Rogers Group Inc: KYTC bid record

Rogers Group Inc submitted 195 bids on Kentucky Transportation Cabinet contracts in the data, from 22 NOV 2019 to 22 OCT 2026, and was the low bidder on 141 of them (72%). When it was not low, its total sat a median +9.0% above the low bid.

Owner
Kentucky Transportation Cabinet
Low bid volume
$190,781,547
Latest bid
22 OCT 2026
Data through
22 OCT 2026
195Bids
141Low bids
72Win rate, percent
+9.0%Median gap to the low bid when not low, 54 bids

By year

YearBidsLow bidsWin rate
201922100%
202018844%
2021402563%
2022464087%
2023272385%
2024261973%
2025151387%
2026211152%
Rogers Group Inc, KYTC: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 21299473%
District 1342779%
Rogers Group Inc, KYTC: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Temporary signsSF8758 (67%)$6.79$6.50
Fuel adjustmentDOL4545 (100%)$1.00$1.00
Asphalt adjustmentDOL4545 (100%)$1.00$1.00
Pave striping-perm paint-4 inLF4841 (85%)$0.29$0.29
Pave striping-temp paint-4 inLF5340 (75%)$0.27$0.20
Pave marking-thermo stop bar-24INLF4840 (83%)$16.00$14.00
Leveling & wedging PG64-22TON6233 (53%)$73.80$94.00
Edgeline rumble stripsLF4730 (64%)$0.30$0.26
CL2 asph surf 0.38D PG64-22TON5328 (53%)$70.56$102.95
Dga baseTON5327 (51%)$32.55$45.00
Maintain & control trafficLS A A3527 (77%)$4,066.94$10,625
Pave marking-thermo curv arrowEACH3226 (81%)$112.50$125.00
Rogers Group Inc, KYTC: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
E & B Paving LLC3612 of 36
Scotty'S Contracting & Stone LLC2618 of 26
RB Paving and Construction LLC Wos Stonepoint Materials LLC219 of 21
Strawser Construction Inc121 of 12
RB Paving and Construction LLC115 of 11
Murray Paving Inc105 of 10
Strawser Construction Inc & Subsidiaries100 of 10
American Pavements Inc90 of 9
Missouri Petroleum Products Company LLC70 of 7
J H Rudolph & Co Inc71 of 7
Rogers Group Inc, KYTC: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
22 OCT 202626-3042ASPHALT RESURFACING EMPIRE RD (KY 1296)1 of 2$341,816Low, 2.0% under the second
22 OCT 202626-3060ASPHALT RESURFACING VARIOUS ROAD IN UNION CO1 of 2$738,868Low, 6.0% under the second
22 OCT 202626-3066ASPHALT RESURFACING VARIOUS ROADS IN WEBSTER CO2 of 3$1,353,764+11%
03 SEP 202626-2039ASPHALT RESURFACING GREENVILLE ROAD (US 62)1 of 2$1,109,403Low, 13% under the second
03 SEP 202626-2025ASPHALT RESURFACING UNIONTOWN TO MORGANFIELD ROAD (KY 1179)2 of 2$410,115+1.0%
03 SEP 202626-2046ASPHALT RESURFACING MORGANFIELD TO CORYDON ROAD (US 60)1 of 2$2,223,696Low, 7.0% under the second
03 SEP 202626-2019ASPHALT RESURFACING GATE 7 ROAD (KY 788)1 of 1$380,299Low
20 AUG 202626-2021ASPHALT RESURFACING HOUSE BRIDGE ROAD (KY 1557)1 of 3$355,873Low, 1.0% under the second
20 AUG 202626-2026ASPHALT RESURFACING MAIN STREET (KY 120)1 of 2$566,700Low, 3.0% under the second
20 AUG 202626-2027ASPHALT RESURFACING DIXON TO SEBREE ROAD (KY 132)2 of 3$628,239+2.0%
20 AUG 202626-3018ASPHALT RESURFACING KY 1078 (KY 1078)2 of 3$398,181+3.0%
20 AUG 202626-3021ASPHALT RESURFACING VARIOUS COUNTY ROADS IN WEBSTER CO2 of 3$407,762+1.0%
21 MAY 202626-3014ASPHALT RESURFACING VARIOUS ROADS IN UNION CO1 of 2$545,635Low, 19% under the second
26 MAR 202626-1506ASPHALT SURFACE WITH GRADE & DRAIN PEMBROKE OAK GROVE RD. (KY 115)2 of 2$7,623,145+2.0%
26 MAR 202626-2168PAVEMENT (WITH ALTERNATES) OLD BURKESVILLE ROAD (KY 1590)3 of 3$750,451+21%
26 MAR 202626-2076ASPHALT RESURFACING SHAWNEETOWN TO MORGANFIELD ROAD (KY 56)1 of 2$389,055Low, 2.0% under the second
19 FEB 202626-2018ASPHALT RESURFACING S VIRGINIA ST/S MAIN ST (US 41)1 of 1$385,904Low
19 FEB 202626-2110ASPHALT RESURFACING HALES HIGHWAY / MAIN STREET (KY 379)2 of 2$1,577,472+22%
19 FEB 202626-2098PAVEMENT (WITH ALTERNATES) BYPASS ROAD (US 68)1 of 4$1,218,556Low, 2.0% under the second
19 FEB 202626-3012ASPHALT RESURFACING KY 416 (KY 416)2 of 3$280,653+18%
19 FEB 202626-2038ASPHALT RESURFACING HENDERSON COUNTY (US 41A & KY 136)3 of 3$915,467+15%
25 SEP 202525-1020GRADE & DRAIN WITH ASPHALT SURFACE BREATHITT PARKWAY(PW-9004)1 of 2$17,013,946Low, 3.0% under the second
25 SEP 202525-2355ASPHALT RESURFACING ALBANY TO JAMESTOWN ROAD (US 127)2 of 2$1,129,058+13%
21 AUG 202525-1903INTERSTATE RESURFACING & REHAB I-24 PAVEMENT REHABILITATION1 of 1$26,076,729Low
21 AUG 202525-2331ASPHALT RESURFACING MAIN STREET (US 68X)1 of 1$681,815Low
Rogers Group Inc: latest KYTC bids in the data

How this record was read

KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; KYTC's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way