KYTC contract 25-1020 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE BREATHITT PARKWAY(PW-9004). Let by Kentucky Transportation Cabinet on September 25, 2025. 2 bids received; low bid $17,013,946 by Rogers Group Inc, -1.5% against the engineer's estimate of $17,269,609.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 SEP 2025
- Pay items
- 152
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rogers Group Inc | $17,013,946 | Low | -1.0% |
| 2 | Cleary Construction Inc | $17,450,000 | +3.0% | +1.0% |
Engineer's estimate: $17,269,609.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rogers Group Inc | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 30,393 | $35.88 | $28.00 |
| 0020 | Asphalt seal aggregate | TON A A | 215.59 | $123.99 | $126.97 |
| 0030 | Asphalt seal coat | TON A A | 25.90 | $1,235.66 | $1,265.34 |
| 0040 | Leveling & wedging PG76-22 | TON A A | 1,289 | $116.86 | $120.88 |
| 0050 | CL3 asph base 1.00D PG64-22 | TON A A | 1,793 | $118.15 | $122.19 |
| 0060 | CL4 asph base 1.00D PG64-22 | TON A A | 12,119 | $90.24 | $93.62 |
| 0070 | CL4 asph base 1.00D PG76-22 | TON A A | 3,180 | $104.04 | $107.75 |
| 0080 | CL3 asph surf 0.50B PG64-22 | TON A A | 703 | $140.44 | $145.02 |
| 0090 | CL4 asph surf 0.50A PG76-22 | TON A A | 3,238 | $157.00 | $161.97 |
| 0100 | CL3 asph surf 0.38B PG64-22 | TON A A | 1,392 | $149.27 | $154.07 |
| 0110 | Asphalt pave milling & texturing | TON A A | 3,485 | $19.05 | $20.01 |
| 0120 | CL4 asph surf 0.38B PG 64-22 | TON A A | 1,266 | $137.58 | $142.09 |
| 0130 | Asphalt material for tack non-tracking | TON A A | 41.47 | $1,224.86 | $1,254.29 |
| 0140 | Crushed aggregate size no 2 | TON A A | 71,875 | $37.07 | $27.65 |
| 0150 | Crushed aggregate size no 23 | TON A A | 950 | $38.57 | $27.75 |
| 0160 | Flume inlet type 2 | EACH A A | 4 | $6,700.00 | $7,000.00 |
| 0170 | Standard header curb | LF A A | 20 | $75.00 | $300.00 |
| 0180 | Delineator for guardrail BI directional white | EACH A A | 95 | $16.19 | $12.00 |
| 0190 | Relocate temp conc barrier | LF A A | 13,090 | $11.16 | $8.00 |
| 0193 | Queue warning PCMS | MONT A A | 24 | $693.24 | $530.00 |
| 0196 | Queue warning portable radar sensors | MONT A A | 24 | $311.96 | $238.50 |
| 0200 | Barricade-type III | EACH A A | 30 | $347.73 | $159.00 |
| 0210 | Remove pavement | SQYD A A | 9,610 | $8.95 | $20.00 |
| 0220 | Temp ditch | LF A A | 8,336 | $0.01 | $1.00 |
| 0230 | Clean temp ditch | LF A A | 4,168 | $0.01 | $0.01 |
| 0240 | Embankment in place | CUYD A A | 104,769 | $17.57 | $20.50 |
| 0250 | Water | MGAL A A | 270 | $0.01 | $0.01 |
| 0260 | Fence-woven wire type 1 | LF A A | 1,355 | $10.41 | $10.00 |
| 0270 | Guardrail-steel W beam-S face | LF A A | 1,925 | $33.96 | $35.00 |
| 0280 | Guardrail end treatment type 1 | EACH A A | 6 | $3,698.29 | $4,000.00 |
| 0290 | Guardrail end treatment type 2M | EACH A A | 2 | $1,899.86 | $1,500.00 |
| 0300 | Remove guardrail | LF A A | 6,168 | $3.87 | $2.00 |
| 0310 | Remove concrete masonry | CUYD A A | 121.60 | $942.00 | $1,380.00 |
| 0320 | Cap inlet | SQYD A A | 1 | $1,458.50 | $3,000.00 |
| 0330 | Channel lining class II | TON A A | 6,333 | $53.45 | $60.00 |
| 0340 | Channel lining class III | TON A A | 2,726 | $58.34 | $65.00 |
| 0350 | Clearing and grubbing | LS A A | 1 | $180,998 | $260,000 |
| 0360 | Concrete-class B | CUYD A A | 2.75 | $2,015.88 | $1,000.00 |
| 0370 | Temporary signs | SQFT A A | 1,500 | $9.00 | $9.54 |
| 0380 | Fabric-geotextile class 1 | SQYD A A | 123,126 | $2.25 | $2.50 |
| 0390 | Fabric-geotextile class 1A | SQYD A A | 108,500 | $3.34 | $3.50 |
| 0400 | Maintain & control traffic | LS A A | 1 | $637,098 | $400,000 |
| 0410 | Portable changeable message sign | EACH A A | 16 | $4,054.81 | $8,904.00 |
| 0420 | Mobilization for mill & text | LS A A | 1 | $3,000.00 | $7,500.00 |
| 0430 | Safeloading | CUYD A A | 4 | $628.62 | $380.80 |
| 0440 | Shoulder rumble strips | LF A A | 47,080 | $0.37 | $0.27 |
| 0450 | Temp silt fence | LF A A | 8,336 | $2.51 | $3.75 |
| 0460 | Silt trap type A | EACH A A | 52 | $322.29 | $300.00 |
| 0470 | Silt trap type B | EACH A A | 52 | $210.11 | $150.00 |
| 0480 | Silt trap type C | EACH A A | 52 | $219.04 | $300.00 |
| 0490 | Clean silt trap type A | EACH A A | 52 | $68.37 | $0.01 |
| 0500 | Clean silt trap type B | EACH A A | 52 | $69.74 | $0.01 |
| 0510 | Clean silt trap type C | EACH A A | 52 | $70.44 | $0.01 |
| 0520 | Staking | LS A A | 1 | $154,882 | $225,000 |
| 0530 | Arrow panel | EACH A A | 4 | $8,145.59 | $3,021.00 |
| 0535 | Masonry coating | SQYD A A | 981 | $12.00 | $40.00 |
| 0540 | Conc barrier wall type 9T | LF A A | 13,090 | $36.51 | $55.00 |
| 0550 | Erosion control blanket | SQYD A A | 89,077 | $3.50 | $1.73 |
| 0560 | Temp mulch | SQYD A A | 167,787 | $0.42 | $0.28 |
| 0570 | Temp seeding and protection | SQYD A A | 125,840 | $0.43 | $0.34 |
| 0580 | Initial fertilizer | TON A A | 13 | $1,448.16 | $990.00 |
| 0590 | Maintenance fertilizer | TON A A | 7.80 | $1,448.16 | $990.00 |
| 0600 | Seeding and protection | SQYD A A | 241,351 | $0.70 | $0.55 |
| 0610 | Agricultural limestone | TON A A | 156 | $87.45 | $98.00 |
| 0620 | Pave striping-temp paint-6 in | LF A A | 55,000 | $0.30 | $0.30 |
| 0630 | Pave striping-thermo-6 in W | LF A A | 32,087 | $1.45 | $1.45 |
| 0640 | Pave striping-thermo-6 in Y | LF A A | 22,172 | $1.45 | $1.45 |
| 0650 | Pave striping-thermo-12 in W | LF A A | 3,923 | $2.15 | $2.15 |
| 0660 | Pave striping-thermo-12 in Y | LF A A | 181 | $2.20 | $2.20 |
| 0670 | Pave marking-thermo stop bar-24IN | LF A A | 124 | $20.00 | $20.00 |
| 0680 | Pave marking-thermo cross-hatch | SQFT A A | 3,841 | $7.50 | $7.50 |
| 0690 | Pave marking-thermo curv arrow | EACH A A | 9 | $120.00 | $120.00 |
| 0700 | Inlaid pavement marker-MW | EACH A A | 219 | $24.00 | $24.00 |
| 0710 | Inlaid pavement marker-by | EACH A A | 235 | $24.00 | $24.00 |
| 0720 | Inlaid pavement marker-B W/R | EACH A A | 92 | $24.00 | $24.00 |
| 0730 | Inlaid pavement marker-B Y/R | EACH A A | 59 | $24.00 | $24.00 |
| 0740 | Concrete-class A | CUYD A A | 2 | $761.82 | $938.18 |
| 0750 | Crash cushion TY 6 class B TL3 | EACH A A | 14 | $6,240.98 | $4,105.00 |
| 0760 | Fuel adjustment | DOLL A A | 107,913 | $1.00 | $1.00 |
| 0770 | Asphalt adjustment | DOLL A A | 111,295 | $1.00 | $1.00 |
| 0780 | Joint adhesive | LF A A | 14,503 | $1.00 | $1.00 |
| 0790 | Temporary pipe | LF A A | 250 | $117.29 | $110.00 |
| 0800 | Object marker TY 3 | EACH A A | 6 | $46.00 | $50.00 |
| 0810 | Sawcut pavement | LF A A | 16,203 | $1.69 | $2.00 |
| 0820 | Longitudinal edge key | LF A A | 14,503 | $3.24 | $2.56 |
| 0830 | G/R steel W beam-S face (7 FT post) | LF A A | 3,012.50 | $35.37 | $34.00 |
| 0840 | Water blasting existing stripe | LF A A | 10,000 | $0.76 | $0.76 |
| 0850 | Bridge barrier retrofit | LF A A | 1,074.30 | $350.00 | $645.00 |
| 0860 | Pave stripe-wet ref tape-6 in Y | LF A A | 316 | $10.00 | $10.00 |
| 0870 | Pave stripe-wet ref tape-6 in W | LF A A | 627 | $10.00 | $10.00 |
| 0880 | Object marker type 1 | EACH A A | 14 | $358.76 | $200.00 |
| 0890 | Pave mark thermo-wrong way arrow | EACH A A | 4 | $155.00 | $155.00 |
| 0900 | Thrie beam guardrail transition TL-3 | EACH A A | 8 | $5,148.06 | $3,700.00 |
| 0910 | Portable queue warning alert system | MONT A A | 7 | $1,816.29 | $1,388.60 |
| 0920 | Thrie beam bullnose terminal | EACH A A | 2 | $26,222 | $23,500 |
| 0930 | Electronic delivery MGMT system - agg | LS A A | 1 | $1.00 | $1.00 |
| 0940 | Crushed aggregate size no 2 | TON A A | 31 | $74.86 | $200.00 |
| 0950 | Culvert pipe-18 in | LF A A | 202 | $134.05 | $150.00 |
| 0960 | Culvert pipe-24 in | LF A A | 238 | $143.38 | $165.00 |
| 0970 | Culvert pipe-30 in | LF A A | 91 | $171.05 | $200.00 |
| 0980 | Culvert pipe-36 in | LF A A | 108 | $231.63 | $215.00 |
| 0990 | Culvert pipe-42 in | LF A A | 231 | $213.82 | $235.00 |
| 1000 | Culvert pipe-48 in | LF A A | 81 | $341.97 | $265.00 |
| 1010 | Storm sewer pipe-18 in | LF A A | 614 | $118.19 | $105.00 |
| 1020 | Perforated pipe-4 in | LF A A | 7,705 | $14.74 | $30.00 |
| 1030 | Non-perforated pipe-4 in | LF A A | 3,112 | $14.74 | $31.00 |
| 1040 | Inspect & certify edge drain system | LS A A | 1 | $3,400.00 | $5,000.00 |
| 1050 | Perf pipe headwall TY 1-4 in | EACH A A | 8 | $580.65 | $1,650.00 |
| 1060 | Perf pipe headwall TY 3-4 in | EACH A A | 23 | $882.61 | $1,650.00 |
| 1070 | Pipe culvert headwall-18 in | EACH A A | 1 | $1,693.51 | $3,500.00 |
| 1080 | Pipe culvert headwall-24 in | EACH A A | 2 | $1,808.25 | $4,000.00 |
| 1090 | Pipe culvert headwall-36 in | EACH A A | 1 | $3,063.25 | $4,500.00 |
| 1100 | Pipe culvert headwall-42 in | EACH A A | 2 | $3,980.05 | $5,500.00 |
| 1110 | Pipe culvert headwall-48 in | EACH A A | 3 | $4,282.02 | $6,500.00 |
| 1120 | S & F box inlet-outlet-18 in | EACH A A | 8 | $3,244.43 | $4,500.00 |
| 1130 | S & F box inlet-outlet-24 in | EACH A A | 4 | $5,187.92 | $6,000.00 |
| 1140 | S & F box inlet-outlet-30 in | EACH A A | 3 | $6,951.41 | $8,500.00 |
| 1150 | S & F box inlet-outlet-36 in | EACH A A | 2 | $10,102 | $12,000 |
| 1160 | Drop box inlet type 1 | EACH A A | 7 | $6,414.54 | $12,500 |
| 1170 | Drop box inlet type 10 | EACH A A | 1 | $7,388.20 | $7,500.00 |
| 1180 | Fabric-geotextile class 2 for pipe | SQYD A A | 2,147 | $2.00 | $2.00 |
| 1190 | Concrete-class A | CUYD A A | 34.54 | $534.51 | $600.00 |
| 1200 | Bore and jack pipe-24 in | LF A A | 101 | $707.73 | $875.00 |
| 1210 | Pipeline inspection | LF A A | 1,565 | $4.35 | $2.35 |
| 1220 | SBM aluminum panel signs | SQFT A A | 697.50 | $40.65 | $35.00 |
| 1230 | SBM alum sheet signs .080 in | SQFT A A | 271 | $46.21 | $35.00 |
| 1240 | SBM alum sheet signs .125 in | SQFT A A | 723 | $47.86 | $35.00 |
| 1250 | Steel post type 1 | LF A A | 2,553 | $31.61 | $35.00 |
| 1260 | Steel post mile markers | EACH A A | 2 | $396.14 | $500.00 |
| 1270 | GMSS galv steel type C | LB A A | 3,640 | $9.09 | $8.00 |
| 1280 | Rem overhead sign support STR | EACH A A | 2 | $2,763.35 | $10,000 |
| 1290 | Remove sign support beam | EACH A A | 4 | $184.22 | $1,000.00 |
| 1300 | Class A concrete for signs | CUYD A A | 13.20 | $1,654.37 | $1,000.00 |
| 1310 | Remove & relocate signs | EACH A A | 4 | $699.56 | $1,000.00 |
| 1320 | GMSS type D | EACH A A | 16 | $373.73 | $850.00 |
| 1330 | Rem sign bridge mount attachment | EACH A A | 2 | $2,947.57 | $1,000.00 |
| 1340 | Barcode sign inventory | EACH A A | 124 | $46.06 | $20.00 |
| 1350 | Pole 80 FT MTG HT high mast | EACH A A | 10 | $36,600 | $36,600 |
| 1360 | Pole 120 FT MTG HT high mast | EACH A A | 4 | $58,458 | $58,458 |
| 1370 | Lighting control equipment | EACH A A | 2 | $25,000 | $25,000 |
| 1380 | Conduit-3 in | LF A A | 3,100 | $19.00 | $19.00 |
| 1390 | Marker | EACH A A | 17 | $780.00 | $780.00 |
| 1400 | Trenching and backfilling | LF A A | 6,800 | $15.25 | $15.25 |
| 1410 | Remove lighting | LS A A | 1 | $39,000 | $39,000 |
| 1420 | Electrical junction box type A | EACH A A | 4 | $3,700.00 | $3,700.00 |
| 1430 | Electrical junction box type C | EACH A A | 7 | $3,500.00 | $3,500.00 |
| 1440 | Bore and jack conduit | LF A A | 3,100 | $4.50 | $4.50 |
| 1450 | Pole base-high mast | CUYD A A | 132 | $1,980.00 | $1,980.00 |
| 1460 | High mast LED luminaire | EACH A A | 64 | $2,600.00 | $2,600.00 |
| 1470 | Cable-no. 10/3C ducted | LF A A | 14,200 | $5.25 | $5.25 |
| 1480 | Mobilization | LS A A | 1 | $555,589 | $805,000 |
| 1490 | Demobilization | LS A A | 1 | $313,503 | $247,132 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.