KYTC contract 26-5402 bid tabulation
BRIDGE REPLACEMENT KY 90. Let by Kentucky Transportation Cabinet on January 29, 2026. 2 bids received; low bid $3,721,244 by Scott and Murphy Inc, -0.9% against the engineer's estimate of $3,756,902.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 29 JAN 2026
- Pay items
- 70
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scott and Murphy Inc | $3,721,244 | Low | -1.0% |
| 2 | Orders Construction Company Inc | $5,270,616 | +42% | +40% |
Engineer's estimate: $3,756,902.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scott and Murphy Inc | 2. Orders Construction Company Inc |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 3,594 | $36.00 | $44.00 |
| 0020 | Asphalt seal aggregate | TON A A | 54.25 | $140.00 | $160.00 |
| 0030 | Asphalt seal coat | TON A A | 6.51 | $1,650.00 | $1,900.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 2,080 | $115.00 | $130.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 477 | $150.00 | $170.00 |
| 0060 | Asphalt material for tack | TON A A | 0.87 | $750.00 | $860.00 |
| 0070 | Fuel adjustment | DOLL A A | 3,980 | $1.00 | $1.00 |
| 0080 | Asphalt adjustment | DOLL A A | 9,997 | $1.00 | $1.00 |
| 0090 | Entrance pipe-18 in | LF A A | 60 | $71.00 | $150.00 |
| 0100 | Entrance pipe-24 in | LF A A | 50 | $93.00 | $170.00 |
| 0110 | Entrance pipe-30 in | LF A A | 120 | $150.00 | $180.00 |
| 0120 | Culvert pipe-18 in | LF A A | 80 | $71.00 | $160.00 |
| 0130 | Culvert pipe-24 in | LF A A | 273 | $93.00 | $130.00 |
| 0140 | Culvert pipe-30 in | LF A A | 26 | $150.00 | $190.00 |
| 0150 | Pipe culvert headwall-18 in | EACH A A | 2 | $1,800.00 | $1,700.00 |
| 0160 | Pipe culvert headwall-24 in | EACH A A | 6 | $2,100.00 | $1,400.00 |
| 0170 | Pipe culvert headwall-30 in | EACH A A | 4 | $4,000.00 | $1,900.00 |
| 0180 | Flume inlet type 1 | EACH A A | 1 | $6,700.00 | $12,000 |
| 0190 | Delineator for guardrail BI directional white | EACH A A | 46 | $13.58 | $15.00 |
| 0200 | Barricade-type III | EACH A A | 4 | $285.00 | $170.00 |
| 0210 | Remove pavement | SQYD A A | 30 | $25.00 | $190.00 |
| 0220 | Temp ditch | LF A A | 285 | $2.00 | $31.00 |
| 0230 | Embankment in place | CUYD A A | 25,567 | $34.00 | $40.00 |
| 0240 | Guardrail-steel W beam-S face | LF A A | 2,362.50 | $30.39 | $34.00 |
| 0250 | Guardrail terminal section no 1 | EACH A A | 5 | $86.34 | $95.00 |
| 0260 | Guardrail end treatment type 1 | EACH A A | 3 | $3,676.46 | $4,100.00 |
| 0270 | Right-of-way monument type 1 | EACH A A | 19 | $285.00 | $120.00 |
| 0280 | Witness post | EACH A A | 19 | $270.00 | $140.00 |
| 0290 | Channel lining class II | TON A A | 182 | $44.00 | $64.00 |
| 0300 | Channel lining class III | TON A A | 100 | $45.00 | $69.00 |
| 0310 | Clearing and grubbing | LS A A | 1 | $53,500 | $125,000 |
| 0320 | Temporary signs | SQFT A A | 81 | $18.00 | $20.00 |
| 0330 | Edge key | LF A A | 95 | $45.00 | $52.00 |
| 0340 | Maintain & control traffic | LS A A | 1 | $36,000 | $100,000 |
| 0350 | Portable changeable message sign | EACH A A | 2 | $4,000.00 | $9,300.00 |
| 0360 | Edgeline rumble strips | LF A A | 3,316 | $1.36 | $1.50 |
| 0370 | Staking | LS A A | 1 | $11,500 | $150,000 |
| 0380 | Erosion control blanket | SQYD A A | 162 | $4.50 | $5.00 |
| 0390 | Pave striping-temp paint-6 in | LF A A | 3,000 | $0.34 | $2.20 |
| 0400 | Pave striping-thermo-6 in W | LF A A | 3,690 | $1.35 | $11.00 |
| 0410 | Pave striping-thermo-6 in Y | LF A A | 4,100 | $1.35 | $11.00 |
| 0420 | Object marker TY 3 | EACH A A | 3 | $36.59 | $120.00 |
| 0430 | Erosion control | LS A A | 1 | $45,400 | $55,000 |
| 0440 | Turf reinforcement mat 1 | SQYD A A | 540 | $10.24 | $11.00 |
| 0450 | Turf reinforcement mat 4 | SQYD A A | 29 | $20.00 | $22.00 |
| 0460 | Barcode sign inventory | EACH A A | 4 | $1.00 | $1.10 |
| 0470 | Thrie beam guardrail transition TL-3 | EACH A A | 4 | $4,845.34 | $3,700.00 |
| 0480 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,000.00 | $8,500.00 |
| 0490 | Kytc S&F headwall-18 in | EACH A A | 2 | $2,500.00 | $1,700.00 |
| 0500 | Structure granular backfill | CUYD A A | 575 | $79.00 | $95.00 |
| 0510 | Remove structure | LS A A | 1 | $20,000 | $250,000 |
| 0520 | Armored edge for concrete | LF A A | 58 | $122.96 | $380.00 |
| 0530 | Structure excav-solid rock | CUYD A A | 38 | $316.32 | $370.00 |
| 0540 | Foundation preparation | LS A A | 1 | $13,847 | $125,000 |
| 0550 | Cyclopean stone rip rap | TON A A | 185 | $38.13 | $54.00 |
| 0560 | Crushed aggregate slope prot | TON A A | 195 | $30.82 | $65.00 |
| 0570 | Test piles | LF A A | 64 | $122.84 | $200.00 |
| 0580 | Pre-drilling for piles | LF A A | 394 | $200.28 | $280.00 |
| 0590 | Piles-steel HP12X53 | LF A A | 434 | $78.99 | $120.00 |
| 0600 | Pile points-12 in | EACH A A | 18 | $169.32 | $350.00 |
| 0610 | Concrete-class A | CUYD A A | 274.50 | $982.54 | $1,400.00 |
| 0620 | Concrete-class AA | CUYD A A | 236.20 | $1,299.86 | $1,700.00 |
| 0630 | Steel reinforcement | LB A A | 35,132 | $1.80 | $2.00 |
| 0640 | Steel reinforcement-epoxy coated | LB A A | 89,370 | $1.89 | $2.30 |
| 0650 | Precast PC I beam type 4 | LF A A | 721.40 | $758.43 | $740.00 |
| 0660 | Concrete sealing | SQFT A A | 16,453 | $1.99 | $3.70 |
| 0670 | Rail system type C412 | LF A A | 368.10 | $501.94 | $590.00 |
| 0680 | Mobilization for concrete surf treatment | LS A A | 1 | $3,252.25 | $11,000 |
| 0690 | Mobilization | LS A A | 1 | $92,000 | $230,000 |
| 0700 | Demobilization | LS A A | 1 | $55,819 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way