0670 | Channel lining class III | TON A A | 595 | $56.00 | $70.64 |
| 0680 | Clearing and grubbing | LS A A | 1 | $250,000 | $1,941,565 |
| 0690 | Concrete-class B | CUYD A A | 3.42 | $1,082.78 | $1,082.78 |
| 0700 | Temporary signs | SQFT A A | 1,450 | $14.84 | $6.00 |
| 0710 | Edge key | LF A A | 1,858 | $28.00 | $14.72 |
| 0720 | Fabric-geotextile class 2 | SQYD A A | 85,538 | $2.00 | $2.02 |
| 0730 | Fabric-geotextile class 2 for pipe | SQYD A A | 44,702 | $2.00 | $2.00 |
| 0740 | Handrail-type A-1 | LF A A | 239 | $117.00 | $105.00 |
| 0750 | Maintain & control traffic | LS A A | 1 | $1,500,000 | $4,300,000 |
| 0760 | Truck mounted attenuator | EACH A A | 4 | $5,000.00 | $10,000 |
| 0770 | Portable changeable message sign | EACH A A | 10 | $15,000 | $17,808 |
| 0780 | Safeloading | CUYD A A | 60.70 | $269.51 | $229.72 |
| 0790 | Edgeline rumble strips | LF A A | 1,400 | $2.15 | $2.15 |
| 0800 | Temp silt fence | LF A A | 11,629 | $3.17 | $1.96 |
| 0810 | Silt trap type A | EACH A A | 103 | $350.00 | $155.81 |
| 0820 | Silt trap type B | EACH A A | 103 | $100.00 | $268.54 |
| 0830 | Silt trap type C | EACH A A | 103 | $100.00 | $596.78 |
| 0840 | Clean silt trap type A | EACH A A | 103 | $50.00 | $158.92 |
| 0850 | Clean silt trap type B | EACH A A | 103 | $50.00 | $158.92 |
| 0860 | Clean silt trap type C | EACH A A | 103 | $50.00 | $158.92 |
| 0870 | Sidewalk-4 in concrete | SQYD A A | 17,599 | $68.68 | $68.68 |
| 0880 | Remove concrete sidewalk | SQYD A A | 290 | $15.00 | $68.99 |
| 0890 | Staking | LS A A | 1 | $125,000 | $262,118 |
| 0900 | Remove structure | LS A A | 1 | $23,500 | $40,000 |
| 0910 | Remove structure | LS A A | 1 | $13,301 | $4,149.20 |
| 0920 | Remove structure | LS A A | 1 | $10,690 | $2,755.53 |
| 0930 | Remove structure | LS A A | 1 | $29,400 | $12,261 |
| 0940 | Arrow panel | EACH A A | 6 | $0.01 | $14,400 |
| 0950 | Install temp crash cushion | EACH A A | 2 | $4,898.06 | $4,898.06 |
| 0960 | Conc barrier wall type 9T | LF A A | 598 | $80.00 | $70.03 |
| 0970 | Conduit-1 1/4 in | LF A A | 80 | $8.17 | $8.17 |
| 0980 | Conduit-2 in | LF A A | 40 | $11.26 | $11.26 |
| 0990 | Trenching and backfilling | LF A A | 110 | $15.00 | $15.00 |
| 1000 | Piezoelectric sensor | EACH A A | 4 | $2,500.00 | $2,500.00 |
| 1010 | Loop wire | LF A A | 1,800 | $0.31 | $0.31 |
| 1020 | Loop saw slot and fill | LF A A | 400 | $10.00 | $10.00 |
| 1030 | Temp relocation of signal head | EACH A A | 58 | $200.00 | $200.00 |
| 1040 | Erosion control blanket | SQYD A A | 16,072 | $1.88 | $1.74 |
| 1050 | Temp mulch | SQYD A A | 333,072 | $0.34 | $0.26 |
| 1060 | Temp seeding and protection | SQYD A A | 247,961 | $0.36 | $0.30 |
| 1070 | Initial fertilizer | TON A A | 25.60 | $1,211.51 | $1,032.00 |
| 1080 | Maintenance fertilizer | TON A A | 15.30 | $1,211.51 | $1,032.00 |
| 1090 | Seeding and protection | SQYD A A | 495,923 | $0.64 | $0.47 |
| 1100 | Agricultural limestone | TON A A | 307.40 | $65.19 | $98.00 |
| 1110 | Pave striping-temp paint-4 in | LF A A | 19,314 | $0.18 | $0.16 |
| 1120 | Pave striping-temp paint-6 in | LF A A | 256,858 | $0.21 | $0.20 |
| 1130 | Pave striping-temp paint-12 in | LF A A | 14,048 | $0.32 | $0.40 |
| 1140 | Pave striping-perm paint-4 in | LF A A | 9,657 | $0.28 | $0.22 |
| 1150 | Pave striping-thermo-6 in W | LF A A | 69,510 | $0.85 | $0.90 |
| 1160 | Pave striping-thermo-6 in Y | LF A A | 56,745 | $0.85 | $0.90 |
| 1170 | Pave striping-thermo-12 in Y | LF A A | 62 | $2.50 | $4.50 |
| 1180 | Pave striping-dur TY 1-6 in W | LF A A | 275 | $8.50 | $8.50 |
| 1190 | Pave striping-dur TY 1-6 in Y | LF A A | 275 | $8.50 | $8.50 |
| 1200 | Pave marking-thermo X-walk-6 in | LF A A | 6,656 | $1.50 | $2.00 |
| 1210 | Pave marking-thermo stop bar-24IN | LF A A | 1,615 | $9.00 | $9.00 |
| 1220 | Pave marking-thermo cross-hatch | SQFT A A | 2,927 | $2.00 | $3.50 |
| 1230 | Pave marking-dotted lane exten | LF A A | 1,624 | $2.60 | $2.75 |
| 1240 | Pave marking-thermo STR arrow | EACH A A | 1 | $100.00 | $105.00 |
| 1250 | Pave marking-thermo curv arrow | EACH A A | 123 | $90.00 | $115.00 |
| 1260 | Pave marking-thermo comb arrow | EACH A A | 11 | $130.00 | $175.00 |
| 1270 | Pave marking-thermo only | EACH A A | 2 | $250.00 | $275.00 |
| 1280 | Remove pavement marker type V | EACH A A | 459 | $39.87 | $5.79 |
| 1290 | Inlaid pavement marker-MW | EACH A A | 747 | $26.00 | $30.00 |
| 1300 | Inlaid pavement marker-MY | EACH A A | 414 | $26.00 | $30.00 |
| 1310 | Inlaid pavement marker-by | EACH A A | 138 | $26.00 | $30.00 |
| 1320 | Concrete-class A | CUYD A A | 118.70 | $369.46 | $118.70 |
| 1330 | Fuel adjustment | DOLL A A | 161,845 | $1.00 | $1.00 |
| 1340 | Asphalt adjustment | DOLL A A | 365,197 | $1.00 | $1.00 |
| 1350 | Pave mark temp paint stop bar | LF A A | 3,230 | $2.50 | $5.00 |
| 1360 | Pave mark temp paint line arrow | EACH A A | 396 | $50.00 | $45.00 |
| 1370 | Galvanized steel cabinet | EACH A A | 2 | $900.00 | $900.00 |
| 1380 | Wood post | EACH A A | 4 | $350.00 | $350.00 |
| 1390 | Electrical junction box type A | EACH A A | 2 | $3,000.00 | $3,000.00 |
| 1400 | Centerline rumble strips | LF A A | 700 | $2.15 | $2.15 |
| 1410 | Sawcut pavement | LF A A | 1,103 | $5.50 | $7.23 |
| 1420 | High slump 3000 psi grout | CUYD A A | 6.30 | $314.06 | $258.89 |
| 1430 | Longitudinal edge key | LF A A | 19,955 | $3.00 | $1.00 |
| 1440 | Pave mark thermo cone cap-solid yellow | SQFT A A | 207 | $5.50 | $4.50 |
| 1450 | Sheet piling | LF A A | 98 | $550.00 | $279.23 |
| 1460 | Pave marking-thermo yield bar-36 in | LF A A | 102 | $50.00 | $45.00 |
| 1470 | Pavement marking-thermo letters | EACH A A | 42 | $125.00 | $85.00 |
| 1480 | Detectable warnings | SQFT A A | 3,276 | $51.77 | $51.77 |
| 1490 | Turf reinforcement mat 1 | SQYD A A | 3,173 | $9.56 | $6.34 |
| 1500 | Temporary pipe-30 in | LF A A | 14 | $216.27 | $288.14 |
| 1510 | Pave mark thermo chevron | SQFT A A | 222 | $5.50 | $4.50 |
| 1520 | Pipeline inspection | LF A A | 30,222 | $2.20 | $2.20 |
| 1530 | Utility coordination | LS A A | 1 | $40,000 | $150,000 |
| 1550 | Crushed aggregate size no 2 | TON A A | 6 | $200.00 | $1,000.00 |
| 1560 | Entrance pipe-15 in | LF A A | 589 | $137.21 | $120.41 |
| 1570 | Entrance pipe-18 in | LF A A | 211 | $145.49 | $129.25 |
| 1580 | Entrance pipe-24 in | LF A A | 250 | $162.12 | $134.44 |
| 1590 | Entrance pipe-30 in equiv | LF A A | 70 | $159.13 | $123.97 |
| 1600 | Culvert pipe-15 in | LF A A | 277 | $120.66 | $90.56 |
| 1610 | Culvert pipe-18 in | LF A A | 310 | $104.51 | $84.11 |
| 1620 | Culvert pipe-24 in | LF A A | 445 | $135.99 | $101.76 |
| 1630 | Culvert pipe-36 in | LF A A | 205 | $246.06 | $124.88 |
| 1640 | Culvert pipe-42 in equiv | LF A A | 62 | $309.97 | $253.74 |
| 1650 | Storm sewer pipe-12 in | LF A A | 229 | $171.86 | $67.98 |
| 1660 | Storm sewer pipe-15 in | LF A A | 4,395 | $86.91 | $97.12 |
| 1670 | Storm sewer pipe-18 in | LF A A | 14,931 | $99.53 | $94.78 |
| 1680 | Storm sewer pipe-24 in | LF A A | 5,256 | $121.11 | $130.79 |
| 1690 | Storm sewer pipe-30 in | LF A A | 1,961 | $186.52 | $170.71 |
| 1700 | Storm sewer pipe-36 in | LF A A | 693 | $276.88 | $217.46 |
| 1710 | Storm sewer pipe-42 in | LF A A | 308 | $302.05 | $294.00 |
| 1720 | Perforated pipe-4 in | LF A A | 36,589 | $12.36 | $25.50 |
| 1730 | Perforated pipe-6 in | LF A A | 2,517 | $15.69 | $28.50 |
| 1740 | Non-perforated pipe-4 in | LF A A | 623 | $22.41 | $30.00 |
| 1750 | Non-perforated pipe-6 in | LF A A | 15 | $26.81 | $35.00 |
| 1760 | Perf pipe headwall TY 2-4 in | EACH A A | 3 | $1,058.16 | $1,000.00 |
| 1770 | Perf pipe headwall TY 3-4 in | EACH A A | 5 | $1,058.27 | $1,000.00 |
| 1780 | Pipe culvert headwall-12 in | EACH A A | 1 | $1,793.48 | $1,304.53 |
| 1790 | Pipe culvert headwall-15 in | EACH A A | 15 | $2,077.64 | $1,376.81 |
| 1800 | Pipe culvert headwall-18 in | EACH A A | 14 | $2,153.88 | $1,442.62 |
| 1810 | Pipe culvert headwall-24 in | EACH A A | 11 | $2,224.03 | $1,968.93 |
| 1820 | Pipe culvert headwall-30 in | EACH A A | 4 | $3,070.93 | $2,167.16 |
| 1830 | Pipe culvert headwall-36 in | EACH A A | 4 | $4,215.97 | $2,445.63 |
| 1840 | Pipe culvert headwall-42 in | EACH A A | 2 | $4,275.01 | $3,343.98 |
| 1850 | Sloped box outlet type 1-24 in | EACH A A | 2 | $3,076.02 | $2,862.35 |
| 1860 | S & F box inlet-outlet-18 in | EACH A A | 3 | $2,961.89 | $2,771.15 |
| 1870 | S & F box inlet-outlet-30 in | EACH A A | 1 | $6,264.16 | $5,535.84 |
| 1880 | S & F box inlet-outlet-36 in | EACH A A | 3 | $7,000.00 | $12,852 |
| 1890 | Curb box inlet type A | EACH A A | 210 | $7,000.00 | $5,749.00 |
| 1900 | Curb box inlet type B | EACH A A | 2 | $7,000.00 | $5,826.95 |
| 1910 | Curb box inlet type F | EACH A A | 3 | $5,494.96 | $2,702.89 |
| 1920 | Drop box inlet type 1 | EACH A A | 1 | $3,514.41 | $4,625.45 |
| 1930 | Drop box inlet type 3 | EACH A A | 35 | $5,285.34 | $5,001.30 |
| 1940 | Drop box inlet type 6D | EACH A A | 3 | $2,831.84 | $6,545.52 |
| 1950 | Drop box inlet type 11 | EACH A A | 20 | $3,208.89 | $2,552.30 |
| 1960 | Drop box inlet type 12A | LF A A | 50 | $2,288.52 | $366.01 |
| 1970 | Drop box inlet type 13G | EACH A A | 12 | $4,311.99 | $2,509.05 |
| 1980 | Drop box inlet type 13S | EACH A A | 3 | $5,539.07 | $2,947.77 |
| 1990 | Drop box inlet type 14 | EACH A A | 7 | $3,346.45 | $2,245.51 |
| 2000 | Cap drop box inlet | EACH A A | 1 | $5,303.55 | $1,778.89 |
| 2010 | Drop box inlet type 16S | EACH A A | 1 | $2,394.32 | $6,020.49 |
| 2020 | Cap curb box inlet | EACH A A | 8 | $2,058.56 | $1,732.25 |
| 2030 | Junction box-18 in | EACH A A | 2 | $984.48 | $2,491.53 |
| 2040 | Junction box | EACH A A | 22 | $3,115.87 | $2,491.53 |
| 2050 | Manhole type A | EACH A A | 20 | $5,184.95 | $3,311.49 |
| 2060 | Manhole type C | EACH A A | 11 | $8,461.26 | $6,297.34 |
| 2070 | Adjust manhole frame to grade | EACH A A | 2 | $1,750.18 | $2,120.38 |
| 2080 | Metal end section TY 3-42 in (equiv) | EACH A A | 2 | $2,187.72 | $4,419.11 |
| 2090 | Entrance pipe-36 in | LF A A | 30 | $175.02 | $161.37 |
| 2100 | Structure granular backfill | CUYD A A | 631 | $75.50 | $85.00 |
| 2110 | Armored edge for concrete | LF A A | 155.90 | $205.00 | $85.00 |
| 2120 | Structure excav-solid rock | CUYD A A | 347 | $230.00 | $50.00 |
| 2130 | Foundation preparation | LS A A | 1 | $258,500 | $60,000 |
| 2140 | Cyclopean stone rip rap | TON A A | 122 | $98.00 | $65.00 |
| 2150 | Concrete-class A | CUYD A A | 348 | $1,020.00 | $1,000.00 |
| 2160 | Concrete-class AA | CUYD A A | 113.40 | $1,768.00 | $1,400.00 |
| 2170 | Steel reinforcement | LB A A | 27,201 | $2.63 | $2.00 |
| 2180 | Steel reinforcement-epoxy coated | LB A A | 24,667 | $2.35 | $2.00 |
| 2190 | Approach slab | SQYD A A | 142 | $850.00 | $500.00 |
| 2200 | Precast PC box beam SB21 | LF A A | 306 | $455.00 | $500.00 |
| 2210 | Concrete sealing | SQFT A A | 6,481 | $2.00 | $2.00 |
| 2220 | Rail system single slope - 40 in | LF A A | 106.40 | $267.00 | $170.00 |
| 2230 | Mobilization for concrete surf treatment | LS A A | 1 | $1,675.00 | $500.00 |
| 2240 | Granular embankment | CUYD A A | 90 | $103.50 | $100.00 |
| 2250 | Remove concrete masonry | CUYD A A | 20 | $760.00 | $500.00 |
| 2260 | Fabric-geotextile class 1 | SQYD A A | 119 | $4.13 | $4.00 |
| 2270 | Structure excav-solid rock | CUYD A A | 5 | $790.00 | $500.00 |
| 2280 | Foundation preparation | LS A A | 1 | $40,500 | $60,000 |
| 2290 | Concrete-class A | CUYD A A | 67.80 | $1,850.00 | $1,000.00 |
| 2300 | Steel reinforcement | LB A A | 9,779 | $4.85 | $2.00 |
| 2310 | Structure excav-solid rock | CUYD A A | 5 | $760.00 | $500.00 |
| 2320 | Foundation preparation | LS A A | 1 | $274,715 | $60,000 |
| 2330 | Concrete-class A | CUYD A A | 112 | $1,855.00 | $1,000.00 |
| 2340 | Steel reinforcement | LB A A | 12,450 | $5.30 | $2.00 |
| 2350 | Structure granular backfill | CUYD A A | 614 | $110.30 | $85.00 |
| 2360 | Armored edge for concrete | LF A A | 412 | $115.00 | $85.00 |
| 2370 | Foundation preparation | LS A A | 1 | $55,500 | $60,000 |
| 2380 | Cyclopean stone rip rap | TON A A | 1,336 | $64.00 | $50.00 |
| 2390 | Test piles | LF A A | 94 | $125.50 | $200.00 |
| 2400 | Piles-steel HP12X53 | LF A A | 408 | $126.50 | $125.00 |
| 2410 | Pile points-12 in | EACH A A | 26 | $159.00 | $175.00 |
| 2420 | Concrete-class A | CUYD A A | 77.60 | $1,300.00 | $1,000.00 |
| 2430 | Concrete-class AA | CUYD A A | 347.50 | $1,150.00 | $1,400.00 |
| 2440 | Steel reinforcement-epoxy coated | LB A A | 86,157 | $2.20 | $2.00 |
| 2450 | Approach slab | SQYD A A | 378 | $620.00 | $500.00 |
| 2460 | Precast PC I beam type 3 | LF A A | 810 | $536.00 | $500.00 |
| 2470 | Concrete sealing | SQFT A A | 12,211 | $2.00 | $2.00 |
| 2480 | Rail system single slope - 40 in | LF A A | 166 | $240.00 | $170.00 |
| 2490 | Mobilization for concrete surf treatment | LS A A | 1 | $1,600.00 | $500.00 |
| 2500 | Remove trees or stumps | EACH A A | 24 | $2,002.34 | $500.00 |
| 2510 | W cap existing main | EACH A A | 52 | $3,706.50 | $3,706.50 |
| 2520 | W encasement steel bored range 1 | LF A A | 127 | $204.75 | $204.75 |
| 2530 | W encasement steel bored range 3 | LF A A | 727 | $430.50 | $430.50 |
| 2540 | W encasement steel bored range 4 | LF A A | 150 | $546.00 | $546.00 |
| 2550 | W encasement steel bored range 4 | LF A A | 110 | $656.25 | $656.25 |
| 2560 | W encasement steel bored range 5 | LF A A | 422 | $813.75 | $813.75 |
| 2570 | W encasement steel open cut range 3 | LF A A | 165 | $215.25 | $215.25 |
| 2580 | W encasement steel open cut range 5 | LF A A | 450 | $451.50 | $451.50 |
| 2590 | W fire hydrant assembly | EACH A A | 34 | $11,500 | $11,500 |
| 2600 | W flush hydrant assembly | EACH A A | 3 | $6,200.00 | $6,200.00 |
| 2610 | W meter 1 inch | EACH A A | 7 | $2,485.00 | $2,485.00 |
| 2620 | W meter 1-1/2 inch | EACH A A | 1 | $5,230.00 | $5,230.00 |
| 2630 | W meter 2 inch | EACH A A | 1 | $6,980.00 | $6,980.00 |
| 2640 | W meter 3/4 inch | EACH A A | 77 | $2,010.00 | $2,010.00 |
| 2650 | W meter/fire service combo vault | EACH A A | 1 | $147,000 | $147,000 |
| 2660 | W pipe ductile iron 06 inch | LF A A | 4,205 | $152.00 | $152.00 |
| 2670 | W pipe ductile iron 08 inch | LF A A | 370 | $187.00 | $187.00 |
| 2680 | W pipe ductile iron 12 inch | LF A A | 11,419 | $239.15 | $239.15 |
| 2690 | W pipe PVC 02 inch | LF A A | 640 | $80.00 | $80.00 |
| 2700 | W pipe PVC 03 inch | LF A A | 730 | $88.00 | $88.00 |
| 2710 | W pipe PVC 06 inch | LF A A | 520 | $111.50 | $111.50 |
| 2720 | W pipe PVC 10 inch | LF A A | 180 | $141.75 | $141.75 |
| 2730 | W pipe polyethylene/plastic 03 inch | LF A A | 85 | $113.50 | $113.50 |
| 2740 | W serv PE/PLST long side 1 in | EACH A A | 3 | $11,350 | $11,350 |
| 2750 | W serv PE/PLST long side 1-1/2 in | EACH A A | 1 | $15,385 | $15,385 |
| 2760 | W serv PE/PLST long side 3/4 in | EACH A A | 28 | $11,100 | $11,100 |
| 2770 | W serv PE/PLST short side 1 in | EACH A A | 4 | $2,100.00 | $2,100.00 |
| 2780 | W serv PE/PLST short side 2 in | EACH A A | 1 | $4,850.00 | $4,850.00 |
| 2790 | W serv PE/PLST short side 3/4 in | EACH A A | 49 | $1,560.00 | $1,560.00 |
| 2800 | W service special | EACH A A | 1 | $7,500.00 | $7,500.00 |
| 2810 | W tapping sleeve and valve size 1 | EACH A A | 1 | $2,400.00 | $2,400.00 |
| 2820 | W tapping sleeve and valve size 1 | EACH A A | 2 | $2,920.00 | $2,920.00 |
| 2830 | W tapping sleeve and valve size 1 | EACH A A | 10 | $5,250.00 | $5,250.00 |
| 2840 | W tapping sleeve and valve size 1 | EACH A A | 2 | $6,900.00 | $6,900.00 |
| 2850 | W tapping sleeve and valve size 2 | EACH A A | 14 | $12,600 | $12,600 |
| 2860 | W tie-in 02 inch | EACH A A | 7 | $3,685.00 | $3,685.00 |
| 2870 | W tie-in 03 inch | EACH A A | 3 | $3,230.00 | $3,230.00 |
| 2880 | W tie-in 06 inch | EACH A A | 21 | $4,235.00 | $4,235.00 |
| 2890 | W tie-in 08 inch | EACH A A | 3 | $4,225.00 | $4,225.00 |
| 2900 | W tie-in 10 inch | EACH A A | 2 | $6,410.00 | $6,410.00 |
| 2910 | W tie-in 12 inch | EACH A A | 18 | $7,500.00 | $7,500.00 |
| 2920 | W valve 02 inch | EACH A A | 10 | $2,165.00 | $2,165.00 |
| 2930 | W valve 03 inch | EACH A A | 3 | $2,750.00 | $2,750.00 |
| 2940 | W valve 06 inch | EACH A A | 27 | $3,150.00 | $3,150.00 |
| 2950 | W valve 08 inch | EACH A A | 1 | $4,450.00 | $4,450.00 |
| 2960 | W valve 10 inch | EACH A A | 1 | $6,025.00 | $6,025.00 |
| 2970 | W valve 12 inch | EACH A A | 37 | $7,275.00 | $7,275.00 |
| 2980 | W encasement special | LF A A | 65 | $285.00 | $285.00 |
| 2990 | W meter special | EACH A A | 1 | $6,100.00 | $6,100.00 |
| 3000 | S encasement steel bored range 4 | LF A A | 769 | $680.00 | $680.00 |
| 3010 | S encasement steel bored range 4 | LF A A | 85 | $805.00 | $805.00 |
| 3020 | S encasement steel bored range 5 | LF A A | 220 | $860.00 | $860.00 |
| 3030 | S encasement steel bored range 6 | LF A A | 130 | $977.00 | $977.00 |
| 3040 | S encasement steel bored range 6 | LF A A | 50 | $1,395.00 | $1,395.00 |
| 3050 | S encasement steel open cut range 4 | LF A A | 298 | $290.00 | $290.00 |
| 3060 | S encasement steel open cut range 4 | LF A A | 150 | $395.00 | $395.00 |
| 3070 | S encasement steel open cut range 5 | LF A A | 594 | $530.00 | $530.00 |
| 3080 | S force main air RLS/vac VLV 02 in | EACH A A | 5 | $6,525.00 | $6,525.00 |
| 3090 | S force main PVC 04 inch | LF A A | 545 | $98.00 | $98.00 |
| 3100 | S force main PVC 08 inch | LF A A | 1,695 | $120.00 | $120.00 |
| 3110 | S force main PVC 12 inch | LF A A | 3,115 | $165.00 | $165.00 |
| 3120 | S force main tie-in 04 inch | EACH A A | 3 | $2,385.00 | $2,385.00 |
| 3130 | S force main tie-in 08 inch | EACH A A | 8 | $3,735.00 | $3,735.00 |
| 3140 | S force main tie-in 12 inch | EACH A A | 4 | $7,545.00 | $7,545.00 |
| 3150 | S lateral cleanout | EACH A A | 75 | $2,100.00 | $2,100.00 |
| 3160 | S lateral special | EACH A A | 75 | $1,100.00 | $1,100.00 |
| 3170 | S manhole | EACH A A | 89 | $9,500.00 | $9,500.00 |
| 3180 | S manhole | EACH A A | 6 | $12,600 | $12,600 |
| 3190 | S manhole abandon/remove | EACH A A | 61 | $3,150.00 | $3,150.00 |
| 3200 | S manhole tap existing | EACH A A | 3 | $2,000.00 | $2,000.00 |
| 3210 | S pipe PVC 08 inch | LF A A | 5,415 | $165.00 | $165.00 |
| 3220 | S pipe PVC 10 inch | LF A A | 2,765 | $220.00 | $220.00 |
| 3230 | S pipe PVC 12 inch | LF A A | 1,040 | $275.00 | $275.00 |
| 3240 | S pipe special | LF A A | 2,000 | $121.30 | $121.30 |
| 3250 | S pipe special | LF A A | 3,875 | $514.50 | $514.50 |
| 3260 | S pump station | EACH A A | 1 | $462,000 | $462,000 |
| 3270 | S pipe PVC 15 inch | LF A A | 220 | $275.00 | $275.00 |
| 3280 | S pipe PVC 6 inch | LF A A | 2,000 | $131.25 | $131.25 |
| 3290 | Remove & relocate signs | EACH A A | 8 | $1,000.00 | $200.00 |
| 3300 | Concrete paving replacement | LF A A | 680 | $51.65 | $140.00 |
| 3310 | Dead cap | EACH A A | 15 | $3,700.00 | $3,700.00 |
| 3320 | Asphalt driveway/parking lot replacement | LF A A | 7,275 | $13.58 | $115.00 |
| 3330 | Gravel replacement driveways | LF A A | 985 | $50.50 | $50.50 |
| 3340 | Fence-special | LF A A | 100 | $126.00 | $126.00 |
| 3350 | SBM alum sheet signs .080 in | SQFT A A | 1,387 | $29.62 | $31.00 |
| 3360 | SBM alum sheet signs .125 in | SQFT A A | 239 | $34.06 | $34.50 |
| 3370 | Steel post type 1 | LF A A | 1,698 | $19.79 | $20.25 |
| 3380 | Class A concrete for signs | CUYD A A | 10.50 | $1,279.15 | $1,281.00 |
| 3390 | Remove-store and reinstall sign | EACH A A | 2 | $300.21 | $301.00 |
| 3400 | Remove sign | EACH A A | 12 | $57.18 | $58.00 |
| 3410 | GMSS type D | EACH A A | 48 | $364.35 | $365.00 |
| 3420 | Barcode sign inventory | EACH A A | 308 | $20.01 | $21.00 |
| 3430 | Fused connector kit | EACH A A | 89 | $150.00 | $151.50 |
| 3440 | Electrical junction box type B | EACH A A | 4 | $2,000.00 | $2,020.00 |
| 3450 | Trenching and backfilling | LF A A | 690 | $15.00 | $16.00 |
| 3460 | Cable-no. 14/7C | LF A A | 18,600 | $2.40 | $2.50 |
| 3470 | Mast arm pole | EACH A A | 1 | $27,910 | $28,000 |
| 3480 | Messenger-15400 LB | LF A A | 2,690 | $5.38 | $5.50 |
| 3490 | Messenger-26900 LB | LF A A | 775 | $5.80 | $5.90 |
| 3500 | Install steel strain pole | EACH A A | 26 | $9,900.00 | $10,050 |
| 3510 | Temp relocation of signal head | EACH A A | 44 | $200.00 | $200.00 |
| 3520 | Install span mounted sign | EACH A A | 23 | $250.00 | $250.00 |
| 3530 | Install pedestrian head-LED | EACH A A | 39 | $600.00 | $620.00 |
| 3540 | Install LED signal-3 section | EACH A A | 58 | $550.00 | $555.00 |
| 3550 | Install LED signal- 4 section | EACH A A | 18 | $350.00 | $360.00 |
| 3560 | Install coordinating unit | EACH A A | 1 | $2,500.00 | $2,650.00 |
| 3570 | Bore and jack conduit | LF A A | 140 | $30.00 | $31.00 |
| 3580 | Install pedestrian detector | EACH A A | 42 | $350.00 | $350.00 |
| 3590 | Remove & reinstall coordinating unit | EACH A A | 5 | $2,500.00 | $2,550.00 |
| 3600 | Traffic signal pole base | CUYD A A | 125 | $300.00 | $302.50 |
| 3610 | Install signal pedestal | EACH A A | 25 | $5,000.00 | $5,050.00 |
| 3620 | Tether wire | LF A A | 140 | $2.72 | $3.00 |
| 3630 | PVC conduit-1 1/4 in-schedule 80 | LF A A | 330 | $1.13 | $1.25 |
| 3640 | PVC conduit-2 in-schedule 80 | LF A A | 790 | $1.75 | $1.85 |
| 3650 | Install signal controller-TY atc | EACH A A | 6 | $7,000.00 | $7,100.00 |
| 3660 | Remove signal equipment | EACH A A | 6 | $10,000 | $10,200 |
| 3670 | Install radar presence detector type A | EACH A A | 24 | $1,500.00 | $1,650.00 |
| 3680 | Install radar advance detector type B | EACH A A | 2 | $1,500.00 | $1,600.00 |
| 3690 | Install mast arm dampener | EACH A A | 1 | $250.00 | $260.00 |
| 3700 | Install solar school flasher assembly | EACH A A | 2 | $7,500.00 | $7,650.00 |
| 3710 | Mobilization | LS A A | 1 | $2,350,000 | $3,503,000 |
| 3720 | Demobilization | LS A A | 1 | $1,025,000 | $1,070,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 20, 2026. Compiled by Mirage Metrics.