KYTC contract 26-5401 bid tabulation
BRIDGE REPLACEMENT KY 78 OVER HANGING FORK CREEK. Let by Kentucky Transportation Cabinet on January 29, 2026. 2 bids received; low bid $3,291,802 by Bush & Burchett Inc, +3.1% against the engineer's estimate of $3,193,741.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 29 JAN 2026
- Pay items
- 73
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bush & Burchett Inc | $3,291,802 | Low | +3.0% |
| 2 | Orders Construction Company Inc | $4,081,345 | +24% | +28% |
Engineer's estimate: $3,193,741.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bush & Burchett Inc | 2. Orders Construction Company Inc |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 2,627 | $38.90 | $43.00 |
| 0020 | Asphalt seal aggregate | TON A A | 36 | $200.00 | $220.00 |
| 0030 | Asphalt seal coat | TON A A | 4.34 | $1,400.00 | $1,500.00 |
| 0040 | CL2 asph base 0.75D PG64-22 | TON A A | 1,031 | $108.50 | $120.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 284 | $122.10 | $130.00 |
| 0060 | Asphalt material for tack | TON A A | 2.94 | $71.00 | $780.00 |
| 0070 | Fuel adjustment | DOLL A A | 2,047 | $1.00 | $1.00 |
| 0080 | Asphalt adjustment | DOLL A A | 5,141 | $1.00 | $1.00 |
| 0090 | Crushed aggregate size no 2 | TON A A | 25 | $75.00 | $83.00 |
| 0100 | Entrance pipe-15 in | LF A A | 47 | $85.00 | $94.00 |
| 0110 | Entrance pipe-24 in | LF A A | 62 | $125.00 | $140.00 |
| 0120 | Perforated pipe-4 in | LF A A | 120 | $28.50 | $31.00 |
| 0130 | Non-perforated pipe-4 in | LF A A | 50 | $30.00 | $33.00 |
| 0140 | Perf pipe headwall TY 1-4 in | EACH A A | 2 | $1,600.00 | $1,800.00 |
| 0150 | Perf pipe headwall TY 3-4 in | EACH A A | 1 | $1,600.00 | $1,800.00 |
| 0160 | Metal end section TY 1-24 in | EACH A A | 1 | $6,500.00 | $7,200.00 |
| 0170 | Sloped box outlet type 1-15 in | EACH A A | 1 | $2,500.00 | $2,800.00 |
| 0180 | Drop box inlet type 14 | EACH A A | 1 | $3,050.00 | $3,400.00 |
| 0190 | Junction box-24 in | EACH A A | 1 | $2,800.00 | $3,100.00 |
| 0200 | Flume inlet type 2 | EACH A A | 1 | $9,500.00 | $10,000 |
| 0210 | Standard header curb | LF A A | 22 | $105.00 | $120.00 |
| 0220 | Delineator for guardrail BI directional white | EACH A A | 32 | $13.58 | $11.00 |
| 0230 | Remove pavement | SQYD A A | 350 | $15.00 | $17.00 |
| 0240 | Roadway excavation | CUYD A A | 23,833 | $19.50 | $22.00 |
| 0250 | Guardrail-steel W beam-S face | LF A A | 1,112.50 | $29.11 | $35.00 |
| 0260 | Guardrail-steel W beam-S face A | LF A A | 50 | $35.54 | $72.00 |
| 0270 | Guardrail terminal section no 1 | EACH A A | 2 | $86.34 | $110.00 |
| 0280 | Remove guardrail | LF A A | 1,088 | $2.32 | $2.20 |
| 0290 | Guardrail end treatment type 4A | EACH A A | 2 | $3,729.02 | $5,500.00 |
| 0300 | Extra length guardrail post | EACH A A | 20 | $53.23 | $83.00 |
| 0310 | Right-of-way monument type 1 | EACH A A | 12 | $144.14 | $260.00 |
| 0320 | Witness post | EACH A A | 3 | $127.59 | $240.00 |
| 0330 | Channel lining class II | TON A A | 88 | $51.00 | $56.00 |
| 0340 | Channel lining class III | TON A A | 2,057 | $53.75 | $59.00 |
| 0350 | Clearing and grubbing | LS A A | 1 | $25,750 | $105,000 |
| 0360 | Object marker type 2 | EACH A A | 4 | $235.20 | $110.00 |
| 0370 | Edge key | LF A A | 44 | $85.00 | $94.00 |
| 0380 | Fabric-geotextile class 1 | SQYD A A | 500 | $5.00 | $5.50 |
| 0390 | Fabric-geotextile class 2 | SQYD A A | 500 | $5.00 | $5.50 |
| 0400 | Staking | LS A A | 1 | $22,500 | $150,000 |
| 0410 | Pave striping-thermo-6 in W | LF A A | 2,600 | $1.35 | $1.50 |
| 0420 | Pave striping-thermo-6 in Y | LF A A | 2,600 | $1.35 | $1.50 |
| 0430 | Object marker TY 3 | EACH A A | 2 | $28.32 | $220.00 |
| 0440 | Erosion control | LS A A | 1 | $50,000 | $65,000 |
| 0450 | Turf reinforcement mat 1 | SQYD A A | 419 | $9.82 | $17.00 |
| 0460 | Barcode sign inventory | EACH A A | 4 | $26.12 | $22.00 |
| 0470 | Thrie beam guardrail transition TL-3 | EACH A A | 4 | $3,066.78 | $3,900.00 |
| 0480 | Barricade-type III | EACH A A | 2 | $1,000.00 | $1,100.00 |
| 0490 | Structure granular backfill | CUYD A A | 942 | $60.00 | $140.00 |
| 0500 | Temporary signs | SQFT A A | 502 | $17.75 | $20.00 |
| 0510 | Maintain & control traffic | LS A A | 1 | $45,000 | $100,000 |
| 0520 | Portable changeable message sign | EACH A A | 2 | $10,000 | $11,000 |
| 0530 | Remove structure | LS A A | 1 | $70,000 | $250,000 |
| 0540 | Armored edge for concrete | LF A A | 67.90 | $125.00 | $430.00 |
| 0550 | Structure excav-solid rock | CUYD A A | 101 | $150.00 | $420.00 |
| 0560 | Foundation preparation | LS A A | 1 | $230,000 | $225,000 |
| 0570 | Cyclopean stone rip rap | TON A A | 481 | $50.00 | $66.00 |
| 0580 | Test piles | LF A A | 51 | $300.00 | $400.00 |
| 0590 | Pre-drilling for piles | LF A A | 130 | $850.00 | $500.00 |
| 0600 | Piles-steel HP12X53 | LF A A | 84 | $175.00 | $300.00 |
| 0610 | Pile points-21 in | EACH A A | 13 | $1.00 | $310.00 |
| 0620 | Pile points-12 in | EACH A A | 7 | $175.00 | $310.00 |
| 0630 | Concrete-class A | CUYD A A | 346.70 | $1,200.00 | $1,300.00 |
| 0640 | Concrete-class AA | CUYD A A | 183.40 | $1,650.00 | $1,500.00 |
| 0650 | Steel reinforcement | LB A A | 27,653 | $2.00 | $2.00 |
| 0660 | Steel reinforcement-epoxy coated | LB A A | 57,360 | $2.00 | $2.20 |
| 0670 | Precast PC I beam type 2 | LF A A | 600 | $600.00 | $510.00 |
| 0680 | Concrete sealing | SQFT A A | 10,990 | $2.00 | $3.80 |
| 0690 | Piles-steel W21 X 122 | LF A A | 324 | $230.00 | $350.00 |
| 0700 | Rail system single slope - 40 in | LF A A | 310 | $140.00 | $230.00 |
| 0710 | Mobilization for concrete surf treatment | LS A A | 1 | $500.00 | $11,000 |
| 0720 | Mobilization | LS A A | 1 | $150,000 | $162,000 |
| 0730 | Demobilization | LS A A | 1 | $47,000 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.