ASPHALT RESURFACING KY 416 (KY 416). Let by Kentucky Transportation Cabinet on February 19, 2026. 3 bids received; low bid $238,750 by Scotty'S Contracting & Stone LLC, -29% against the engineer's estimate of $336,729.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 19 FEB 2026
- Pay items
- 12
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $238,750 | Low | -29% |
| 2 | Rogers Group Inc | $280,653 | +18% | -17% |
| 3 | E & B Paving LLC | $289,568 | +21% | -14% |
Engineer's estimate: $336,729.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Rogers Group Inc | 3. E & B Paving LLC |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 400 | $45.71 | $46.96 | $58.50 |
| 0020 | Leveling & wedging PG64-22 | TON A A | 313 | $91.40 | $100.17 | $111.00 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A A | 1,830 | $83.93 | $99.11 | $99.00 |
| 0040 | Asphalt material for tack | TON A A | 15 | $489.99 | $909.19 | $550.00 |
| 0050 | Temporary signs | SQFT A A | 190 | $5.74 | $8.78 | $8.48 |
| 0060 | Maintain & control traffic | LS A A | 1 | $7,653.82 | $3,250.41 | $9,000.00 |
| 0070 | Mobilization for mill & text | LS A A | 1 | $3,659.64 | $952.61 | $6,200.00 |
| 0080 | Asphalt pave milling & texturing | TON A A | 150 | $43.89 | $77.05 | $54.00 |
| 0090 | Pave striping-temp paint-4 in | LF A A | 15,000 | $0.01 | $0.30 | $0.30 |
| 0100 | Pave striping-perm paint-4 in | LF A A | 25,000 | $0.33 | $0.33 | $0.33 |
| 0110 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 | $1.00 | $1.00 |
| 0120 | Demobilization | LS A A | 1 | $3,528.33 | $5,326.75 | $4,343.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of February 19, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.