Galusha Contracting LLC: KYTC bid record
Galusha Contracting LLC submitted 31 bids on Kentucky Transportation Cabinet contracts in the data, from 24 JUL 2020 to 23 APR 2026, and was the low bidder on 9 of them (29%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Kentucky Transportation Cabinet
- Low bid volume
- $14,745,450
- Latest bid
- 23 APR 2026
- Data through
- 22 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 4 | 0 | 0% |
| 2021 | 4 | 0 | 0% |
| 2022 | 1 | 0 | 0% |
| 2023 | 2 | 2 | 100% |
| 2024 | 15 | 5 | 33% |
| 2025 | 4 | 1 | 25% |
| 2026 | 1 | 1 | 100% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 4 | 6 | 2 | 33% |
| District 2 | 6 | 3 | 50% |
| District 3 | 5 | 1 | 20% |
| District 7 | 3 | 0 | 0% |
| District 6 | 3 | 0 | 0% |
| District 1 | 2 | 0 | 0% |
| District 5 | 2 | 1 | 50% |
| District 8 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Concrete-class A | CY | 22 | 9 (41%) | $832.50 | $1,088.01 | |
| Concrete sealing | SF | 22 | 9 (41%) | $1.98 | $3.00 | |
| Guardrail-steel W beam-S face | LF | 18 | 9 (50%) | $36.50 | $38.00 | |
| Extra length guardrail post | EACH | 9 | 9 (100%) | $30.25 | $50.00 | |
| Delineator for guardrail BI directional white | EACH | 15 | 8 (53%) | $11.16 | $14.19 | |
| Guardrail terminal section no 1 | EACH | 14 | 7 (50%) | $90.50 | $85.06 | |
| Guardrail end treatment type 7 | EACH | 10 | 7 (70%) | $1,748.50 | $1,610.68 | |
| Steel reinforcement | LB | 15 | 6 (40%) | $1.63 | $1.85 | |
| Rail system side mounted MGS | LF | 11 | 6 (55%) | $249.00 | $231.46 | |
| Steel reinforcement-epoxy coated | LB | 22 | 5 (23%) | $1.75 | $2.00 | |
| Concrete-class AA | CY | 21 | 5 (24%) | $1,821.52 | $1,716.02 | |
| Structure granular backfill | CUYD A | 7 | 5 (71%) | $72.00 | $81.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Scott and Murphy Inc | 24 | 8 of 24 |
| Hinkle Construction Services LLC | 15 | 4 of 15 |
| M & M Services Co Inc | 13 | 4 of 13 |
| Cambry Contracting Inc | 12 | 7 of 12 |
| Jave LLC | 12 | 1 of 12 |
| Ragle Inc | 9 | 2 of 9 |
| Haydon Bridge Company Inc | 8 | 1 of 8 |
| Todd Johnson Contracting Inc | 7 | 4 of 7 |
| Central Bridge Co LLC | 5 | 2 of 5 |
| Frederick & May Construction Co | 4 | 2 of 4 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 23 APR 2026 | 26-5410 | BRIDGE REPLACEMENT CR 1401 | 1 of 6 | $547,195 | Low, 16% under the second | |
| 11 DEC 2025 | 25-5400 | BRIDGE REPLACEMENT KY 1046 | 2 of 7 | $872,540 | +7.0% | |
| 24 JUL 2025 | 25-5382 | BRIDGE REPLACEMENT KY 138 | 1 of 4 | $6,633,271 | Low, 10% under the second | |
| 20 MAR 2025 | 25-5374 | District 6 | BRIDGE REPLACEMENT KY 36 | 3 of 4 | $2,985,258 | +4.0% |
| 20 FEB 2025 | 25-5371 | District 5 | BRIDGE REPLACEMENT VARIOUS ROUTES IN FRANKLIN COUNTY | 2 of 3 | $4,586,101 | +1.0% |
| 12 DEC 2024 | 24-5369 | District 2 | BRIDGE REPLACEMENT US 60 | 1 of 3 | $2,544,813 | Low, 7.0% under the second |
| 12 DEC 2024 | 24-1017 | District 2 | BRIDGE REPLACEMENT KY-1033 | 2 of 5 | $1,227,101 | +6.0% |
| 14 NOV 2024 | 24-5367 | District 8 | BRIDGE REPLACEMENT KY 1576 | 2 of 5 | $1,168,066 | +5.0% |
| 14 NOV 2024 | 24-2943 | District 7 | BRIDGE REPLACEMENT BIRDIE ROAD (KY 395) | 4 of 9 | $805,132 | +13% |
| 14 NOV 2024 | 24-2906 | District 4 | BRIDGE WITH GRADE & DRAIN SHORT LINE PIKE (KY 1195) | 2 of 7 | $550,340 | +27% |
| 24 OCT 2024 | 24-5365 | District 2 | BRIDGE REPLACEMENT KY 143 | 1 of 4 | $897,986 | Low, 28% under the second |
| 24 OCT 2024 | 24-2958 | District 4 | BRIDGE SUPERSTRUCTURE REPLACEMENT BOSTON ROAD (KY 62) | 1 of 8 | $457,163 | Low, 8.0% under the second |
| 24 OCT 2024 | 24-2957 | District 4 | BRIDGE REPAIRS BRANDENBURG ROAD (KY 259) | 2 of 7 | $1,576,918 | +11% |
| 26 SEP 2024 | 24-5361 | District 2 | BRIDGE REPLACEMENT KY 812 | 1 of 3 | $1,370,851 | Low, 29% under the second |
| 26 SEP 2024 | 24-2995 | District 3 | BRIDGE WITH GRADE, DRAIN & SURFACE STRINGTOWN FLIPPIN ROAD (KY 678) | 2 of 4 | $825,018 | +2.0% |
| 22 AUG 2024 | 24-2952 | District 6 | BRIDGE REPLACEMENT ELLISTON-MT. ZION ROAD (KY 1942) | 4 of 7 | $1,018,207 | +13% |
| 18 JUL 2024 | 24-5358 | District 6 | BRIDGE REPLACEMENT KY 491 | 2 of 8 | $753,739 | +4.0% |
| 23 MAY 2024 | 24-5349 | District 4 | BRIDGE REPLACEMENT VARIOUS ROUTES IN DISTRICT 4 | 1 of 6 | $1,518,227 | Low, 2.0% under the second |
| 22 FEB 2024 | 24-5337 | District 4 | BRIDGE REPLACEMENT US 62 | 2 of 6 | $2,410,595 | +1.0% |
| 25 JAN 2024 | 24-5334 | District 2 | BRIDGE REPLACEMENT KY 70 | 3 of 4 | $1,620,431 | +11% |
| 16 NOV 2023 | 23-5327 | District 3 | BRIDGE REPLACEMENT OLD BUCK CREEK ROAD (CR 1239) | 1 of 3 | $439,941 | Low, 5.0% under the second |
| 26 JAN 2023 | 23-5253 | District 5 | BRIDGE REPLACEMENT CR 1007 | 1 of 5 | $336,003 | Low, 13% under the second |
| 28 APR 2022 | 22-5238 | District 3 | BRIDGE REPLACEMENT CR 1108 | 3 of 4 | $1,090,765 | +24% |
| 22 OCT 2021 | 21-5212 | District 2 | BRIDGE REPLACEMENT WALNUT STREET - US 41 ALT | 2 of 4 | $2,372,838 | +5.0% |
| 23 JUL 2021 | 21-5187 | District 1 | BRIDGE REPLACEMENT KY 91 | 2 of 4 | $1,124,623 | +20% |
How this record was read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; KYTC's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.