KYTC contract 26-5402 bid tabulation

BRIDGE REPLACEMENT KY 90. Let by Kentucky Transportation Cabinet on January 29, 2026. 2 bids received; low bid $3,721,244 by Scott and Murphy Inc, -0.9% against the engineer's estimate of $3,756,902.

Owner
Kentucky Transportation Cabinet
Letting
29 JAN 2026
Pay items
70
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Scott and Murphy Inc$3,721,244Low-1.0%
2Orders Construction Company Inc$5,270,616+42%+40%
KYTC contract 26-5402: bids by rank

Engineer's estimate: $3,756,902.

Bid tabulation

LinePay itemUnitQuantity1. Scott and Murphy Inc2. Orders Construction Company Inc
0010Dga baseTON A A3,594$36.00$44.00
0020Asphalt seal aggregateTON A A54.25$140.00$160.00
0030Asphalt seal coatTON A A6.51$1,650.00$1,900.00
0040CL2 asph base 1.00D PG64-22TON A A2,080$115.00$130.00
0050CL2 asph surf 0.38D PG64-22TON A A477$150.00$170.00
0060Asphalt material for tackTON A A0.87$750.00$860.00
0070Fuel adjustmentDOLL A A3,980$1.00$1.00
0080Asphalt adjustmentDOLL A A9,997$1.00$1.00
0090Entrance pipe-18 inLF A A60$71.00$150.00
0100Entrance pipe-24 inLF A A50$93.00$170.00
0110Entrance pipe-30 inLF A A120$150.00$180.00
0120Culvert pipe-18 inLF A A80$71.00$160.00
0130Culvert pipe-24 inLF A A273$93.00$130.00
0140Culvert pipe-30 inLF A A26$150.00$190.00
0150Pipe culvert headwall-18 inEACH A A2$1,800.00$1,700.00
0160Pipe culvert headwall-24 inEACH A A6$2,100.00$1,400.00
0170Pipe culvert headwall-30 inEACH A A4$4,000.00$1,900.00
0180Flume inlet type 1EACH A A1$6,700.00$12,000
0190Delineator for guardrail BI directional whiteEACH A A46$13.58$15.00
0200Barricade-type IIIEACH A A4$285.00$170.00
0210Remove pavementSQYD A A30$25.00$190.00
0220Temp ditchLF A A285$2.00$31.00
0230Embankment in placeCUYD A A25,567$34.00$40.00
0240Guardrail-steel W beam-S faceLF A A2,362.50$30.39$34.00
0250Guardrail terminal section no 1EACH A A5$86.34$95.00
0260Guardrail end treatment type 1EACH A A3$3,676.46$4,100.00
0270Right-of-way monument type 1EACH A A19$285.00$120.00
0280Witness postEACH A A19$270.00$140.00
0290Channel lining class IITON A A182$44.00$64.00
0300Channel lining class IIITON A A100$45.00$69.00
0310Clearing and grubbingLS A A1$53,500$125,000
0320Temporary signsSQFT A A81$18.00$20.00
0330Edge keyLF A A95$45.00$52.00
0340Maintain & control trafficLS A A1$36,000$100,000
0350Portable changeable message signEACH A A2$4,000.00$9,300.00
0360Edgeline rumble stripsLF A A3,316$1.36$1.50
0370StakingLS A A1$11,500$150,000
0380Erosion control blanketSQYD A A162$4.50$5.00
0390Pave striping-temp paint-6 inLF A A3,000$0.34$2.20
0400Pave striping-thermo-6 in WLF A A3,690$1.35$11.00
0410Pave striping-thermo-6 in YLF A A4,100$1.35$11.00
0420Object marker TY 3EACH A A3$36.59$120.00
0430Erosion controlLS A A1$45,400$55,000
0440Turf reinforcement mat 1SQYD A A540$10.24$11.00
0450Turf reinforcement mat 4SQYD A A29$20.00$22.00
0460Barcode sign inventoryEACH A A4$1.00$1.10
0470Thrie beam guardrail transition TL-3EACH A A4$4,845.34$3,700.00
0480Electronic delivery MGMT system - aggLS A A1$1,000.00$8,500.00
0490Kytc S&F headwall-18 inEACH A A2$2,500.00$1,700.00
0500Structure granular backfillCUYD A A575$79.00$95.00
0510Remove structureLS A A1$20,000$250,000
0520Armored edge for concreteLF A A58$122.96$380.00
0530Structure excav-solid rockCUYD A A38$316.32$370.00
0540Foundation preparationLS A A1$13,847$125,000
0550Cyclopean stone rip rapTON A A185$38.13$54.00
0560Crushed aggregate slope protTON A A195$30.82$65.00
0570Test pilesLF A A64$122.84$200.00
0580Pre-drilling for pilesLF A A394$200.28$280.00
0590Piles-steel HP12X53LF A A434$78.99$120.00
0600Pile points-12 inEACH A A18$169.32$350.00
0610Concrete-class ACUYD A A274.50$982.54$1,400.00
0620Concrete-class AACUYD A A236.20$1,299.86$1,700.00
0630Steel reinforcementLB A A35,132$1.80$2.00
0640Steel reinforcement-epoxy coatedLB A A89,370$1.89$2.30
0650Precast PC I beam type 4LF A A721.40$758.43$740.00
0660Concrete sealingSQFT A A16,453$1.99$3.70
0670Rail system type C412LF A A368.10$501.94$590.00
0680Mobilization for concrete surf treatmentLS A A1$3,252.25$11,000
0690MobilizationLS A A1$92,000$230,000
0700DemobilizationLS A A1$55,819$75,000
KYTC contract 26-5402: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of January 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy