KYTC contract 25-5396 bid tabulation
BRIDGE REPLACEMENT KY 90. Let by Kentucky Transportation Cabinet on November 20, 2025. 4 bids received; low bid $1,046,481 by Cambry Contracting Inc, -18% against the engineer's estimate of $1,273,655.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 NOV 2025
- Pay items
- 44
- Data through
- 22 OCT 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cambry Contracting Inc | $1,046,481 | Low | -18% |
| 2 | Scott and Murphy Inc | $1,227,637 | +17% | -4.0% |
| 3 | Jave LLC | $1,297,778 | +24% | +2.0% |
Engineer's estimate: $1,273,655.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cambry Contracting Inc | 2. Scott and Murphy Inc | 3. Jave LLC |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 948 | $39.00 | $29.99 | $40.95 |
| 0020 | Asphalt seal aggregate | TON A A | 9.62 | $800.00 | $800.00 | $840.00 |
| 0030 | Asphalt seal coat | TON A A | 1.15 | $3,500.00 | $3,500.00 | $3,675.00 |
| 0040 | CL2 asph base 0.75D PG64-22 | TON A A | 433 | $140.00 | $140.00 | $147.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 124 | $150.00 | $150.00 | $157.50 |
| 0060 | Asphalt material for tack | TON A A | 1.23 | $70.00 | $750.00 | $787.50 |
| 0070 | Dga base | TON A A | 470 | $39.00 | $29.99 | $40.95 |
| 0080 | CL2 asph base 0.75D PG64-22 | TON A A | 100 | $140.00 | $140.00 | $147.00 |
| 0090 | Delineator for guardrail BI directional white | EACH A A | 24 | $15.94 | $15.94 | $16.74 |
| 0100 | Barricade-type III | EACH A A | 2 | $150.00 | $288.91 | $105.00 |
| 0110 | Roadway excavation | CUYD A A | 260 | $50.00 | $112.59 | $49.88 |
| 0120 | Guardrail-steel W beam-S face | LF A A | 575 | $32.92 | $32.92 | $34.57 |
| 0130 | Remove guardrail | LF A A | 720 | $3.81 | $3.81 | $4.00 |
| 0140 | Guardrail end treatment type 4A | EACH A A | 2 | $3,833.74 | $3,833.74 | $4,025.43 |
| 0150 | Clearing and grubbing | LS A A | 1 | $5,000.00 | $21,062 | $22,119 |
| 0160 | Temporary signs | SQFT A A | 135 | $10.00 | $9.00 | $7.35 |
| 0170 | Object marker type 2 | EACH A A | 4 | $356.30 | $356.30 | $374.12 |
| 0180 | Edge key | LF A A | 48 | $45.00 | $45.00 | $47.25 |
| 0190 | Maintain & control traffic | LS A A | 1 | $10,000 | $12,320 | $9,035.00 |
| 0200 | Diversions (by-pass detours) | LS A A | 1 | $113,000 | $85,434 | $143,302 |
| 0210 | Portable changeable message sign | EACH A A | 2 | $2,100.00 | $3,311.96 | $3,116.40 |
| 0220 | Staking | LS A A | 1 | $5,000.00 | $6,861.60 | $6,960.00 |
| 0230 | Temp signal 2 phase | EACH A A | 1 | $1,000.00 | $15,202 | $16,800 |
| 0240 | Pave striping-temp paint-6 in | LF A A | 820 | $3.00 | $1.00 | $1.05 |
| 0250 | Pave striping-dur TY 1-6 in W | LF A A | 228 | $3.00 | $9.00 | $9.45 |
| 0260 | Pave striping-dur TY 1-6 in Y | LF A A | 30 | $3.00 | $25.00 | $26.25 |
| 0270 | Object marker TY 3 | EACH A A | 2 | $45.74 | $45.74 | $48.03 |
| 0280 | Erosion control | LS A A | 1 | $5,000.00 | $6,729.91 | $14,210 |
| 0290 | Pave mark temp paint stop bar-24 in | LF A A | 24 | $50.00 | $20.00 | $21.00 |
| 0300 | Barcode sign inventory | EACH A A | 4 | $43.55 | $328.90 | $45.73 |
| 0310 | Pave striping-spray thermo-6 in W | LF A A | 1,082 | $1.00 | $3.00 | $3.15 |
| 0320 | Pave striping-spray thermo-6 in Y | LF A A | 130 | $1.00 | $3.00 | $3.15 |
| 0330 | Thrie beam guardrail transition TL-3 | EACH A A | 4 | $3,600.00 | $3,171.50 | $3,330.08 |
| 0340 | Foundation preparation | LS A A | 1 | $25,000 | $5,393.52 | $22,832 |
| 0350 | Cyclopean stone rip rap | TON A A | 64 | $55.00 | $38.11 | $100.53 |
| 0360 | Concrete-class AA | CUYD A A | 114.70 | $1,400.00 | $1,892.47 | $1,775.96 |
| 0370 | Steel reinforcement-epoxy coated | LB A A | 50,164 | $1.65 | $1.97 | $2.23 |
| 0380 | Remove superstructure | LS A A | 1 | $62,000 | $108,100 | $99,721 |
| 0390 | Precast PC I beam type 2 | LF A A | 446.90 | $450.00 | $539.91 | $484.35 |
| 0400 | Concrete patching repair | SQFT A A | 48 | $400.00 | $281.65 | $334.08 |
| 0410 | Concrete sealing | SQFT A A | 8,360 | $1.00 | $2.03 | $3.92 |
| 0420 | Epoxy injection crack repair | LF A A | 10 | $525.00 | $87.79 | $464.00 |
| 0430 | Classic bridge rail | LF A A | 228 | $400.00 | $508.42 | $462.23 |
| 0440 | Demobilization | LS A A | 1 | $15,697 | $18,415 | $19,179 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of November 20, 2025. Compiled by Mirage Metrics.