KYTC contract 26-4503 bid tabulation
WIDENING WEST 2ND ST (KY 254). Let by Kentucky Transportation Cabinet on March 26, 2026. 2 bids received; low bid $2,183,288 by Scotty'S Contracting & Stone LLC, -5.4% against the engineer's estimate of $2,308,444.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 26 MAR 2026
- Pay items
- 80
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $2,183,288 | Low | -5.0% |
| 2 | Westate Construction Inc | $2,305,811 | +6.0% | 0.0% |
Engineer's estimate: $2,308,444.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Westate Construction Inc |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 883 | $51.46 | $57.00 |
| 0020 | Asphalt seal aggregate | TON A A | 39.06 | $253.63 | $321.93 |
| 0030 | Asphalt seal coat | TON A A | 4.50 | $1,395.99 | $1,395.99 |
| 0040 | Leveling & wedging PG64-22 | TON A A | 450 | $109.96 | $109.96 |
| 0050 | CL2 asph base 0.75D PG64-22 | TON A A | 350 | $118.90 | $139.00 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A A | 2,596 | $97.66 | $97.66 |
| 0070 | Asphalt material for tack non-tracking | TON A A | 15 | $626.24 | $626.24 |
| 0080 | Crushed stone base | TON A A | 120 | $51.46 | $60.00 |
| 0090 | Crushed aggregate size no 2 | TON A A | 115 | $57.02 | $70.65 |
| 0100 | Delineator for guardrail BI directional white | EACH A A | 12 | $15.52 | $15.52 |
| 0110 | Cem conc ent pavement-8 in | SQYD A A | 44 | $150.00 | $150.00 |
| 0120 | Roadway excavation | CUYD A A | 2,891 | $67.03 | $81.50 |
| 0130 | Guardrail end treatment type 1 | EACH A A | 4 | $3,551.47 | $3,551.47 |
| 0140 | Remove guardrail | LF A A | 713 | $3.66 | $3.66 |
| 0150 | Channel lining class II | TON A A | 8,196 | $48.31 | $57.00 |
| 0160 | Clearing and grubbing | LS A A | 1 | $21,309 | $3,000.00 |
| 0170 | Temporary signs | SQFT A A | 400 | $8.08 | $9.54 |
| 0180 | Fabric-geotextile class 1 | SQYD A A | 23 | $3.19 | $8.00 |
| 0190 | Fabric-geotextile class 1A | SQYD A A | 360 | $4.50 | $5.00 |
| 0200 | Maintain & control traffic | LS A A | 1 | $7,938.63 | $51,500 |
| 0210 | Maintain & control traffic | LS A A | 1 | $143,781 | $27,000 |
| 0215 | Portable changeable message sign | EACH A A | 2 | $4,273.13 | $742.00 |
| 0220 | Mobilization for mill & text | LS A A | 1 | $2,549.91 | $2,549.91 |
| 0230 | Mobilization for mill & text | LS A A | 1 | $4,388.25 | $4,388.25 |
| 0240 | Asphalt pave milling & texturing | TON A A | 189 | $120.05 | $120.05 |
| 0250 | Edgeline rumble strips | LF A A | 56,097 | $0.25 | $0.25 |
| 0260 | Temp silt fence | LF A A | 10,000 | $0.01 | $3.05 |
| 0270 | Silt trap type A | EACH A A | 10 | $0.01 | $50.00 |
| 0280 | Silt trap type B | EACH A A | 20 | $268.75 | $50.00 |
| 0290 | Silt trap type C | EACH A A | 20 | $0.01 | $50.00 |
| 0300 | Clean silt trap type A | EACH A A | 10 | $0.01 | $10.00 |
| 0310 | Clean silt trap type B | EACH A A | 20 | $0.01 | $10.00 |
| 0320 | Clean silt trap type C | EACH A A | 20 | $0.01 | $10.00 |
| 0330 | Staking | LS A A | 1 | $39,931 | $28,500 |
| 0340 | Base failure repair | SQYD A A | 378 | $142.72 | $225.00 |
| 0350 | Erosion control blanket | SQYD A A | 15,000 | $1.85 | $2.00 |
| 0360 | Temp mulch | SQYD A A | 50,000 | $0.20 | $0.30 |
| 0370 | Temp seeding and protection | SQYD A A | 25,000 | $0.30 | $0.35 |
| 0380 | Initial fertilizer | TON A A | 5 | $1,500.00 | $2,100.00 |
| 0390 | Maintenance fertilizer | TON A A | 3 | $1,500.00 | $2,100.00 |
| 0400 | Seeding and protection | SQYD A A | 25,000 | $0.45 | $0.75 |
| 0410 | Pave striping-temp paint-4 in | LF A A | 70,534 | $0.30 | $0.30 |
| 0420 | Pave striping-perm paint-6 in | LF A A | 116,794 | $0.35 | $0.35 |
| 0430 | Pave marking-thermo stop bar-24IN | LF A A | 30 | $20.00 | $20.00 |
| 0440 | Fuel adjustment | DOLL A A | 2,756 | $1.00 | $1.00 |
| 0450 | Asphalt adjustment | DOLL A A | 3,323 | $1.00 | $1.00 |
| 0460 | Object marker TY 3 | EACH A A | 4 | $29.60 | $29.60 |
| 0470 | Shoulder milling/trenching | SQYD A A | 420 | $22.77 | $26.00 |
| 0480 | G/R steel W beam-S face (7 FT post) | LF A A | 506.25 | $39.70 | $39.70 |
| 0490 | Thrie beam guardrail transition TL-2 | EACH A A | 4 | $1,978.66 | $1,978.66 |
| 0500 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 | $0.01 |
| 0510 | Entrance pipe-18 in | LF A A | 135 | $120.00 | $77.00 |
| 0520 | Entrance pipe-24 in | LF A A | 14 | $156.57 | $87.00 |
| 0530 | Culvert pipe-18 in | LF A A | 196 | $188.94 | $215.00 |
| 0540 | Culvert pipe-24 in | LF A A | 20 | $178.68 | $140.00 |
| 0550 | Culvert pipe-30 in | LF A A | 113 | $243.81 | $215.00 |
| 0560 | Culvert pipe-36 in | LF A A | 56 | $278.33 | $217.00 |
| 0570 | Culvert pipe-60 in | LF A A | 38 | $591.19 | $700.00 |
| 0580 | Pipe culvert headwall-60 in | EACH A A | 2 | $8,000.00 | $14,500 |
| 0590 | Remove pipe | LF A A | 280 | $5.71 | $3.50 |
| 0600 | Fabric-geotextile class 2 for pipe | SQYD A A | 352 | $2.00 | $2.00 |
| 0610 | Foundation preparation | LS A A | 1 | $22,585 | $65,000 |
| 0620 | Foundation preparation | LS A A | 1 | $26,515 | $49,000 |
| 0630 | Concrete-class A | CUYD A A | 24.40 | $301.80 | $280.00 |
| 0640 | Concrete-class A | CUYD A A | 63.20 | $1,485.00 | $1,185.00 |
| 0650 | Concrete-class A | CUYD A A | 63.70 | $1,470.00 | $1,185.00 |
| 0660 | Steel reinforcement | LB A A | 9,919 | $2.20 | $2.54 |
| 0670 | Steel reinforcement | LB A A | 7,895 | $2.20 | $2.56 |
| 0680 | Pipe culvert headwall-72 in | EACH A A | 2 | $18,000 | $16,500 |
| 0690 | Sloped and mitered headwall-18 in | EACH A A | 4 | $3,000.00 | $2,400.00 |
| 0700 | Sloped and mitered headwall-24 in | EACH A A | 2 | $3,800.00 | $2,900.00 |
| 0710 | Sloped and mitered headwall-30 in | EACH A A | 8 | $4,500.00 | $3,200.00 |
| 0720 | Sloped and mitered headwall-36 in | EACH A A | 6 | $5,000.00 | $4,100.00 |
| 0730 | Temporary signs | SQFT A A | 400 | $8.08 | $9.54 |
| 0740 | SBM alum sheet signs .080 in | SQFT A A | 343.63 | $46.99 | $46.99 |
| 0750 | SBM alum sheet signs .125 in | SQFT A A | 102.52 | $48.64 | $48.64 |
| 0760 | Steel post type 1 | LF A A | 872 | $25.46 | $25.46 |
| 0770 | Remove sign | EACH A A | 94 | $65.00 | $65.00 |
| 0780 | Barcode sign inventory | EACH A A | 94 | $47.62 | $47.62 |
| 0790 | Demobilization | LS A A | 1 | $32,358 | $34,068 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way