KYTC contract 26-4532 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE JOE PRATHER HIGHWAY (KY 313). Let by Kentucky Transportation Cabinet on July 23, 2026. 6 bids received; low bid $172,146 by Dirt Works Unlimited LLC, -34% against the engineer's estimate of $262,344.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 JUL 2026
- Pay items
- 32
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dirt Works Unlimited LLC | $172,146 | Low | -34% |
| 2 | Mago Construction Company LLC | $178,578 | +4.0% | -32% |
| 3 | Scotty'S Contracting & Stone LLC | $179,077 | +4.0% | -32% |
| 4 | E & B Paving LLC | $198,600 | +15% | -24% |
| 5 | Phillips Brothers Construction LLC | $207,065 | +20% | -21% |
| 6 | Louisville Paving Company Inc | $223,500 | +30% | -15% |
Engineer's estimate: $262,344.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dirt Works Unlimited LLC | 2. Mago Construction Company LLC | 3. Scotty'S Contracting & Stone LLC | 4. E & B Paving LLC | 5. Phillips Brothers Construction LLC | 6. Louisville Paving Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 820 | $40.00 | $40.00 | $57.18 | $37.00 | $30.00 | $35.68 |
| 0020 | Asphalt seal aggregate | TON A A | 1.04 | $100.00 | $5,000.00 | $2,650.00 | $4,100.00 | $2,650.00 | $18,038 |
| 0030 | Asphalt seal coat | TON A A | 0.12 | $1,000.00 | $800.00 | $14,540 | $11,765 | $14,540 | $1,250.00 |
| 0040 | CL3 asph base 0.75D PG64-22 | TON A A | 220 | $130.00 | $120.00 | $105.30 | $142.00 | $105.30 | $117.00 |
| 0050 | CL3 asph surf 0.38B PG64-22 | TON A A | 147 | $150.00 | $168.00 | $105.40 | $162.00 | $105.40 | $150.00 |
| 0060 | Asphalt material for tack non-tracking | TON A A | 0.86 | $1.00 | $1.00 | $825.00 | $1.00 | $825.00 | $0.01 |
| 0070 | Electronic delivery MGMT system - agg | LS A A | 1 | $800.00 | $1.00 | $0.01 | $1.00 | $1,200.00 | $1.00 |
| 0080 | Barricade-type III | EACH A A | 4 | $150.00 | $100.00 | $85.00 | $159.00 | $200.00 | $150.00 |
| 0090 | Temporary signs | SQFT A A | 128 | $7.00 | $5.00 | $18.75 | $7.42 | $9.50 | $7.00 |
| 0100 | Fabric-geotextile class 1 | SQYD A A | 632 | $2.40 | $3.50 | $2.91 | $3.00 | $7.50 | $8.25 |
| 0110 | Maintain & control traffic | LS A A | 1 | $20,000 | $4,300.00 | $11,000 | $10,125 | $25,000 | $29,018 |
| 0120 | Portable changeable message sign | EACH A A | 3 | $500.00 | $1,272.00 | $595.00 | $530.00 | $1,325.00 | $1,000.00 |
| 0130 | Mobilization for mill & text | LS A A | 1 | $12,700 | $13,500 | $8,200.00 | $3,500.00 | $8,200.00 | $18,000 |
| 0140 | Asphalt pave milling & texturing | TON A A | 103 | $15.00 | $14.50 | $63.25 | $90.00 | $63.25 | $69.11 |
| 0150 | Temp silt fence | LF A A | 275 | $2.50 | $4.00 | $2.98 | $3.50 | $6.00 | $7.39 |
| 0160 | Silt trap type B | EACH A A | 1 | $250.00 | $225.00 | $255.10 | $840.00 | $500.00 | $1,102.50 |
| 0170 | Silt trap type C | EACH A A | 1 | $150.00 | $225.00 | $0.01 | $275.00 | $500.00 | $1,905.00 |
| 0180 | Clean silt trap type B | EACH A A | 1 | $50.00 | $10.00 | $129.81 | $55.00 | $250.00 | $2,950.00 |
| 0190 | Clean silt trap type C | EACH A A | 1 | $50.00 | $10.00 | $0.01 | $55.00 | $250.00 | $2,700.00 |
| 0200 | Staking | LS A A | 1 | $5,000.00 | $4,000.00 | $4,080.22 | $5,500.00 | $6,500.00 | $9,660.00 |
| 0210 | Initial fertilizer | TON A A | 0.06 | $6,500.00 | $1,032.00 | $2,625.00 | $10,000 | $3,000.00 | $1,032.00 |
| 0220 | Maintenance fertilizer | TON A A | 0.03 | $8,500.00 | $1,032.00 | $2,625.00 | $10,000 | $3,000.00 | $1,032.00 |
| 0230 | Seeding and protection | SQYD A A | 831 | $2.00 | $5.19 | $0.79 | $5.00 | $2.00 | $5.19 |
| 0240 | Pave marking-thermo stop bar-24IN | LF A A | 18 | $15.00 | $15.00 | $15.00 | $15.00 | $7.50 | $15.00 |
| 0250 | Pave marking-thermo cross-hatch | SQFT A A | 700 | $6.00 | $6.00 | $6.00 | $6.00 | $7.50 | $6.00 |
| 0260 | Pave marking-thermo curv arrow | EACH A A | 4 | $125.00 | $125.00 | $125.00 | $125.00 | $156.25 | $125.00 |
| 0270 | Joint adhesive | LF A A | 610 | $0.10 | $5.00 | $5.00 | $0.10 | $6.25 | $3.15 |
| 0280 | Excavation | CUYD A A | 800 | $30.00 | $45.00 | $41.26 | $65.00 | $52.00 | $28.81 |
| 0290 | Pave mark thermo chevron | SQFT A A | 960 | $4.75 | $4.75 | $4.75 | $4.75 | $6.00 | $4.00 |
| 0300 | Pave striping-spray thermo-6 in W | LF A A | 1,600 | $1.00 | $1.00 | $1.00 | $1.00 | $1.25 | $1.00 |
| 0310 | Pave striping-spray thermo-6 in Y | LF A A | 228 | $1.00 | $1.00 | $1.00 | $1.00 | $1.25 | $1.00 |
| 0320 | Demobilization | LS A A | 1 | $5,000.00 | $2,639.09 | $2,646.65 | $3,400.00 | $15,900 | $3,332.11 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of July 23, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.