KYTC contract 26-4531 bid tabulation
ASPHALT PAVEMENT & ROADWAY REHAB SCOTTSVILLE ROAD (US 31E). Let by Kentucky Transportation Cabinet on June 25, 2026. 2 bids received; low bid $4,227,598 by Scotty'S Contracting & Stone LLC, -10% against the engineer's estimate of $4,710,071.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 JUN 2026
- Pay items
- 61
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $4,227,598 | Low | -10% |
| 2 | Cleary Construction Inc | $5,975,000 | +41% | +27% |
Engineer's estimate: $4,710,071.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Asphalt seal aggregate | TON A A | 286 | $108.76 | $100.00 |
| 0020 | Asphalt seal coat | TON A A | 34 | $971.93 | $1,000.00 |
| 0030 | Leveling & wedging PG64-22 | TON A A | 1,423 | $95.56 | $116.00 |
| 0040 | CL3 asph base 1.00D PG64-22 | TON A A | 6,522 | $90.35 | $192.00 |
| 0050 | CL3 asph surf 0.38B PG64-22 | TON A A | 6,371 | $102.86 | $122.00 |
| 0060 | Asphalt pave milling & texturing | TON A A | 6,310 | $9.49 | $5.00 |
| 0070 | Joint adhesive | LF A A | 43,224 | $0.50 | $0.50 |
| 0080 | Asphalt material for tack non-tracking | TON A A | 34 | $672.31 | $716.00 |
| 0090 | Crushed stone base | TON A A | 13,874 | $35.44 | $45.00 |
| 0100 | Drainage blanket-type II-asph | TON A A | 3,582 | $80.43 | $182.00 |
| 0110 | Storm sewer pipe-18 in | LF A A | 60 | $232.21 | $113.00 |
| 0120 | Storm sewer pipe-24 in | LF A A | 60 | $255.00 | $126.00 |
| 0130 | Delineator for G/R mono directional white | EACH A A | 58 | $10.00 | $10.00 |
| 0140 | Barricade-type III | EACH A A | 10 | $275.00 | $100.00 |
| 0150 | Roadway excavation | CUYD A A | 20,333 | $22.20 | $34.00 |
| 0160 | Ditching | LF A A | 850 | $1.59 | $10.00 |
| 0170 | G/R terminal section no 1 | EACH A A | 17 | $65.00 | $65.00 |
| 0180 | G/R end treatment type 1 | EACH A A | 14 | $3,400.00 | $3,400.00 |
| 0190 | Remove G/R | LF A A | 6,125 | $3.00 | $3.00 |
| 0200 | G/R-W beam-S face TL-3 | LF A A | 6,625 | $30.50 | $30.50 |
| 0210 | Channel lining class II | TON A A | 21 | $158.12 | $85.00 |
| 0220 | Clearing and grubbing | LS A A | 1 | $85,795 | $35,000 |
| 0230 | Temporary signs | SQFT A A | 450 | $11.40 | $6.00 |
| 0240 | Fabric-geotextile class 4A | SQYD A A | 17,903 | $4.31 | $4.36 |
| 0250 | Maintain & control traffic | LS A A | 1 | $317,804 | $275,000 |
| 0260 | Portable changeable message sign | EACH A A | 4 | $2,848.75 | $3,180.00 |
| 0270 | Mobilization for mill & text | LS A A | 1 | $3,102.49 | $10,000 |
| 0280 | Edgeline rumble strips | LF A A | 42,101 | $0.24 | $0.14 |
| 0290 | Temp silt fence | LF A A | 22,100 | $2.73 | $2.50 |
| 0300 | Silt trap type B | EACH A A | 10 | $328.95 | $150.00 |
| 0310 | Silt trap type C | EACH A A | 10 | $328.95 | $250.00 |
| 0320 | Clean silt trap type B | EACH A A | 10 | $0.01 | $0.01 |
| 0330 | Clean silt trap type C | EACH A A | 10 | $0.01 | $0.01 |
| 0340 | Staking | LS A A | 1 | $21,117 | $91,000 |
| 0350 | Erosion control blanket | SQYD A A | 8,317 | $1.95 | $2.35 |
| 0360 | Temp mulch | SQYD A A | 8,317 | $0.25 | $0.33 |
| 0370 | Temp seeding and protection | SQYD A A | 8,317 | $0.35 | $0.35 |
| 0380 | Initial fertilizer | TON A A | 1 | $1,600.00 | $2,000.00 |
| 0390 | Maintenance fertilizer | TON A A | 1 | $1,600.00 | $2,000.00 |
| 0400 | SBM alum sheet signs .125 in | SQFT A A | 297 | $37.00 | $37.00 |
| 0410 | Steel post type 1 | LF A A | 544 | $22.00 | $22.00 |
| 0420 | Pave striping-temp paint-6 in | LF A A | 84,200 | $0.32 | $0.32 |
| 0430 | Pave striping-thermo-6 in W | LF A A | 42,599 | $1.30 | $1.30 |
| 0440 | Pave striping-thermo-6 in Y | LF A A | 35,413 | $1.30 | $1.30 |
| 0450 | Pave striping-temp rem tape-Y | LF A A | 42,101 | $0.89 | $2.89 |
| 0460 | Pave marking-thermo stop bar-24IN | LF A A | 180 | $15.00 | $15.00 |
| 0470 | Pave marking-thermo cross-hatch | SQFT A A | 605 | $7.00 | $7.00 |
| 0480 | Inlaid pavement marker-by | EACH A A | 528 | $24.00 | $24.00 |
| 0490 | Fuel adjustment | DOLL A A | 29,786 | $1.00 | $1.00 |
| 0500 | Asphalt adjustment | DOLL A A | 42,182 | $1.00 | $1.00 |
| 0510 | Object marker TY 3 | EACH A A | 14 | $55.00 | $55.00 |
| 0520 | Centerline rumble strips | LF A A | 42,101 | $0.16 | $0.16 |
| 0530 | Barcode sign inventory | EACH A A | 30 | $25.00 | $25.00 |
| 0540 | Install radar presence detector type A | EACH A A | 2 | $1,401.25 | $1,475.00 |
| 0550 | Install radar advance detector type B | EACH A A | 2 | $1,401.25 | $1,475.00 |
| 0560 | Sloped and mitered headwall-18 in | EACH A A | 13 | $3,000.00 | $2,500.00 |
| 0570 | Sloped and mitered headwall-24 in | EACH A A | 1 | $3,800.00 | $2,850.00 |
| 0580 | Pave mark-thermo polymer mod curve arrow | EACH A A | 8 | $700.00 | $700.00 |
| 0590 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 | $1.00 |
| 0600 | Mobilization | LS A A | 1 | $115,708 | $275,000 |
| 0610 | Demobilization | LS A A | 1 | $59,703 | $83,924 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of June 25, 2026. Compiled by Mirage Metrics.