Scott and Murphy Inc: KYTC bid record
Scott and Murphy Inc submitted 96 bids on Kentucky Transportation Cabinet contracts in the data, from 22 NOV 2019 to 20 AUG 2026, and was the low bidder on 33 of them (34%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- Kentucky Transportation Cabinet
- Low bid volume
- $65,897,590
- Latest bid
- 20 AUG 2026
- Data through
- 22 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2019 | 1 | 1 | 100% |
| 2020 | 10 | 2 | 20% |
| 2021 | 26 | 13 | 50% |
| 2022 | 6 | 2 | 33% |
| 2023 | 19 | 7 | 37% |
| 2024 | 21 | 5 | 24% |
| 2025 | 9 | 2 | 22% |
| 2026 | 4 | 1 | 25% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 3 | 27 | 12 | 44% |
| District 2 | 22 | 7 | 32% |
| District 4 | 16 | 5 | 31% |
| District 5 | 7 | 3 | 43% |
| District 8 | 6 | 3 | 50% |
| District 1 | 5 | 2 | 40% |
| District 7 | 2 | 0 | 0% |
| District 10 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Delineator for guardrail BI directional white | EACH | 45 | 38 (84%) | $12.50 | $14.19 | |
| CL2 asph surf 0.38D PG64-22 | TON | 51 | 36 (71%) | $200.00 | $102.95 | |
| Guardrail-steel W beam-S face | LF | 41 | 35 (85%) | $36.60 | $38.00 | |
| Steel reinforcement-epoxy coated | LB | 61 | 31 (51%) | $1.75 | $2.00 | |
| CL2 asph base 1.00D PG64-22 | TON | 46 | 29 (63%) | $144.12 | $135.00 | |
| Portable changeable message sign | EACH | 58 | 28 (48%) | $1,717.50 | $1,750.00 | |
| Guardrail terminal section no 1 | EACH | 32 | 27 (84%) | $85.97 | $85.06 | |
| Asphalt seal coat | TON | 38 | 24 (63%) | $1,525.00 | $1,370.39 | |
| Test piles | LF | 38 | 23 (61%) | $114.00 | $187.47 | |
| Edge key | LF | 43 | 22 (51%) | $50.00 | $47.55 | |
| Asphalt seal aggregate | TON | 38 | 22 (58%) | $416.23 | $261.98 | |
| Asphalt material for tack | TON | 28 | 21 (75%) | $867.60 | $10.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Galusha Contracting LLC | 24 | 16 of 24 |
| Cambry Contracting Inc | 23 | 18 of 23 |
| M & M Services Co Inc | 21 | 11 of 21 |
| Jave LLC | 20 | 7 of 20 |
| Hinkle Construction Services LLC | 19 | 6 of 19 |
| Haydon Bridge Company Inc | 19 | 4 of 19 |
| Ragle Inc | 15 | 3 of 15 |
| Louisville Paving Company Inc | 14 | 4 of 14 |
| Scotty'S Contracting & Stone LLC | 10 | 7 of 10 |
| E & B Paving LLC | 9 | 2 of 9 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 20 AUG 2026 | 26-5416 | BRIDGE SUPERSTRUCTURE REPLACEMENT KY 61 | 2 of 3 | $827,319 | +1.0% | |
| 23 JUL 2026 | 26-1130 | CULVERT REPLACEMENT CULVERT REPLACEMENT ON KY 90 AT MP 10.09 | 3 of 4 | $1,313,699 | +95% | |
| 23 APR 2026 | 26-5410 | BRIDGE REPLACEMENT CR 1401 | 2 of 6 | $635,871 | +16% | |
| 29 JAN 2026 | 26-5402 | BRIDGE REPLACEMENT KY 90 | 1 of 2 | $3,721,244 | Low, 42% under the second | |
| 11 DEC 2025 | 25-5400 | BRIDGE REPLACEMENT KY 1046 | 4 of 7 | $951,364 | +17% | |
| 20 NOV 2025 | 25-5396 | BRIDGE REPLACEMENT KY 90 | 2 of 4 | $1,227,637 | +17% | |
| 20 NOV 2025 | 25-2904 | BRIDGE SUPERSTRUCTURE REPLACEMENT CR 1339 (WEST FIFTH STREET) | 4 of 4 | $1,820,718 | +84% | |
| 25 SEP 2025 | 25-5390 | BRIDGE REPLACEMENT KY 210 | 3 of 4 | $1,711,959 | +17% | |
| 25 SEP 2025 | 25-2317 | JPC PAVEMENT SCOTTSVILLE ROAD (US 231) | 2 of 3 | $325,896 | +3.0% | |
| 24 JUL 2025 | 25-5382 | BRIDGE REPLACEMENT KY 138 | 2 of 4 | $7,318,766 | +10% | |
| 24 APR 2025 | 25-5378 | District 2 | BRIDGE REPLACEMENT ROCKPORT FERRY ROAD (CR 1068) | 1 of 3 | $192,379 | Low, 56% under the second |
| 20 FEB 2025 | 25-5370 | District 3 | BRIDGE SUPERSTRUCTURE REPLACEMENT I-165 | 1 of 2 | $18,726,209 | Low, 21% under the second |
| 23 JAN 2025 | 25-2970 | District 2 | BRIDGE REPAIRS CARTER ROAD (KY 2698) | 2 of 2 | $680,582 | +34% |
| 12 DEC 2024 | 24-5369 | District 2 | BRIDGE REPLACEMENT US 60 | 2 of 3 | $2,734,648 | +7.0% |
| 12 DEC 2024 | 24-1017 | District 2 | BRIDGE REPLACEMENT KY-1033 | 4 of 5 | $1,535,592 | +32% |
| 14 NOV 2024 | 24-5367 | District 8 | BRIDGE REPLACEMENT KY 1576 | 1 of 5 | $1,111,354 | Low, 5.0% under the second |
| 14 NOV 2024 | 24-2906 | District 4 | BRIDGE WITH GRADE & DRAIN SHORT LINE PIKE (KY 1195) | 3 of 7 | $594,161 | +37% |
| 24 OCT 2024 | 24-1318 | District 2 | GRADE, DRAIN & SURFACE WITH BRIDGE HARTFORD-SEBREE ROAD (KY 136) | 1 of 2 | $9,588,072 | Low, 20% under the second |
| 24 OCT 2024 | 24-5365 | District 2 | BRIDGE REPLACEMENT KY 143 | 3 of 4 | $1,294,651 | +44% |
| 24 OCT 2024 | 24-2958 | District 4 | BRIDGE SUPERSTRUCTURE REPLACEMENT BOSTON ROAD (KY 62) | 4 of 8 | $532,379 | +16% |
| 24 OCT 2024 | 24-2957 | District 4 | BRIDGE REPAIRS BRANDENBURG ROAD (KY 259) | 6 of 7 | $1,859,378 | +31% |
| 24 OCT 2024 | 24-2962 | District 3 | BRIDGE REPLACEMENT BEE SPRINGS ROAD (KY 238) | 2 of 5 | $646,209 | 0.0% |
| 26 SEP 2024 | 24-5361 | District 2 | BRIDGE REPLACEMENT KY 812 | 2 of 3 | $1,774,656 | +29% |
| 26 SEP 2024 | 24-2955 | District 2 | BRIDGE REPAIRS CARTER ROAD (KY 2698) | 2 of 2 | $877,960 | +11% |
| 26 SEP 2024 | 24-2995 | District 3 | BRIDGE WITH GRADE, DRAIN & SURFACE STRINGTOWN FLIPPIN ROAD (KY 678) | 1 of 4 | $806,399 | Low, 2.0% under the second |
How this record was read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; KYTC's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.