KYTC contract 26-3015 bid tabulation

ASPHALT RESURFACING ROBERTS ROAD (KY 677). Let by Kentucky Transportation Cabinet on July 23, 2026. 2 bids received; low bid $133,499 by Scotty'S Contracting & Stone LLC, -35% against the engineer's estimate of $205,285.

Owner
Kentucky Transportation Cabinet
Letting
23 JUL 2026
Pay items
15
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Scotty'S Contracting & Stone LLC$133,499Low-35%
2Cleary Construction Inc$153,140+15%-25%
KYTC contract 26-3015: bids by rank

Engineer's estimate: $205,285.

Bid tabulation

LinePay itemUnitQuantity1. Scotty'S Contracting & Stone LLC2. Cleary Construction Inc
0010Dga baseTON A A70$57.29$41.75
0020Asphalt scratch course PG64-22TON A A343$97.50$119.00
0030CL2 asph surf 0.38D PG64-22TON A A755$95.59$109.00
0040Temporary signsSQFT A A190$4.87$5.00
0050Maintain & control trafficLS A A1$3,042.67$3,065.00
0060Mobilization for mill & textLS A A1$6,509.82$1,600.00
0070Asphalt pave milling & texturingTON A A15$8.94$20.00
0080Pave striping-temp paint-4 inLF A A10,676$0.01$0.30
0090Pave striping-perm paint-4 inLF A A10,676$0.32$0.32
0100Pave marking-thermo stop bar-24INLF A A15$20.00$20.00
0110Fuel adjustmentDOLL A A1,722$1.00$1.00
0120Asphalt adjustmentDOLL A A4,325$1.00$1.00
0130Fiber reinforcement for HMATON A A755$2.00$8.00
0140Asphalt material for tack non-trackingTON A A9$0.01$0.01
0150DemobilizationLS A A1$1,883.58$2,184.29
KYTC contract 26-3015: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of July 23, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy