KYTC letting results, November 16, 2023
42 contracts let by Kentucky Transportation Cabinet on November 16, 2023, $68,190,956 in low bids, a median of 2 bidders per contract. On the 42 with an engineer's estimate, the low bid came in under it 26 times; median low bid -4.0% against the estimate.
- Owner
- Kentucky Transportation Cabinet
- Contracts
- 42
- Low bids, total
- $68,190,956
- Data through
- 22 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 23-2996 | BRIDGE REPAIR MISCELLANEOUS WORK BLUEGRASS PARKWAY (BG 9002) | District 7 | 3 | M & M Services Co Inc | $10,643,787 | $12,208,243 | +15% | +71% | KYTC |
| 23-2477 | JPC PAVEMENT REPAIRS - DIAMOND GRINDING I-275 | District 6 | 3 | Mac Construction & Excavating Inc | $7,139,275 | $7,370,577 | +3.0% | +19% | KYTC |
| 23-5325 | BRIDGE REPLACEMENT VARIOUS ROUTES | District 2 | 2 | Scott and Murphy Inc | $6,931,624 | $7,078,744 | +2.0% | -6.0% | KYTC |
| 23-1109 | ASPHALT REHAB WITH GRADE & DRAIN BILLTOWN ROAD (KY 1819) | District 5 | 5 | Flynn Brothers Contracting Inc | $5,114,852 | $5,725,000 | +12% | -5.0% | KYTC |
| 23-5324 | BRIDGE REPLACEMENT KY 502 | District 2 | 3 | Haydon Bridge Company Inc | $4,205,553 | $4,870,980 | +16% | 0.0% | KYTC |
| 23-4417 | GRADE & DRAIN WITH ASPHALT SURFACE LANCASTER/DANVILLE ROAD (KY 52) | District 7 | 1 | The Allen Company Inc | $3,924,534 | -2.0% | KYTC | ||
| 23-4017 | SIGNS VARIOUS ROUTES IN DISTRICT 5 | District 5 | 1 | Eden Fence Inc | $3,742,131 | +8.0% | KYTC | ||
| 23-4420 | GRADE & DRAIN WITH ASPHALT SURFACE STAMPING GROUND ROAD (KY 227) | District 7 | 1 | Hinkle Construction Services LLC | $2,198,000 | +27% | KYTC | ||
| 23-1045 | ASPHALT REHAB INTERSTATE/PARKWAY JULIAN CARROLL PARKWAY(PW-9003) | District 1 | 1 | Jim Smith Contracting Company LLC | $2,092,916 | -16% | KYTC | ||
| 23-4018 | SIGNS VARIOUS ROUTES IN DISTRICT 6 | District 6 | 1 | George B Stone Co LLC | $2,000,000 | -3.0% | KYTC | ||
| 23-2951 | BRIDGE PAINTING & CLEANING VARIOUS ROUTES IN CARTER COUNTY ~ 3 LOCATIONS | District 9 | 8 | Euro Paint LLC | $1,859,501 | $2,105,600 | +13% | -30% | KYTC |
| 23-2478 | ASPHALT PAVEMENT & ROADWAY REHAB MOREHEAD CONNECTOR (KY 32) | District 9 | 1 | Hinkle Contracting Company LLC | $1,574,119 | +8.0% | KYTC | ||
| 23-2455 | PAVEMENT (WITH ALTERNATES) DAVIESS COUNTY (US 60 & KY 603) | District 2 | 2 | Yager Materials Corp | $1,438,578 | $1,527,379 | +6.0% | +5.0% | KYTC |
| 23-1336 | WIDENING US 68 | District 3 | 1 | Scotty'S Contracting & Stone LLC | $1,352,143 | -10% | KYTC | ||
| 23-2446 | PAVEMENT (WITH ALTERNATES) MURRAY TO FARMINGTON ROAD (KY 121) | District 1 | 2 | Jim Smith Contracting Company LLC | $1,039,426 | $1,442,705 | +39% | -17% | KYTC |
| 23-2954 | BRIDGE REPAIR MISCELLANEOUS WORK MILTON-MADISON BRIDGE (US 421) | District 5 | 2 | The Truesdell Corporation | $994,994 | $1,034,033 | +4.0% | -61% | KYTC |
| 23-3135 | ASPHALT RESURFACING VARIOUS ROADS IN HARLAN CO | District 11 | 1 | Mountain Enterprises Inc | $925,998 | +20% | KYTC | ||
| 23-2448 | PAVEMENT (WITH ALTERNATES) KNOX COUNTY (KY 11 & KY 229) | District 11 | 2 | Strawser Construction Inc | $771,936 | $878,613 | +14% | -6.0% | KYTC |
| 23-2469 | PAVEMENT (WITH ALTERNATES) FALLSBURG TO WEBBVILLE ROAD (KY 1) | District 12 | 2 | Strawser Construction Inc | $758,153 | $771,210 | +2.0% | -3.0% | KYTC |
| 23-2466 | PAVEMENT (WITH ALTERNATES) US 68 BYPASS (US 68) | District 3 | 2 | Scotty'S Contracting & Stone LLC | $674,536 | $772,431 | +15% | +11% | KYTC |
| 23-5328 | BRIDGE REPLACEMENT KY 525 | District 1 | 3 | Jim Smith Contracting Company LLC | $658,768 | $747,065 | +13% | -20% | KYTC |
| 23-1044 | GRADE & DRAIN WITH ASPHALT SURFACE KY-1581 | District 2 | 3 | Scott and Murphy Inc | $648,735 | $690,999 | +7.0% | -13% | KYTC |
| 23-2090 | PAVEMENT (WITH ALTERNATES) WEST LAUREL ROAD (KY 192) | District 11 | 2 | L-M Asphalt Partners LTD D/B/A Ats Construction | $607,418 | $675,183 | +11% | +8.0% | KYTC |
| 23-2459 | MICROSURFACING TAYLOR MILL ROAD (KY 16) | District 6 | 1 | Strawser Construction Inc | $580,169 | -21% | KYTC | ||
| 23-3134 | ASPHALT RESURFACING VARIOUS ROADS IN CLARK COUNTY | District 7 | 1 | The Allen Company Inc | $571,680 | +8.0% | KYTC | ||
| 23-2959 | BRIDGE REPLACEMENT CARRSVILLE ROAD (KY 135) | District 1 | 2 | Jim Smith Contracting Company LLC | $546,398 | $757,476 | +39% | -19% | KYTC |
| 23-2468 | PAVEMENT (WITH ALTERNATES) OLD MILL ROAD (KY 1638) | District 4 | 4 | Louisville Paving Company Inc | $525,976 | $538,244 | +2.0% | -19% | KYTC |
| 23-2475 | GUARDRAIL VARIOUS GUARDRAIL PROJECTS | District 12 | 1 | George B Stone Co LLC | $524,850 | -9.0% | KYTC | ||
| 23-2470 | PAVEMENT (WITH ALTERNATES) DENNSITON TO FRENCHBURG (US 460) | District 10 | 2 | Walker Construction & Materials LLC | $446,460 | $483,213 | +8.0% | -6.0% | KYTC |
| 23-5327 | BRIDGE REPLACEMENT OLD BUCK CREEK ROAD (CR 1239) | District 3 | 3 | Galusha Contracting LLC | $439,941 | $463,433 | +5.0% | -19% | KYTC |
| 23-2473 | GUARDRAIL VARIOUS GUARDRAIL PROJECTS | District 11 | 1 | George B Stone Co LLC | $434,453 | -12% | KYTC | ||
| 23-2445 | PAVEMENT (WITH ALTERNATES) WYOMING ROAD (KY 111) | District 9 | 1 | Walker Construction & Materials LLC | $378,411 | -9.0% | KYTC | ||
| 23-3136 | ASPHALT RESURFACING VARIOUS ROADS IN ROCKCASTLE CO | District 8 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $375,909 | +16% | KYTC | ||
| 23-2463 | PAVEMENT (WITH ALTERNATES) MAYSVILLE ROAD (KY 11) | District 9 | 3 | H G Mays Corporation | $374,753 | $495,286 | +32% | -26% | KYTC |
| 23-2464 | PAVEMENT (WITH ALTERNATES) BOONEVILLE TO EVERSOLE (KY 28) | District 10 | 2 | Hinkle Contracting Company LLC | $311,887 | $367,103 | +18% | +5.0% | KYTC |
| 23-2450 | PAVEMENT (WITH ALTERNATES) BRADFORDSVILLE ROAD (KY 49) | District 4 | 2 | Haydon Materials LLC | $290,484 | $357,470 | +23% | 0.0% | KYTC |
| 23-2906 | BRIDGE REPAIR MISCELLANEOUS WORK VERSAILLES ROAD (US 62) | District 7 | 3 | M & M Services Co Inc | $285,301 | $300,000 | +5.0% | -1.0% | KYTC |
| 23-2447 | PAVEMENT (WITH ALTERNATES) N. 25TH STREET (KY 2402) | District 11 | 1 | Hinkle Contracting Company LLC | $276,424 | +12% | KYTC | ||
| 23-2458 | PAVEMENT (WITH ALTERNATES) BRACKEN COUNTY (KY 1159 & 1289) | District 6 | 3 | Mago Construction Company LLC | $218,103 | $221,133 | +1.0% | -24% | KYTC |
| 23-4504 | SIGNS INTERSTATE 69 (I-69) | District 1 | 1 | Eden Fence Inc | $191,495 | -4.0% | KYTC | ||
| 23-2454 | PAVEMENT (WITH ALTERNATES) MARION ROAD (KY 70) | District 2 | 1 | Rogers Group Inc | $92,694 | +23% | KYTC | ||
| 23-4505 | SIGNS US HIGHWAY 31W (US 31W) | District 3 | 1 | Davis H Elliot Construction Company Inc | $28,590 | -52% | KYTC |
Gap is the second bid over the low bid. Where a contract shows fewer bids than KYTC received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.